HomeMy WebLinkAboutC2026-013 - 2/10/2026 - Approved CITY OF CORPUS CHRISTI
ENGINEERING SERVICES
CHANGE ORDER
VENDOR ID NO.: 117424
PROJECT: Oso WRP Process Upgrades and Breakpoint Chlorination Facility Decommissioning CONTRACT NO.: 5467
CONTRACTOR: CSA Construstion Inc.
ENGINEER: Ardurra Group,Inc.(dab LNV,Inc.) PROJECT NUMBER: 20084A
PROJECT MANAGER: Sandra Gomez CHANGE ORDER NO: 4
OPERATING DEPT.: Water CHANGE ORDER DATE: REV 2/12/26
Make the following additions,modifications or deletions to the work described in the Contract Documents:
ADDITIONS Quantity Unit I Init Price Total
Additional scope of work
PART B-Solids Dewatering Bid.
New B1-674- Replace roofing and decking with similar materials I LS $ 1,910 215.40 $ 1910,215.40
New B 1-675 Substitute Tectum IIIP panels in lieu of metal decking 1 LS $ 90,122.59 $ 80,122 59
New B1-676 Add the replacement of the two rear l0xl0 roll up doors 1 LS $ 24240.51 $ 2424051
New B1-677 Add the replacement of the second-floor office operator sink and cabinet 1 LS $ 19,059.05 $ 19,059.05
Subtotal: $ 2,033,637.55
PART B-AERATED SLUDGE HOLDING TANK
New B 1-373 Aerated Sludge Holding Tank Modifications 1 LS $ 613.039.24 $ 613,039.24
New B1-374 Remove and replace the ADH tank perimeter handrail with new aluminum handrail 1 LS $ 75,311.65 $ 75,31 1.65
Subtotal: $ 688,350.89
PART4-GENERAL
A4 Unantiepated Work Allowance 1 LS $ 800 000.00 $ 800,000.00
Subtotal: $ 800,000.00
Additional Contract Time Due To:Scope of Work 130 DAY $ - $ -
Additions Total: $ 3,521,988.44
DELETIONS Quantity Unit Unit Price Total
N/A
Additional Calendar Days requested 30 NET TOTAL OF THIS CHANGE ORDER: S 3,521,988.44
was this Change necessary:
Council Approved:This change order authorizes payment for are building upper deck and roof reconstruction at the
dewatering building,the replacement of are coarse bubble aeration system in the aerated sludge
holding tank,and an additional allowance for unanticipated construction costs moving forward.
This Contract MOdZfication represents Final Ad)ustinent for any and all amounts due or to become due to Contractor fir changes referred to herein.Contractor further release's all other claims,Lf any
(except those claims previously submitted in writing in shict accordance with the Contract),for additional compensation under this Conhac4 including without limitation any rights Contractor nuiy have
for additional compensation arising out if delays or disruption if Contractor's schedule as may have arisen prior to the date if this Contract Moderation. Unless otherwise expressly provided herein,the
time of cornpletion and all other terms and conditions of the Contract remain unchanged
Original Contract Amount $ 109,890,200.00 Proposed Change Order
Maximum Change Order Contingency Amount(25%) $ 27,472,550.00 Funding Source(s)
Remaining Available Contingency Amount(including this CO) $ 23,950,56156 SECTION/FUND
FUND: 4261-46-89
PreviouslyApproved Change Order Amount $ ACCOUNT: 550910
Proposed Change Order Amount $ 3,521,988.44 for use by CAP ACTIVITY;120084A426(EXP
Revised Contract Amount _ $ 113,412,188.44 for use by CAP AMOUNT;1$3,521 988.44
Percent of Total Change Orders(including this CO) 321
SECTION/FUND
Original Contract Time for Substantial Completion 1465 CD's FUND; n/a
Notice to Proceed Date 6/1 1/2 024 ACCOUNT: n/a
Original Substantial Completion Date 6/15/2028 ACTIVITY; n/a
AMOUNT: n/a
Previously Approved Change Order Time 154 CD's
Additional Time on This Change Order 130 CD's SECTION/FUND
Revised Contract Time for Substantial Completion 1749 CD's FUND: n/a
Revised Substantial Completion Date 3/26/2029 for use by CAP ACCOUNT: n/a
ACTIVITY: n/a
CONTRACTOR AMOUNT: n/a
REQUESTED BY: CSA Construstion Tnc.
