HomeMy WebLinkAbout11690 ORD - 09/12/19730 JRR :vp:9/12/73 •
AN ORDINANCE
AUTHORIZING EXECUTION OF CHANGE ORDER NO. 1 TO THE
CONTRACT WITH ASPHALT MAINTENANCE COMPANY, INC., FOR
CONSTRUCTION OF 15TH, 18TH, ESPINOSA AND DOLORES
STREET IMPROVEMENTS AND STORM SEWER. IMPROVEMENTS,
SAID CHANGE ORDER TO INCLUDE STREET AND STORM SEWER
IMPROVEMENTS TO 17TH STREET FROM ELIZABETH TO THE
CROSSTOWN EXPRESSWAY, TO ELIZABETH STREET FROM
17TH TO 18TH STREET, AND TO PRESCOTT STREET FROM
17TH TO 18TH STREETS; APPROPRIATING OUT OF NO. 220
STREET BOND FUND $77,000 OF WHICH $73,640 IS FOR THE
CHANGE ORDER AND $3,360 IS FOR CONTINGENCIES AND
INCIDENTAL EXPENSES, ALL APPLICABLE TO PROJECT NO.
22o -67 -92.9; AND DECLARING AN EMERGENCY.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF CORPUS CHRISTI,
TEXAS:
SECTION 1. That the City Manager be, and he is hereby, authorized
to execute Change Order No. 1 to the contract with Asphalt Maintenance
Company, Inc., for construction of 15th, 18th, Espinosa and Dolores Street
Improvements and Storm Sewer Improvements, said Change Order to include
street and storm sewer improvements to 17th Street from Elizabeth to the
Crosstown Expressway, to Elizabeth Street from 17th to 18th Street, and to
Prescott Street from 17th to 18th Streets, copy of which, marked Exhibit "A ",
is attached hereto and made a part hereof.
SECTION 2. There is hereby appropriated out of No. 220 Street
Bond Fund $77,000, of which $73,640 is for the Change Order and $3,360 is
for contingencies and incidental expenses, all applicable to Project No.
220 -67 -92.9•
SECTION 3. The necessity to authorize the aforesaid Change Order
in order that the construction may proceed without delay on the above named
streets creates a public emergency and an imperative public necessity requiring
the suspension of the Charter rule that no ordinance or resolution shall
be passed finally on the date of its introduction but that such ordinance
or resolution shall be read at three several meetings of the City Council,
and the Mayor having declared such emergency and necessity to exist, and
having requested the suspension of the Charter rule and that this ordinance
be passed finally on the date of its introduction and take effect and be
C:
in full force and effect from and after its passage, IT IS ACCORDINGLY SO
ORDAINED, this the . day of September, 1973.
ATTEST:
City Secretary
APPROVED:
/ § DAY OF SEPTEMBER, 1973:
C y
'Att ney
•
MAY a:'n==z �:?�4�'/
THE CITY OF CORPUS CHRISTI, TERAS
•
CHANGE CEDER
Engineering Services.Ileparfinent
. Engineering Division
City of Corpus Christi, Texas
Change Order No. I Project No. 220 -67 -92.9
Operating Department Engineering & Physical Development Date September 6. 1973
Name of Project 15th, 18th and Espinosa Street Improvements
Contractor Asphalt Maintenance Company, Incorporated
CHANGE
See attached sheet
was this
specifications,
Portions of Prescott. Elizabeth & 17th Streets were added to the project
How can similar changes be avoided in the future? unavoidable
Contract Price S374,224.30
This Change Order 73.640.00
New Contract Price 447864.30
Amount Appropriated $472.000.00
CITY OF CORPUS CHRISTI, S
By L . a
irector df En nee ing Services
AP VED City Manager
City Attorney
Dir. of Finance
•
ADD DEDUCT
,116.06 $18,476.06
Chief Engineer
CONTRACTOR
Hy 1
Title
NOTE: Contractor, please sign one copy
and return it to the Director of
Engineering Services.
Rev. 6 -71
15th, 18th and Espinosa
Street Improvements
1161
NO.
YGJ U1l1C11 V1V Vl Uf]H1VIa6J - %JUHIILLLnal UAL10
AND UNIT PRICES
Y&UN .. 11V
CONTRACT PRICE
1- 1 far. L.
