HomeMy WebLinkAboutC2020-025 - 1/17/2020 - NA CITY OF CORPUS CHRISTI
AMENDMENT NO. 4
CONTRACT FOR PROFESSIONAL SERVICES
The City of Corpus Christi,Texas, a Texas home-rule municipal corporation ("City")and Freese and Nichols,Inc.
("Consultant"), agree to the following amendments to the Contract for Professional Services for Everhart Road
from SPID to Holly Road (Project No. 18014A):
Original Contract June 12, 2018 Resolution No. 031445 $823,700.00
Amendment No. 1 February 13, 2019 Administrative Approval $49,969.00
Amendment No. 2 April 8, 2019 Administrative Approval $48,493.00
Amendment No. 3 July 24, 2019 Administrative Approval $11,740.00
In the Original Contract, Exhibit "A", Section I. Scope of Services shall be amended as set forth in the attached
Amendment No. 4, Exhibit "A".
In the Original Contract,Article III Compensation shall be amended based on the modified scope of services in the
attached Amendment No. 4, Exhibit "A" for a fee not to exceed $49,972.00, for a total restated fee not to exceed
$983,874.00.
All other terms and conditions of the June 12, 2018 Contract for Professional Services between the City and
Consultant,and of any amendments to that contract,which are not specifically addressed herein shall remain in full
force and effect.
CITY OF CORPUS CHRISTI E E A ICHO jINC.
#1.. 1/10/2020
Michael Rodriguez Date R n Guzm n . .
, 44s. Date
Chief of Staff PrincipalNice President
800 N. Shoreline Blvd., Suite 1600N
Corpus Christi, TX 78401
APPROVED AS TO LEGAL FORM (361) 561-6500
Aimee Alcorn-Reed rg@freese.com
2020.01.13 08:29:20-06'00'
Assistant City Attorney Date
Fund Name Accounting Unit Account Activity Amount
Street B Corp 3250-051 550950 18014-A-3250-EXP_ $15,357.00
Water 2012A RVBD 4089-041 550950 18014-A-4089-EXP 21,247.00
Wastewater 2013 RVBD 4252-042 550950 18014-A-4252-EXP 13,368.00
Total $49,972.00
SCANNED
Innovative approaches
mfivRKEHE0SLEs Practical results
Outstanding service
800 N.Shoreline Blvd.,Suite 1600N • Corpus Christi,Texas 78401 • 361-561-6500 • fax 361-561-6501 www.freese.com
October 28, 2019
Mr.Jeff Edmonds, P.E.
Director of Engineering Services
City of Corpus Christi _
P. O. Box 9277
Corpus Christi,Texas 78469-9277
Re: Everhart Road—Holly Road to South Padre Island Drive-Amendment No.4
City Project No. 18014A
Dear Mr. Edmonds,
Freese and Nichols, Inc. (FNI) is pleased to submit an amendment to our professional services contract to
provide additional construction administration phase and ROW acquisition services for the Everhart Road—
Holly Road to South Padre Island Drive, City Project 18014A for your consideration. This amendment will
include the following services:
1. Construction Administration Phase
a. Provide additional construction phase services
i. 36"water line support to include RFI responses and numerous submittal reviews
ii. Additional construction site visits to support installation of 36"waterline and all
associated appurtenances
b. Prepare additional traffic control drawings to support the contractor modified phasing,
wastewater bypass plan and AEPs relocation of power poles
c. Additional meetings
i. Weekly progress meetings
ii. Planning meetings with City and contractor
2. ROW Acquisition Survey
a. Provide additional ROW acquisition survey for up to two(2)additional sidewalk easement parcels
on Everhart Road near SPID
b. Provide a revised metes and bounds and exhibit for a parcel at Everhart and Bonner intersection
Summary of Fees
Basic Services Fees
1. Construction Administration Phase—Time and Materials $44,363
Additional Services Fees
2. ROW Acquisition Survey $5,609
TOTAL $49,972
AMEND. NO. 4
Exhibit"A"
Page 1 of 2
•
Freese and Nichols, Inc. respectfully requests a not to exceed fee in the amount of$49,972 to perform
these services.
Please feel free to contact me at 361.561.6500 should you have any questions regarding this matter.
Respectfully,
T2 (....)etiz.
Ron Guzman, P.E.
Principal/Vice President
AMEND. NO. 4
Exhibit"A"
Page 2 of 2
Everhart Road from SPID to Holly Road
Project No. 18014A
Summary of Fees
Original Contract Amendment No. 1 Amendment No. 2 Amendment No. 3 Amendment No. 4 Total
Basic Services _ . •
1 Preliminary Phase $106,851.00 $0.00 $0.00 $0.00 $0.00 $106,851.00
2 Design Phase 387,114.00 49,969.00 27,088.00 0.00 0.00 464,171.00 ,
3 Bid Phase 17,770.00 0.00 0.00 11,740.00 0.00 29,510.00 .
4 Construction Administration Phase 50,000.00 0.00 0.00 0.00 44,363.00 94,363.00
(Time and Materials)
Subtotal Basic Services 561,735.00 49,969.00 27,088.00 11,740.00 44,363.00 694,895.00
Additional Services
1 Permit Preparation 12,527.00 0.00 0.00 0.00 0.00 12,527.00
2 Topographic Survey 53,763.00_ 0.00 0.00 0.00 0.00 53,763.00
3 ROW Acquistion Survey 17,315.00 0.00 0.00 0.00 5,609.00 22,924.00
4 Environmental Issues TBD 0.00 0.00 0.00 0.00 0.00
5 Public Meetings 15,874.00 0.00 9,896.00 0.00 0.00 25,770.00
6 Construction Observation Services TBD 0.00 0.00 0.00 0.00 0.00
7 Traffic Control 98,507.00 0.00 0.00 0.00 0.00 98,507.00
8 Signalization Improvements 57,096.00 0.00 11,509.00 0.00 0.00 68,605.00
9 Warranty Phase 6,883.00 0.00 0.00 0.00, 0.00 6,883.00
Subtotal Additional Services 261,965.00 0.00 21,405.00 0.00 5,609.00 288,979.00
Total Authorized Fee $823,700.00 $49,969.00 $48,493.00 $11,740.00 $49,972.00 $983,874.00
06/12/18 02/13/19 04/08/19 07/24/19
Res. 031445 Admin. Appproval Admin. Appproval Admin. Appproval Admin. Approval