HomeMy WebLinkAboutC2026-037 - 3/17/2026 - Approved CITY OF CORPUS CHRISTI
ENGINEERING SERVICES
CHANGE ORDER
VENDOR 1D NO.: 159872
PROJECT: New Peoples Street Boardwalk CONTRACT NO.: 5840
CONTRACTOR: SR Trident,Inc.
ENGINEER: Jacobs Engineering Group PROJECT NUMBER: 21027
PROJECT MANAGER: Curtis Weiss CHANGE ORDER NO: 2
OPERATING DEPT.: Park&Recreations CHANGE ORDER DATE: 3/24/2026
Make the following additions,modifications or deletions to the work described in the Contract Documents:
ADDITIONS Quantity Unit Unit Price Total
Scope of work
PART A-GENERAL
A-N6 Standby for Delayed Demolition(RFI#8) 1 LS $ 126,928.00 $ 126,928.00
A-N7 Delays Caused by Underground Debris(Pile Driving)(RFI#19) 1 LS $ 558,638.00 $ 558,638.00
A-N8 Electrical wiring drwaings 1 LS $ 17,613.80 S 17,613.80
Additional Contract Time Due To:Scope of Work 154 DAY $ - $ -
Additions Total: S 703,179.80
DELETIONS Quantity Unit Unit Price Total
N/A
Additional Calendar Days requested 154 NET TOTAL OF THIS CHANGE ORDER: S 703,179.80
Why was this Change necessary:
During the demolition phase of the project,a couple of unforeseen issues arose that caused delays with the project. The first delaywas the discovery of Harrison's Landing's structure being
tied into the city's boardwalk structure.The project was designed with the idea that Harrison's Landing was structurally supported on its own. This caused a redesign of the project which
included corrective measures to separate Harrison's Landing from the city's new boardwalk structure.This redesign also triggered a redesign of the portion of the boardwalk in front of
Harrison's Landing. Once the new design was completed,and the estimate was received from the contractor to build the new structure,afield directive was issued to the contractor bythe
OAR to minimize the financial impact to Harrison's Landing.
While the deck was removed,and during an extremely low tide event,it was also discovered that several large sections of the bulkhead along People Street had spatted and was causing
undermining under the Peoples Street asphalt pavement.It was decided that these areas needed to be repaired while the decking was removed and during the low tide to prevent any serious
undermining that could possibly create sinkhole conditions under Peoples Street. The contractor was issued another field directive by the OAR to pump the voids full of a concrete mixture
and make repairs to the surface of the concrete bulkhead.
Lastly,a major contributing factor to the cost and time delays of this change order is all the unforeseen debris under the mud that the contractor encountered during pile driving operations.
There was a total of 164 concrete piles that had to be driven for the new boardwalk and finger piers and over half of them came into conflict with debris under the mudline. Driving piles is a
time-consuming practice,and each time a pile encountered debris it caused a two-to-three-day delay with driving that pile.Due to these delays,the contractor submitted a change request for
compensation to cover the cost of additional rental equipment and labor cost. Engineering Services negotiated the value of this change request for two months and finally came to an
agreement with the contractor for the final value of this change order.
This Contract Modification represents Final Adjustment for any and all amounts due or to become due to Contractor for changes referred to herein.Contractor further releases all other claims,if
any(except those claims previously submitted in writing in strict accordance with the Contract).for additional compensation under this Contract,including without limitation any rights Contractor
may have for additional compensation arising out of delays or disruption of Contractor's schedule as may have arisen prior to the date of this Contract Modification.Unless otherwise expressly
provided herein,the time of completion and all other terms and conditions of the Contract remain unchanged.
Original Contract Amount $ 5,999,753.60 Proposed Change Order
Maximum Change Order Contingency Amount(25%) $ 1,499,938.40 Funding Source(s)
Remaining Available Contingency Amount(including this CO) $ 702,324.10 SECTION/FUND
FUND: 3271-27-89
Previously Appfoved Change Order Amount $ 94,434.50 ACCOUNT: 550910
Proposed Change Order Amount S 703,179.80 for use by CAP ACTIVITY:121027
Revised Contract Amount S 6,797,367.90 for use by CAP AMOUNT:1$703,179.90
Percent of Total Change Orders(including this CO) 13.29%
SECTION/FUND
Original Contract Time for Substantial Completion 180 CD's FUND:
Notice to Proceed Date 9/2/2024 ACCOUNT: n/a
Original Substantial Completion Date 3/1/2025 ACTIVITY:
AMOUNT:
Previouslv Approved Change Order Time 119 CD's
Additional Time on This Change Order 154 CD's SECTION/FUND
Revised Contract Time for Substantial Completion 453 CD's FUND:
Revised Substantial Completion Date 11/29/2025 for use by CAP ACCOUNT: D/a
ACTIVITY:
CONTRACTOR AMOUNT:
REQUESTED BY: SR Trident,Inc.
SECTION/FUND
03/25/2026 AC FUND:
NT
Jerred King Date ACTIVITY:
Marine Project Manager AMOUNT:
CITY OF CORPUS CHRISTI
ENGINEERING SERVICES
CHANGE ORDER
VENDOR ID NO.: 159872
PROJECT: New Peoples Street Boardwall< CONTRACT NO.: 5840
CONTRACTOR: SR Trident,Inc.
