:�. ; CITY OF CORPUS CHRISTI
1
• Wr AMENDMENT NO. 2
1 ,
CONTRACT FOR PROFESSIONAL SERVICES
ssZ
The City of Corpus Christi,Texas, hereinafter called"CITY,"and HDR ENGINEERING,INC.,hereinafter
called "CONSULTANT," agree to the following amendment to the Contract for Professional Services
Leopard Street(Palm Drive to Nueces Bay Blvd.) Bond 2018 (Project No. 18027A)) as authorized
and administratively amended by:
Original Contract July 18, 2018 Administrative Approval $49,935.00
Amendment No. 1 August 21. 2018 Motion No. M2018-140 , $526,664.50
IN THE ORIGINAL CONTRACT, EXHIBIT A, SCOPE OF SERVICES, shall be modified as shown in
the attached Exhibit A.
IN THE ORIGINAL CONTRACT, COMPENSATION shall be modified as shown in the attached Exhibit
A.for an additional fee not to exceed $27.711.00 for a total restated fee not to exceed$604,310.50.
All other terms and conditions of the August 21,2018 contract between the"CITY"and"CONSULTANT"
and of any amendments to that contract which are not specifically addressed herein shall remain in full
force and effect.
CITY OF CORPUS CHRISTI HDR ENGINEERING, INC.
?ki ../.4,.-- - I/- ,Z• / - • : . . /.,Vo• 2a
r
Michael Rodriguez Date Arthur B. Colwell, P.E. Date
Chief of Staff Vice-President/Office Principal
555 N. Carancahua--Suite 1600
Corpus Christi,TX 78401-0849
361/696-33000ffice '
samuel.saldivar@hdrinc.com
APPROVED AS TO FORM
2020.02.04 I`
09:30:56 -06'00'
Legal Department f Date
Accounting
Fund NameUnit ' Account No. ~ Activity No. Amount
Streets 3556-051 550950 18027-A-3556-EXP $13,855.50
Gas 4561-022 550950 18027-A-4561-EXP $13,855.50
Total $27,711.00
SCANNEd
November 14, 2019 10018658
Mr. Jeff H. Edmonds, P.E., Director of Engineering Services
City Of Corpus Christi
1201 Leopard Street
Corpus Christi, TX 78401
RE: Amendment 2 Leopard Street— Bond 2018 (Project No. 18027A)
Dear Mr. Edmonds,
HDR is requesting an amendment for the Leopard Street project from Nueces Bay Blvd. to Palm
Drive. The amendment request addresses unforeseen scope of services for gas line design efforts
and additional utility coordination efforts. We have been communicating with the City PM and
tracking these impacts.
Gas Line Design
HDR coordinated with the Engineering Services and the Gas Department during the development
of the feasibility report. The Gas Department indicated that the gas lines (parallel lines on either
side of Leopard) were behind the street's curb lines and in decent shape due to the lack of incident
reports and therefore would not need to be relocated/replaced. HDR submitted the Final Leopard
(Bond 2018) Feasibility report in June 2018 which recommended no gas line improvements. HDR
revisited the Gas Department during the ELR development and confirmed their recommendation to
defer gas line improvements to a future date. Therefore, the Final ELR was submitted in February
2019 which recommended no gas line improvements. During the 60% design phase, it was
discovered that gas line would have minimal clearances at the cross streets. The Gas Department
elected to replace all the gas mains within the project limits in March 2019. Engineering Services
concurred with the Gas Department, and HDR made modifications to the utility plan sheets and
cross street designs to accommodate the new gas lines. HDR analyzed an alignment that would
accommodate with all existing utilities and proposed improvements/utilities.
Utility Coordination
HDR's utility coordinators initially sent out notification letters to potential private utility owners within
the project limits. One of the utility owners, Fiberlight, confirmed with a response letter they had no
infrastructure within the project limits. During the 60% design phase, AT&T discovered a fiber line
in their duct bank which did not belong to them. Fiberlight acknowledged ownership after this
hdrinc.com
555 N.Carancahua,Suite 1600,Corpus Christi,TX 78401-0849
(361)696-3300
AMENDMENT NO.2
EXHIBIT"A"
Page 1 of 3
Mr.J.H.Edmonds,P.E.
