HomeMy WebLinkAbout033562 ORD - 01/28/2025Ordinance authorizing a Wastewater Trunk Line Construction and
Reimbursement Agreement up to $77,285.28 with MPM Development, LP to
construct a wastewater trunk line related to King's Landing Unit 9
subdivision located north of the Lady Alexa Dr. and Lady Claudia St.
intersection; and authorizing future transfer and appropriation of Water and
Wastewater Trust Fund revenue up to $77,285.28 to reimburse the developer
in accordance with the agreement. (District 3).
WHEREAS, the Developer/Owner, in compliance with the City's Unified Development
Code ("UDC"), has a plat, approved by the Planning Commission on September 20, 2023, to
develop a tract of land, approximately 24.86 acres known as King's Landing Unit 9 Subdivision;
WHEREAS, under the UDC, the Developer/Owner is responsible for the construction of
the 15-inch Wastewater Trunk Line ("Wastewater Improvements");
WHEREAS, under the UDC, the Developer/Owner is eligible for reimbursement of the
Developer/Owner's costs for the construction of Wastewater Improvements;
WHEREAS, it is in the best interests of the City to have the Wastewater Improvements be
constructed to its ultimate capacity under the City's applicable Master Plan;
WHEREAS, the City's participation as Trustee does not create a loan of its credit because
Texas Constitution Article 1.1, Section 3 prohibits the City from becoming a subscriber to the
capital of any private corporation or association, or make any appropriation or donation to the
same, or in anywise loan its credit;
WHEREAS, execution of the Agreement constitutes a promise to pay only to the extent
that the assets and future assets of the trust are sufficient for such purpose and that any
judgement will only be satisfied out of the assets of the trust and not out of the City's assets and
the City is excluded from personal liability;
WHEREAS, the Wastewater Trunk System Trust Fund does not currently have sufficient
funds to fully reimburse Developer/Owner for Wastewater Improvements under the Agreement;
WHEREAS, a construction and reimbursement agreement must be approved by the City
Council before the developer starts construction;
WHEREAS, reimbursement shall only be made when monies are available in and
appropriated from the Wastewater Trunk System Trust Fund;
WHEREAS, the order of the reimbursement will be determined according to the date the
construction and reimbursement agreement is approved by the City Council; and
WHEREAS, if the developer is owed funds from the Wastewater Trunk System Trust Fund
reimbursement shall be made as funds are deposited into the trust fund from other development
and/or, the developer will be given credit for lot or acreage fees that are due on subsequent final
plats filed with the County Clerk per UDC 8.5.3.E.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF CORPUS CHRISTI,
TEXAS, THAT:
SECTION 1. The City Manager or designee is authorized to execute a Wastewater Trunk
Line Construction and Reimbursement Agreement ("Agreement"), attached hereto, with MPM
Development ("Developer"), for the extension of a 15-inch wastewater trunk line, including
all related appurtenances, for the development of King's Landing Unit 9 Subdivision, Corpus
Christi, Nueces County, Texas.
0335,x SCANNED
SECTION 2. In the event of a project delay, the City Manager or designee is authorized to
execute an extension of the agreement for a period not to exceed a period of 24 months.
SECTION 3. The future revenue of the Water Arterial Transmission and Grid Main Trust
Fund, Water Distribution Main Trust Fund, and Wastewater Collection Line Trust Fund are
transferred to the No.4220-21800-777 Wastewater Trunk System Trust Fund until $77,285.28
is appropriated in accordance with Section 4 of this ordinance.
SECTION 4. The City Manager or designee is authorized to appropriate $77,285.28 from the
No.4220-21800-777 Wastewater Trunk System Trust Fund as funds become available to
reimburse the Developer for the wastewater trunk system construction and improvements in
accordance with the Agreement.
SECTION 5. This ordinance takes effect upon passage.
Introduced and voted on the IT 'day�of•JCxnv.
ASSER and APPRO -' on the 30Nlay of
, 2025.
, 2025.
eE T:
becca Huerta, Ci
Paulette Guajardo,ayor
Sec
retary
033562
CITY OF CORPUS CHRISTI
CERTIFICATION OF FUNDS
(City Charter Article IV, Sections 7 & 8)
I, the Director of Financial Services of the City of Corpus Christi, Texas (or his/her duly authorized
representative), hereby certify to the City Council and other appropriate officers that the money
required for the current fiscal year's portion of the contract, agreement, obligation or
expenditure described below is in the Treasury to the credit of the Fund specified below, from
which it is to be drawn, and has not been appropriated for any other purpose. Future payments
are subject to annual appropriation by the City Council.
City Council Action Date: 01 /14/2025 Legistar Number: 24-2090
Agenda Item:
Ordinance authorizing a Wastewater Trunk Line Construction and Reimbursement
Agreement up to $77,285.28 with MPM Development, LP to construct a wastewater
trunk line related to King's Landing Unit 9 subdivision located north of the Lady
Alexa Dr. and Lady Claudia St. intersection; and authorizing future transfer and
appropriation of Water and Wastewater Trust Fund revenue up to $77,285.28 to
reimburse the developer in accordance with the agreement. (District 3).
Amount Required: (Amount to be Certified) $77,285.28
Fund Name
Accounting Unit
Account No.
Amount
Sanitary Sewer Trunk Main
Trust Fund as fund become
available (Future Revenues)
4220-21800-777
540450
$77,285.28
TOTAL
$77,285.28
❑ Certification Not Required
—13,-2oas'