SECTION/FUND
02/24/2026 FUND:Ln/aACCOUNT:Rick Mayfield Date ACTIVITY:Pro eectMana er AMOUNT:
CITY OF CORPUS CHRISTI
ENGINEERING SERVICES
CHANGE ORDER
VENDOR ID NO.: 117424
PROJECT: Oso WRP Process Upgrades and Breakpoint Chlorination Facility Decommissioning CONTRACT NO.: 5467
CONTRACTOR: CSA Construstion Inc.
ENGINEER: Ardurra Group,Inc.(dab LNV,Inc.) PROJECT NUMBER: 20084A
PROJECT MANAGER: Sandra Gomez CHANGE ORDER NO: 4
OPERATING DEPT.: Water CHANGE ORDER DATE: REV 2/12/26
Make the following additions,modifications or deletions to the work described in the Contract Documents:
CITY OF CORPUS CHRISTI
02/17/2026 fog atria?Wuwuthu 02/26/2026
REVIEWED BY: APPROVED BY:f�Rat a Pott—thu(Feb 26,tots 1629:01 CST)
Arnulfo Garcia Date Jeff H.Edmonds,P.E. Date
Finance&Resource Manager Director of Engineering Services
70-40ng(J7a'11180),��ng 02/24/2026
RECOMMENDED BY: 9�eogeoggoao�e 7 Deng tFei�za,zoze�o-zosz esr7
Jiangang(Daniel)Deng,Ph.D.,P.E Date
Assistant Director of Constitution Inspection
02/24/2026 M2026-011 initials��s�
J�a iet Whitehead(Feb 24,2026 1026:58 CST) AUthnrlZed Legistrar No.
APPROVED AS TO FORM:
Janet Whitehead Date 2/10/2026
Assistant City Attorney By Council Council Date RHSB
02/24/2026 C,O-yeas 02/27/2026
RECOMMENDED BY: Raeza,zozsissoaecsF7 ATTEST:
Rodolfu(Rudy)Pena Date (Council) Rebecca Huerta Date
Capital Budget Manager (>$100 000.00 or>_25%)City Secretary
Jana Rodriguez
From: Angelica Garza
Sent: Tuesday, February 17, 2026 2:08 PM
To: Jana Rodriguez; CFAGroupConstruction
Cc: Arnulfo Garcia Jr
Subject: RE: (REQUEST FUNDING) 20084A Change Order 4 - OSO WRP Process Upgrades and
Breakpoint Chlorination Facility Decommissioning.
Attachments: 20084A Change Order 4 draft-2.12.26.pdf
Good afternoon,
Please see the funding source and the funding table below.
Funding Sources
Fund-Dept-Org: 4261-46-89
-Account 550910
Project(Activity): 20084A4261 XP
Amount: 3,521,988.44
Funding Taf3le
Part editions Deletions Net
PartA 800,000.00 - 800,000.00
Part B 2,721,988.44 2,721,988.44
TOTAL 3,521,988.44 - 3,521,988.44
PO:
No PO provided since there are no deletions.
Best regards,
A nget;ca'(ja�ird"-
Contracts/Funds Administrator
361-826-3997
Angel icag2(a)-corpuschristitx.gov
cftY op coneus rHaisri Neuli elp with
ENGINEERING � gp"1ic }
SERVISERVICES icumMm-1 a rCenk our
CES iL au�Ramer call crater.
1
AGENDA MEMORANDUM
Action Item for the City Council Meeting of February 10, 2026
DATE: February 10, 2026
TO: Peter Zanoni, City Manager
FROM: Jeff H. Edmonds, P. E., Director of Engineering Services
0effreye(cDco rpuschristitx.aov
(361) 826-3851
Nicholas J. Winkelmann, P.E., Interim Chief Operating Officer
NickWa-corpuschristitx.aov
(361) 826-1796
Sergio Villasana Jr., CPA, CGFO, CIA, Director of Finance & Procurement
sergiov2acorpuschristitx.gov
(361) 826-3227
Construction Chanae Order
Oso Water Reclamation Plant Process Upgrade &
Breakpoint Chlorination Facility Decommissioning
CAPTION:
Motion authorizing the approval of Change Order No. 4 with CSA Construction, Inc., of Houston,
Texas, for the Oso Water Reclamation Plant (WRP) Process Upgrade & Breakpoint Chlorination
(BPC) Facility Decommissioning project located in Council District 4, in an amount of
$3,521,988.44 for a total amount not to exceed $113,412,188.44 which includes $2,033,637.55
for the solids dewatering building upper deck and roof reconstruction, $688,350.89 for the aerated
sludge holding tank modifications to replace the coarse bubble aeration system, and $800,000.00
for unanticipated underground work allowance, with FY 2026 funding available from the
Wastewater Capital Fund.