Amendment 2 10018658
Leopard Street from Nueces Bay Blvd to Palm Dr(Project No. 18027A)
discovery. AT&T is removing and relocating their duct bank within the project limits and will not
allow Fiberlight to use space in their new duct bank. HDR anticipates the following coordination:
• Update and maintain Utility Communication Log tracking correspondence with utility companies
• Update Existing Utility Layout (add in additional gas lines and Fiberlight lines)
• Identify additional utility conflicts with proposed improvements and constructability of improvements
with labeling corresponding numerical ID
• Display additional potential utility conflicts on Utility Layout
• Update Utility Conflict Matrix identifying each Fiberlight Conflict ID
• Update conflict calculations with pavement/drainage/all improvement design information Including all
prop water, wastewater and storm sewer of additional conflicts from new utilities
• Provide updated Calculation Binder showing evidence of all information used to confirm/ clear EACH
conflict
• Provide updated formal QC of Utility Layout, Conflict Matrix utilizing Calculation Binder
• Upon confirmation of all additional conflicts, work with design team(s) and utility companies to obtain
best solution to resolve each conflict- Design Modifications, or Protect in Place or Relocate facility
• Review all confirmed additional utility conflicts with each utility company and determine best
mitigation of each
• Provide conceptual alignments for both additional facilities needing relocation
• Update Proposed Utility layout
• Assist additional 2 utility companies in the relocation design by providing interim over-the-shoulder
reviews on their relocation design plans to verify clearance of proposed improvements
• Review/ sign-off final relocation plan (Compatibility with road/ drainage improvements, Compliance to
Design Criteria Manual, Utility Accommodations Rules and/ or applicable Regulations,
Constructability, Schedule/ sequencing for Installations, Cutovers and customer outages, removal/
abandonment of old facilities)
• Provide updated finalized utility layout, conflict matrix and evidence
555 N.Carancahua,Suite 1600,Corpus Christi,TX 78401-0849 Texas P.E. Firm Registration No.754
(361)696-3300
Page 2 of 3
AMENDMENT NO.2
EXHIBIT"A"
Page 2 of 3
Mr.J.H.Edmonds,P.E.
Amendment 2 10018658
Leopard Street from Nueces Bay Blvd to Palm Dr(Project No. 18027A)
Fee
In summary, HDR is requesting Amendment#2 in the lump sum amount of $27,711.00 for a
restated fee not to exceed $604,310.50 as shown in Exhibit C.
If you have any questions, don't hesitate to contact us to discuss further.
Sincerely,
HDR _ENGINEERING, INC.
‘//e/&.,,
Samuel
Samuel Saldivar, Jr, P.E. Arthur B. Colwell, P.E.
Civil Program Leader Vice-President/Office Principal
SSJ/KB
Cc: Sarah West, P.E., City of Corpus Christi
Enclosure:
Exhibit C— Fee Summary
555 N.Carancahua,Suite 1600,Corpus Christi,TX 78401-0849 Texas P.E.Firm Registration No.754
(361)696-3300
Page 3 of 3
AMENDMENT NO.2
EXHIBIT"A"
Page 3 of 3
LEOPARD STREET FROM NUECES BAY BLVD TO PALM DR
CITY PROJECT NO. 18027A
SUMMARY OF FEES
Original Amend - Amend Total
Basic Services: Contract No. 1_ No. 2 Contract
!
1 Preliminary Phase $7,909.00 $79,483.00 $0.00 $87,392.00
2 Design Phase $0.00 $327,770.00_ $27,711.00 $355,481.00,
3 Bid Phase $0.00 $13,463.00 $0.00 $13,463.00
4 Construction Admin Phase $0.00 $48,123.00_ $0.00 $48,123.00
Subtotal Basic Services $7,909.00 $468,839.00 $27,711.00 $504,459.00
Additional Services:
1 Permit Preparation $0.00 $6,564.00_ $0.00 $6,564.00
2 ROW Acquisition Survey $0.00 $0.00 $0.00 $0.00
3 Topographic Survey and Parcel Descriptions $42,026.00 $44,333.00 $0.00 $86,359.00
4 Environmental Issues ___ _ $0.00 TBD $0.00 $0.00
5 Public Involvement $0.00 $4,111.00 $0.00 $4,111.00
5a KCS _ $0.00 TBD $0.00 $0.00
6 Subsurface Utility Investigation $0.00 $0.00_ $0.00 $0.00
7 Construction Observation Services $0.00 TBD $0.00 $0.00
8 Warranty Phase $0.00 $2,817.50 $0.00 $2,817.50
Subtotal Additional Services $42,026.00 $57,825.50 $0.00 $99,851.50
Summary of Fees: ,
Basic Services Fees $7,909.00 $468,839.00 $27,711.00 $504,459.00
Additional Services Fees $42,026.00 $57,825.50 $0.00 $99,851.50
Total Authorized Fees $49,935.00 $526,664.50 $27,711.00 $604,310.50
18-Jul-18 21-Aug-18
k Admin Approval M2018-140
AMENDMENT NO.2
EXHIBIT"B"
Page 1 of 1