A RESOLUTION
ADOPTING A PRELIMINARY PROJECT SCHEDULE IN CONNECTION
WITH EACH OF THE FOUR SANITARY SEWER PROJECTS AS FOLLOWS:
1. Oso Treatment Plant System, WPC -TEX =1214,
2. Flour Bluff System, WPC -TEX -1215,
3., Broadway Treatment Plant System., WPC - :TEX -1216, and
4. Westside Treatment Plant System, WPC- TEX -1217,
A COPY OF EACH SCHEDULE BEING ATTACHED HERETO, MARKED
EXHIBITS "A", "B ", "C ", AND "D ", RESPECTIVELY, AND MADE
A PART HEREOF, SAID PROJECT SCHEDULES BEING REQUIRED IN
CONNECTION WITH THE SUBMISSION OF GRANT APPLICATIONS
FOR FINANCIAL ASSISTANCE UNDER THE FEDERAL WATER POLLU-
TION CONTROL ACT AMENDMENT OF 1972, PUBLIC LAW NO. 92 -500;
AND DECLARING AN EMERGENCY.
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF CORPUS CHRISTI,
TEXAS:
SECTION 1. There is hereby adopted a preliminary project schedule
in connection with each of the four sanitary sewer projects as follows:
1. Oso Treatment Plant System, WPC -TEX -1214,
2. Flour Bluff System, WPC -TEX -1215,
3. Broadway Treatment Plant System, WPC- TEX - 121.6, and
4. Westside Treatment Plant System, WPC -TEX -1217,
a copy of each schedule being attached hereto, marked Exhibits "A ", "B ",
"C ", and "D ", respectively, and made a part hereof, said project schedules
being required in connection with the submission of grant applications for
financial assistance under the Federal Water Pollution Control Act Amendment
of 1972, Public Law No. 92 -500.
SECTION 2. The necessity to adopt the preliminary project schedule
in connection with the aforesaid sanitary sewer projects, as required in
connection with the submission of grant applications as aforesaid, creates
a public emergency and an imperative public necessity requiring the suspen-
sion of the Charter rule that no ordinance or resolution shall be passed
finally on the date of its introduction but that such ordinance or resolu-
tion shall be read at three several meetings of the City Council, and the
Mayor having declared such emergency and necessity -to exist, and having
/a7 q(
requested the suspension of the Charter rule and that this ordinance be
passed finally on the date of its introduction and take effect and be in
full force and effect from and after its passage, IT IS ACCORDINGLY SO
RESOLVED, this the &1�day of September, 1975.
ATTEST:
�ys t MAYOR
THE CITY OF CORPUS CHRISTI, TEXAS
MDAP VED:
DAY OF SEPTEMBER, 1975:
City Attorney
i
OSo SYSTEM
4I11C -TEX -1214
General Information Date
Availability of applicant's Step 1- Sept. 1974
share of project costs Step 2 Sept.
Step 3 FThen needed
Availability of ,site (s) for July 1976
project facilities
Project Schedule
Item Calendar nays
step 1
A. Infiltration /Inflow Analysis
(with Evaluation Survey Plan
of Study if required).
Report completed & submitted to State 300 days
after. stop 1 grant award.
B.� Infiltration /Inflow Evaluation
Survey (if required)
Report completed & submitted to State 300 days
after grant amendment for
Survey -
C.' Environmental Assessment
(including time for draft
report, advertisement, & hearing)
Final report completed & submitted to State_ 54o days
after Step 1 grant alloard_
D. Facility Plan
Report completed & submitted to State -24o days
after EPA approval of S/i
Analysis & I/I Survey (if ,
required).
Step 2
Final Flans and Specifications
completed and submitted to State 210 days.
after Step 2 grant" aL ard.
X/-(, "/�
Step 3
Advertise for Construction Bids
within the days indicated after
authorization to advertise for
bids has been issued
Submit Bid Opening Documents
i•:ithin the days indicated after
the bid opening date
Award of Construction Contract
within the days indicated after
authorization to award the
contract has been issued
Initiation of construction
within the days indicated after
the award of the contract
Complete Construction -
within'the days indicated after
initiation of construction
30 days
14 days
14 days
30' days
730 days
IFLDUR BLUFF SYSTMI
WPC -TEX -1215
General Information Date
Availability of applicant's Step I. Sept. 1974
share of project costs Step 2 When needed
Step 3 When needed
Availability of,site(s) for
project facilities Immediately
Project Schedule
Item. Calendar Days
Step 1
A. Infiltration /Inflow Analysis
(with Evaluation Survey Plan
of Study if required).
Report completed & submitted to State 21D clays
after Step I grant award.
(Actually submitted 8/18/75)
13 -� Infiltration /Inflow Evaluation --
- Survey (if required)
Report completed & submitted to State go days
after grant amendment for
Survey.
C_' Environmental Assessment
lincluding time for draft
report, advertisement, & hearing)
Final report completed & submitted to State 16o days
after Step 1 grant award_
D. Facility Plan
Report completed & submitted to State 150 days
after EPA approval of I/I
Analysis & I/I Survey (if
required).