SUMMARY:
This change order authorizes payment for the building upper deck and roof reconstruction at the
dewatering building, the replacement of the coarse bubble aeration system in the aerated sludge
holding tank, and an additional allowance for unanticipated construction costs moving forward.
BACKGROUND AND PURPOSE:
On March 19, 2024, the City Council awarded a construction contract to CSA Construction, Inc.,
of Houston, Texas, for the Oso WRP Process Upgrade & BPC Facility Decommissioning project.
The project aims to replace the existing BPC facility with a biological ammonia removal treatment
process and provide a third treatment basin. Additionally, it involves modifying the two existing
basins to increase treatment capacity from 16.2 MGD to 18.0 MGD. The scope further includes
rehabilitating or replacing aging infrastructure, such as the blower system, clarification units,
disinfection system, solids dewatering and disposal systems, plant electrical and instrumentation,
yard piping, and other miscellaneous improvements.
The original construction scope included repairing the dewatering building roof via sand-blasting
and the application of a protective coating. However, upon inspection, excessive corrosion was
discovered on the rafters and roof panels. Preliminary pressure washing of a test area resulted in
panel failure, leading to the determination that the roof could not withstand blasting media and
was approaching structural failure. As these improvements constitute the reconstruction of 20% or
more of the building, this change order authorizes the demolition and replacement of the roof,
rafters, and substructure to extend the building's structural life. The work includes replacing man-
doors, windows, and skylights; adding new gutters and downspouts; installing an interior access
ladder and certified lightning protection system; and replacing the second floor and exterior
lighting. The total cost for this work is $2,033,637.55.
Additionally, this change order will replace the existing air-bridge coarse bubble aeration system
in Aerated Sludge Holding Tank #1 with a new floor-mounted coarse bubble system to improve
mixing and minimize solids deposition. This work includes the installation of a bypass system to
dewater the tank, allowing for the demolition of the existing air bridge, handrails, and floor
supports. The cost for this work is $688,350.89.
To mitigate the risk of encountering undocumented or failing infrastructure during excavation, an
additional allowance is proposed to cover potential field discoveries, including unforeseen
conditions dating back to the 1941 plant foundations underground. City staff proposes adding an
$800,000 construction allowance to provide funds for unanticipated underground work. This is
necessitated by unknown buried piping and foundation, which was installed 40-80 years ago, and
the uncertain condition of structures that have remained in continuous use since 1984.
Previous modifications include Change Order 1 (design alterations due to site discrepancies),
Change Order 2 (additional offices and workstation remodeling), and Change Order 3(remodeling
of existing office space).
PROJECT TIMELINE:
Change Order No. 4 will add 130 calendar days to the construction contract. The anticipated
completion date for the project is now March 2029.
ALTERNATIVES:
City Council could choose not to approve Change Order No. 4 with CSA Construction, Inc.
However, without these improvements, the existing roof remains at risk of collapse. Such a failure
would likely damage critical dewatering equipment, resulting in significantly higher repair costs
and extensive operational downtime.
FISCAL IMPACT:
The fiscal impact to Corpus Christi Water in FY 2026 is an amount not to exceed $3,521,988.44,
with funding available from the Wastewater Capital Fund. The cost of change order no. 4 will be
paid using currently budgeted funds. Due to the fact total project costs, inclusive of the change
order, are programmed across a five year horizon, the increased total project cost will be
incorporated into future budget cycles, with corresponding budget adjustments reflected in the FY
2027, FY 2028, and FY 2029 budgets.
FUNDING DETAIL:
Fund: Waste Water 2024 CI (Rv Bds) (Fund 4261)
Department: Wastewater(46)
Organization: Grants &Capital Projects Funds (89)
Project: Oso WRP Process Upgrade& BPC Facility Decommissioning (Project
No. 20084A)
Account: Construction (550910)
Activity: 20084A-4261-EXP
Amount: $3,521,988.44
RECOMMENDATION:
Staff recommend approval of Change Order No. 4 in the amount of$3,521,988.44 for the Oso
WRP Process Upgrade & BPC Facility Decommissioning project with CSA Construction, Inc.
