HomeMy WebLinkAboutC2025-216 - 10/22/2025 - NA SIXTH AMENDMENT OF WATER ARTERIAL TRANSMISSION AND GRID MAIN
CONSTRUCTION AND REIMBURSEMENT AGREEMENT
WHEREAS, the Water Arterial Transmission and Grid Main Trust Fund does not currently
have sufficient funds to reimburse the Developer/Owner for Wastewater Improvements fully;
and
WHEREAS, the Developer may be reimbursed when assets of the Wastewater Trunk
System Trust Fund are sufficient, authorized for such purpose, and the Developer/Owner has
priority per UDC §8.5.2. E.
This is an amendment to the Water Arterial Transmission and Grid Main Construction and
Reimbursement Agreement, Document number 2017048024, for Royal Creek Unit 7, originally
dated November 7, 2017, by and between MPM Development, L.P. and the City of Corpus Christi.
NOW, THEREFORE, in consideration of the mutual covenants herein, the Parties agree to amend
the Water Arterial Transmission and Grid Main Construction and Reimbursement Agreement,
Section 5 as follows:
5. DEVELOPER AWARD CONTRACT FOR IMPROVEMENTS
The Developer shall award a contract and complete the improvements to a 12-inch water line
under the approved plans and specifications by November 7, 2026.
All other terms and conditions of the original agreement, with amendments, remain effective and
in full force.
EXECUTED IN ONE ORIGINAL and made effective this 22 day of October , 2025.
OF CORPUS CHR Tl MPM D EL ME T, L.P.
ael Dice Mo es Mostaghasi
Director of Development Services Gene I Partner
APPROVED AS TO FORM:
1444
Buck Brice (Dat
Deputy City Attorney
For City Attorney
SCANNED