CONTRACT PRICE
Elizabeth, 17th & Prescott Street Imps.
1.
Add Excavation - 7,383 SY @ $1.15 /SY
$ 8,490.45
2.
Add Caliche - 22382 CY @ $4.50 /CY
10,719.00
3.
Add Prime Coat - 890 Gal. @ $0.30 /Gal.
267.00
4.
Add Hot -Mix Type "D" 1" - 6,260 SY @ $0.80 /SY
5,008.00
5.
Add Curb & Gutter - 3,414 IF @ $2.55/LF
8,705.70
6.
Add Sidewalk 4' & 5' - 13,482 SF @ $0.70 /SF
9,437.40
7.
Add Concrete Driveways - 6,938 SF @ $1.15 /SF
7,978.70
8.
Add Inlets 5' - 11 ea. @ $375.00/Ea.
4,125.00
9.
Add Manholes Type "A" - 5 ea. @ $375.00/Ea.
1,875.00
10.
Add Reinforced Concrete Pipe 24" - 336 IF
@ $12.38/LF
4,159.68
11.
Add Reinforced Concrete Pipe 21" - 487 IF
@ $11.20 /LF
5,454.40
12.
Add Reinforced Concrete Pipe 18" - 72 IF
@ $10.47 /LF
753.84
13.
Add Reinforced Concrete Pipe 15" - 269 IF
@ $8.61 /LF
2,316.09
14.
Add Reinforced Concrete Pipe 30" - 309 IF
@ $16.98/LF
5,246.82
Revision of 18th Street Storm Sewer
15. Delete Inlet 5' - 2 ea. @ $375.00/Ea.
16. Delete Manholes Type "A" - 1 Ea. @ $375.00/ea.
17. Delete Reinforced Concrete Pipe 42" - 44 IF
@ $23.55/Ea.
18. Delete Reinforced Concrete Pipe 27" - 537 IF
@ $13.70 /LF
19. Delete Reinforced Concrete Pipe 24" - 301 IF
@ $12.38/LF
20. Delete Reinforced Concrete Pipe 18" - 26 IF
@ $10.47 /LF
21. Delete Reinforced Concrete Pipe 15" - 576 IF
@ $8.61 /LF
22. Add Reinforced Concrete Pipe 36" - 44 IF
@ $20.26/LF
23. Add Reinforced Concrete Pipe 33" - 866 IF
@ $18.62/LF
24. Add Reinforced Concrete Pipe 18" - 34 IF
@ $10.47 /LF
25. Add Reinforced Concrete Pipe 15" - 24 IF
@ $8.61 /LF
Change in Contract Price Due to this Change
Order:
Total Decrease
Total Increase
Net (increase) (deepease� contract price
$ 750.00
375.00
1,036.20
7,356.90
3,726.38
272.22
4,959.36
$18,476.06
891.44
16,124.92
355.98
206.64
$92,116.06
73,640.00
Corpus Christi, Texas
day of , 19—L4
TO THE MEMBERS OF THE CITY COUNCIL
Corpus Christi, Texas
For the reasons set forth in the emergency clause of the foregoing
ordinance, a public emergency and imperative necessity exist for the suspen-
sion of the Charter rule or requirement that no ordinance or resolution shall
be passed finally on the date it is introduced, and that such ordinance or
resolution shall be read at three meetings of the City Council; I, therefore,
request that you suspend said Charter rule or requirement and pass this ordi-
nance finally on the date it is introduced, or at the present meeting of the
City Council.
Respectfully,
6�2�
MAYOR
THE CITY OF CORPUS CHRISTI, TEXAS
The Charter rule was suspended by the following vote:
Jason Luby Q�.n
James T. Acuffti
Rev. Harold T. Branch
Thomas V. Gonzales
Ricardo Gonzalez
Gabe Lozano, Sr.
J. Howard Stark /fir,..
The above ordinance was passed by the following vote:
Jason Luby
James T. Acuff
Rev, Harold T. Branch
Thomas V. Gonzales
Ricardo Gonzalez AA-
Gabe Lozano, Sr.
J. Howard Stark