LIST OF SUPPORTING DOCUMENTS:
Location and Vicinity Map
Change Order No. 4
CIP Page
Presentation
CS )nstruction,
Inc. CHANGE ORDER REQUEST
lister Road Houston,TX 77092 No. 027 Rev.02
i,� j -d868 MAIN (713)686-8889 FAX
PROJECT: Corpus Christi OSO WRP Process Upgrades#20084A DATE: 12/31/2025
TO: Attn: Daniel Deng, Ph.D., P.E. JOB: 2402
City of Corpus Christi
4917 Holly Road, Bid. NO 5 CONTRACT NO: 20084A
Corpus Christi, Texas 78411
PAGES INCLUDED: (63)
TITLE: Dewatering Bid. Roof Replacement &Aerated Sludge Holding Tank Modifications
Reference: RFI #089
DESCRIPTION OF PROPOSAL
Dewatering Bid.
Base Bid: Replace roofing and decking with similar materials. New B1-674$1,910,215.40
CSA proposes to demolish and replace the dewatering building roof as per the updated plans and specifications issued
by Ardurra. This work includes but not limited to replacing existing man doors, building windows, skylights, adding new
gutters and down spouts, interior access ladder, roof hatch re-installation, second-floor level and building exterior
lighting replacement and the installation of a certified lightning protection system. CSA will provide temporary
scaffolding over the existing belt presses to allow them to maintain operations.The office and storage room drywall
ceilings will be removed and replaced as well. CSA will maintain access to the belt press master control panel. During this
operation, we will keep the belt presses operational however,these rooms will not be available for operator use and will
need to have the furnishings removed. CSA has not included any labor to remove these furnishings.
Rev.02 This change was due to a conflict between the specifications and plans. The specifications noted the insulation
was to be sloped and the plan details showed two layers of flat insulation. We confirmed the insulation is to be flat as
per the plans.Atlas removed the sloped insulation from their bid to match the plan details. This resulted in a reduced
roofing proposals for both the base bid and alternate#1.
Aerated Sludge Holding Tank Modifications New B1-373$613,039.23
CSA proposes to remove the existing aerated sludge holding tank air bridge course bubble aeration system and replace
with new floor mounted course bubble aeration as per the plans and specifications issued by Ardurra. This work will
include the installation of a temporary bypass system similar to the previously used system when the center wall was
removed from same tank. Once the bypass system is in place, CSA will dewater the holding tank then demolish the
existing air bridges including handrail and floor supports. We will then install the new floor-mounted aeration system
and connect to the existing overhead air header. Included will be sidewalk removal and replacement.The floor mounted
air piping is quoted at 316L, which is their standard, so no alternate will be needed.
CSA reached out to multiple suppliers and subcontractors to try and get more than one bid for work items such as steel
and roofing. These bid totals are shown to the right of the bids we used under the columns labeled "other bids received"
on the attached pricing breakdown worksheets. These other bids are also included in the attached bid documents for
reference.
CS )nstruction,
Inc. CHANGE ORDER REQUEST
lister Road Houston,TX 77092 No. 027 Rev.02
i,� j -d868 MAIN (713)686-8889 FAX
Rev.01 Removed 60 additional days from the Headworks Panel Relocation COR#025 to this COR#027.This will not
change the General Conditions added in this COR#027. The price stays the same.The only change is the added days.
TOTAL Adder:$2,523,254.63 Rev.02 Reduced Price
Rev. 01 TOTAL ADDED DAYS: 70 original+60 from COR#025=130
Alternate#1:Substitute Tectum IIIP panels in lieu of metal decking. New B1-675$80,122.59
This alternate will delete the metal decking and replace it with Tectum IIIP sandwich panels which includes insulation.
The TPA roofing membrane will be on top of the tectum panels.
TOTAL Adder: $80,122.59 Rev.02 Reduced Price
Removing the roof during hurricane season (June 1 through November 1)will render the dewatering building non
hurricane rated during the roof replacement work. This change must be approved December 15th so materials can be
submitted, approved and delivered and work completed before June 1.
Alternate#2:Add the replacement of the two rear 10 x 10 roll up doors. New B1-676$24,240.51
This alternate adds the back two roll up TDI rated doors.These doors are chain hoist operated to match the existing
doors.