Step 2
Final Plans and Specifications
completed and submitted to State i8o days
after Step 2 grant' award.
Step 3
Advertise for Construction Bids
_within the days indicated after
authorization to advertise for
bids has been issued
Submit Bid Opening Documents
within the days indicated after
the bid opening date
Award of Construction Contract
within the days indicated after
authorization to award the
contract has been issued
Initiation of Construction
within the days indicated after
the award of the contract
Complete Construction
within'the days indicated after
initiation of construction
9
30 days
14 days
14 days
30- days
450 days
BROADWAY SYSTEM
WPC -TEX -1216
General Information Date
Availability of applicant's step 1 Sept. 1974
share of project costs Step 2 Sept. 197
Step 3 Sept. 197+
Availability of,site(s) for
project facilities July 1976
Project Schedule
Item Calendar Days
Step 1
A. Infi-.ltration /Inflow Analysis
(with Evaluation Survey Plan
of Study if required).
Report completed & submitted to State 240 clays
after Step I. grant award.
• (Actually submitted 8/7/75)
B. Infiltration /Inflow Evaluation
Survey (if required)
Report completed & submitted to State 365 days
after grant amendment for
Survey.
C. Environmental Assessment
(including time for draft
report, advertisement, & hearing)
-Final report completed & submitted to State 45o days
after Step 1 grant award.
D. Facility Plan -
Report completed & submitted to State 210 days
after EPA approval of I/I
Analysis '& I/I Survey (if ,
required)_
Step 2
Final Flans and Specifications
completed and submitted to State 330 days.
after Step 2 grant' award.
hx /j �„
Step 3
Advertise for Construction Bids
within the days indicated after
authorization to advertise for
bids has been issued
Submit Bid Opening Documents
within the clays indicated after
the bid opening date
Award of Construction Contract
within the days indicated after
authorization to award the
contract has been issued
initiation of Construction
within the,days indicated after
the award of the contract
Complete Construction
within *the days indicated after
initiation of construction
30
days
14
days
14
days
30 •
days
550
days
WESTSIDE SYSTEM
WPC-TEX -1217
General Information Date
Availability of applicant's Step 1 Sept, 1974
share of project costs Step 2 When needed
Step,3 When needed
-}availability of .site (s) for Immediate (Existing site)
project facilities
Project Schedule
Item Calendar nays
Step 1
A. Infiltration /Inflow Analysis
(with Evaluation Survey Plan
of Study if required).
Report completed & submitted to State 240 days
after. Step 3. grant award.
(Actually submitted 8/7/75)
T3.~ Infiltration /Inflow Evaluation
Survey (if required)
Report completed & submitted to State 365 days
after grant amendment for
Survey.
C.', Environmental Assessment
(including time for draft
report, advertisement, & hearing)
Final report completed & submitted to State 450 days
after Step 1 grant award.
• D. _ Facility Plan
Report completed & submitted to State 210 days
after EPA approval of I/I
Analysis & I/I Survey (if ,
required)_
Step 2
Final Plans and Specifications
completed and submitted to State 300 days
after Step 2 grant' award.
Step 3.
Advertise for Construction Bids
within the days indicated after
authorization to advertise for
bids has been issued
Submit Bid Opening Documents
within the days indicated after
the bid opening date
Award of Construction Contract
within the days indicated after
authorization to award the
contract has been issued
initiation of construction
within the days indicated after
the award of the contract
Complete Construction
within the days indicated after
initiation of construction
30 days
14 days
14 days
30- days
450 days
CORPUS CHRISTI TEXAS
ILL- OF �9L
TO THE MIEM3ERS OF THE CITY COUNCIL
CORPUS CHRISTI TEXAS
FOR THE REASONS SET FORTH IN THE EMERGENCY CLAUSE OF THE FOREGOING
ORDINANCES A PUBLIC EMERGENCY AND IMPERATIVE NECESSITY EXIST FOR THE SUSPEN-
SION OF THE CHARTER RULE OR REQUIREMENT THAT NO ORDINANCE OR RESOLUTION SHALL
BE PASSED FINALLY ON THE DATE IT IS INTRODUCED, AND THAT SUCH ORDINANCE OR
RESOLUTION SHALL BE READ AT THREE MEETINGS OF THE CITY COUNCILS I, THEREFORE,
REQUEST THAT YOU SUSPEND SAID CHARTER RULE OR REQUIREMENT AND PASS THIS ORDI-
NANCE FINALLY ON THE DATE IT IS INTRODUCED, OR AT THE PRESENT MEETING OF THE
CITY COUNCIL.
RESPECTFULLY
` I
MAYOR
CITY OF CORPUS CHRISTI, TEX S
THE CHARTER RULE WAS SUSPENDED BY THE FOLLOWING VOTE:
JASON LUBY
OR. BILL TIPTON
EDUARDO DE ASES aL
RUTH GILL
BOB GULLEY
GABE LOZANO, SR.
EDWARD L. SAMPLE