TOTAL Adder:$24,240.51
Alternate#3:Add the replacement of the second-floor office operator sink and cabinet. New B1-677$19,059.05
This alternate adds a new cabinet to replace the existing cabinet which is in bad condition and unrepairable.
TOTAL Adder: $19,059.05
Alternate#4: Remove and replace the ASH Tank perimeter handrail with new aluminum handrail. New B1-374
$75,311.66
This alternate will remove the existing perimeter handrail around the aerated sludge holding tank and replace with new
aluminum handrail. If this alternate is not taken there will be gaps in the existing handrail once the bridges are removed.
TOTAL Adder:$75,311.66
If the dewatering building roof replacement is approved the previously approved COR#012, dewatering building
additional ceiling coating,for$17,225 will not be needed.
APPROVAL:
By: By:
Corpus Christi Engineering Dept. Rick Mayfield
Date: Date: 12/03/25
m U
i2
O LO
Z p
❑
�, IIII� IIIIIIIIIIIIII IIII
O m UI
I IIIII�� IIIIIIIIIII IIII
al O N N
NI
0 0 0 0 0 0 0 M 0 0 M O O 0 0 0 0 0 0 t0 O N M
0 0 0 0 0 0 0 L12 0 0 m 0 0 . . .
0 0 0 lD 0 0 T ai V q 9 T 11 tD
t0 C4 O I[]
O N N fD M V O N cD O cfl C 0 V O I�OJ u]cD 1� r V O N at N
FO fD I�fD cD O N Ql au O O O V w O M f N O O N N OO V M
N N N N N
N O O O O O O O M O O M O 0 0 0 0 0 0 f0
O, 0 0 0 0 0 0 0 Lc]0 0 OJ O 0 0 0 CO 0 0 Oi
> 0 0 6 6 cD 6 6 c]6 6 V O 6 6 OJ O 0 I� Y1
N o o c o w o o V o u O o ' O I�'ITO w 1 I� —
� ��i c!](D N cD M V O N c0 O cfl O IS1 V I�of u]l0 Of
(q N N i � ti O O a7�N 61 ro OJ O OJ O M I�O O
O= W O tD t0 M M M O Oi
'R r
O
o ❑
o in u� o in o v m ❑
R �
t ~ Q
N N (•MJ N N OJ O V
tm JI r
u)
O O O 0000O]00 V N I IpppOjp I I I J J J
oo�n00000volno� o onvnoo Q Q Q
N E w'E i N cD N cD M V O N cD O IQ O I.()V I�OJ L T ~ F F
O O
�' 0 0 cD cD M O N OJ M O OJ M O m
LLl
m m
FE N N
En
Uw
U
`o m K
o
_a a 5 1 1 1 1 N I I ISM I I IM I I I �� a ❑
ma ��� aov M OJ W m a6 Z
�a J M N N w 2 O
❑ O m
«`d
F N f/1 N 2 N f/1 N N N N N N N 1 1.4 N N N N N 1 1 1
f6
3cnz
o° o
- ------- -- --- 11------ 111
w c!
�O N� �I
O O
Q#N CJ
N UJ
C w
O �
R � p
V �
� C
.210
1
I O O
❑a
Im U
,Do
S
N W K y U1 'p>> p 0 C U CJ C y Ol C co O
m❑ OO p0 U W (6 N i d L p0-6 N
o ci c o 2am nayLL
g w
-Q O O c6 Y Y N❑ N y fl_ Q1 o Q a O N a 3
3 m V❑ N N O a L51 61 V W O.N ? S
Z m S D O ❑❑ C p a N Q p
aQ W W F m LL == ��K �3a— u.� 'a W u�tq LZ o
Q� W uJw 0CD o p o Sam -'��'� «:(7 pQUQ—_ Noa
U O O W F Y 3 m E E N m mo c_ m �' m m E 3 3 3 m > m
�u7iaa=no- ou) u)ino�incl D ¢inozzz 2 ae¢
O O O O . . . . . . . . i0 O O M M N ctl O i0
cD O O N .
c O O W W W V N Oi uc
N� O O i0i Oi Oi C'1 t"1 1� III W ia0
N IW W W O 01 O YO O IO
O O O O i0 II O i0
O O O O IO I O IO
cD 0 0 N i i i i i i i i i N Ci i i i i i i O
Q O u]
E IW E
Ni O O 7 Im £ Ali W IW
y
W W
� I
N� a i i i i i i i i i i i i i J N i i i i i i
X N X 6 li
O i
a a a i
O O r
LI O N LI
JI JI
a cD O O N I I I I I I a J J n p
lL�D i N W N� Q O O lX li O
m m m
N N N
H
X f6 CI N z X CI
O
H U H
m n
O n
$'EI I I I I I I I I I I I I I c~io a in $'clll
J DI LLIL m z J Ili
Q = O
❑J O m
F N fA N fA I I I I I I I I I I F y
z z
I
NI NI
�I �I
dl �I
I�
Iw
� IQ
C IY
Y IU
IrL-
N O y
C N p a
O
O O to (6 i 0 O 075 :in
a
N a C C y Ia C a N a
0
V in o
d W W U oa � W F
E� ac 0 w �O p ac
m ix m
L
H 0 O a U a
j a i� O m
# 76 m E a `o
X
Q U O O O IQ O a
002K w d'Q I¢ Q~
Signature: Sa" grwtk&KAo- f�
Sarah Brunkenhoefer(Feb 27,2026 09:35:00 CST)
Email: sarahb@corpuschristitx.gov
O O O O co i0 O O O N N O N
O O O O O O 7 11J Ci Oi O Oi O D] Oi
a0 D] O N �� O N �i t'1 t"J � � D] O�
O O M V' N
N N N N i
O O i0
O O 0
vo v
n rn o �N
� �I o 0 0
wU
I
❑ N iN ❑
H i H
0 0 o O �i0 0 0 0
O O O 0 O O
O O 0� ' N ' ' ' ' iN O O
Ji
J J J O O I I I I I J J J
� O O
7 O
Q Q X��i Q Q Q
m m m w m m m
N to to N to to
� a w 2 incoO
� w
O m
m� ~ mcr
o� o�
0
U p a ❑ a'c I not I I I I I U o (L ❑
❑J O m ❑J O m
z
" " IIIII
co
i � � IIIII
cI
dl >
U XO
O })
O —
U L
U
c V)
o�
U C
Ul�
U U 0 U
w _
a U
a c H
ma
c L
Ea U
y 0 (B
w
0 ❑ V)
O 9 _
w U i
Q
LL1
¢a i7n
20084A change order 4 - 2.26.26_
Final Audit Report 2026-02-27
Created: 2026-02-26
By: Jana Rodriguez Qanar@corpuschristitx.gov)
Status: Signed
Transaction ID: CBJCHBCAABAAQba-8FDzjndOZiuiDplQirYOSxwGhrh5
"20084A change order 4 - 2.26.26." History
Document created by Jana Rodriguez Qanar@corpuschristitx.gov)
2026-02-26-9:01:15 PM GMT
Document emailed to Ratna Pottumuthu (ratnap@corpuschristitx.gov) for signature
2026-02-26-9:01:23 PM GMT
Email viewed by Ratna Pottumuthu (ratnap@corpuschristitx.gov)
2026-02-26-10:28:34 PM GMT
A Signer Ratna Pottumuthu (ratnap@corpuschristitx.gov) entered name at signing as for Ratna Pottumuthu
2026-02-26-10:28:59 PM GMT
h Document e-signed by for Ratna Pottumuthu (ratnap@corpuschristitx.gov)
Signature Date:2026-02-26-10:29:01 PM GMT-Time Source:server
Document emailed to Sarah Brunkenhoefer(sarahb@corpuschristitx.gov) for signature
2026-02-26-10:29:18 PM GMT
Email viewed by Sarah Brunkenhoefer(sarahb@corpuschristitx.gov)
2026-02-27-2:29:23 PM GMT
CA' Document e-signed by Sarah Brunkenhoefer(sarahb@corpuschristitx.gov)
Signature Date:2026-02-27-3:35:00 PM GMT-Time Source:server
Document signing automatically delegated to stephanieb2@cctexas.com by Rebecca Huerta
(rebeccah@corpuschristitx.gov)
2026-02-27-3:37:07 PM GMT
Document emailed to stephanieb2@cctexas.com for signature
2026-02-27-3:37:08 PM GMT
Document emailed to Rebecca Huerta (rebeccah@corpuschristitx.gov) for signature
2026-02-27-3:37:09 PM GMT
Adobe Acrobat Sign
Document e-signed by Rebecca Huerta (rebeccah@corpuschristitx.gov)
Signature Date:2026-02-27-3:50:49 PM GMT-Time Source:server
Agreement completed.
2026-02-27-3:50:49 PM GMT
Adobe Acrobat Sign