ENGINEER: Jacobs Engineering Group PROJECT NUMBER: 21027
PROJECT MANAGER: Curtis Weiss CHANGE ORDER NO: 2
OPERATING DEPT.: Park&Recreations CHANGE ORDER DATE: 3/24/2026
Make the following additions,modifications or deletions to the work described in the Contract Documents:
CITY OF CORPUS CHRISTI
#wdh lA,7J GaYcta,7Y 03/25/2026 03/25/2026
REVIEWED BI: Ar^uito(AJjcar�,aJr(Mar25,262e1037.18COT) APPROVED BY:
Arnulfo Garcia Date -$100,000.00 Jeff H.Edmonds,P.E. Date
Finance&Resource Manager Director of Engineering Services
ki-- 03/25/2026
RECOMMENDED BY: J-Mph Johnson(Mar 25,2026 11:27:30 CDT)
Joseph Johnson Date
Assistant Director of Construction Inspection
sv�—� 03/25/2026 M2026-022 initials
APPROVED AS TO '^e°" °aa' ar25 °°""""°° Authorized Legistrar No. ('
FORM:Janet Whitehead Date 3/17/2026 �ffUE
Assistant City Attorney By Council Council Date RHSB
t , 03/25/2026 l 03/26/2026
RECOMMENDED BY: R.deMar252026153513CDT) ATTEST: SlephaneBo �
a2026 09 15 39CDT)Rodolfo Pena Date (Council) Rebecca Huerta Date
Capital Budget Manager (>$100,000.00 or>_25%) City Secretary
Funding Sources
Fund-Dept-Org: 3271-27-89
Account: 550910
Project(Activity): 21027
Amount: $ 703,179.80
Funding Table
Part Additions Deletions Net
Part A-General 703,179.80 703,179.80
TOTAL 703,179.80 1 703,179.80
PO.
No PO provided since there are no deductions/deletions.
FY 26 thru FY 28 a
Capital Improvement Plan 11'
Corpus Christi, Texas
-_
Project# 21027
Project Name Peoples Boardwalk
Contact Marina General Manager Department Marina
Type Reconditioning-Asset Category Marina Upgrades
Priority Priority Level 1 Status Active
Useful Life 35 years Council District 7
Description
This project is planned for a new boardwalk for tourists,tenants and the general public.The new boardwalk will include upgraded electrical and
water utilities which will restore stability and safety to this area.The boardwalk will be useful to tenants and safe for all.This project will increase
pedestrian traffic,and will maintain a safe environment for the City'svisitors.
Justification
The existing Boardwalk has exceeded its useful life and requires replacement to meet safety standards and offer useful walkway for tenants,staff
and visitors.
Expenditures Prior FY 26 FY 27 FY 28 Total
Construction/Rehab 8,500,000 0 0 0 8,500,000
Design 439,065 0 0 0 439,065
Eng,Admin Reimbursements 587,028 0 0 0 587,028
Total 9,526,093 0 0 0 9,526,093
Funding Sources Prior FY 26 FY 27 FY 28 Total
Type A Sales Tax-1120 Seawall(2000)PRIOR 9,526,093 0 0 0 9,526,093
Total 9,526,093 0 0 0 9,526,093
Budget Impact
An assessment will be done upon completion of project to determine maintenance costs.
125
- - AGENDA MEMORANDUM
Action Item for the City Council Meeting March 17, 2026
DATE: March 17, 2026
TO: Peter Zanoni, City Manager
FROM: Jeff H. Edmonds, P.E., Director of Engineering Services
0effreye(ab-corpuschristitx.gov
(361) 826-3851
Robert Dodd, Director of Parks and Recreation Department
robertd4(aD-corpuschristitx.aov
(361) 826-3133
Construction Change Order
Peoples Boardwalk
CAPTION:
Motion authorizing Change Order No. 2 with SR Trident, Inc., of Gregory, Texas for the Peoples
Boardwalk Project in an amount of $703,179.80 for a total contract amount not to exceed
$6,797,367.90 to address sinkhole conditions under People Street, separation of Harrison's
Landing from the City's Boardwalk structure and removal of unforeseen underground debris,
located in Council District 1,with FY 2026 funding available from the Seawall Capital Improvement
Fund.
SUMMARY:
This change order authorizes additional funding and time extension to complete critical boardwalk
infrastructure improvements due to unforeseen site conditions encountered during the
construction phase.
BACKGROUND AND FINDINGS:
On July 30, 2024, the City Council awarded a construction contract to SR Trident, Inc., of Gregory,
Texas, for the Peoples Boardwalk Project, with work commencing in early September. The
project's scope involves the demolition and reconstruction of the existing wooden boardwalk and
finger piers along Peoples Street, extending from Shoreline Boulevard past Harrison's Landing
restaurant to the Peoples Street T-Head.
There are three main contributors that have caused the project to be delayed, with the 1 st issue
arising during the demolition phase when crews discovered that Harrison's Landing structure was
tied into the City's boardwalk. Because the project was designed with the assumption that the
restaurant was structurally independent, a redesign was required to separate the two structures.
This change also necessitated a redesign of the boardwalk section immediately fronting the
restaurant. Once the new design was finalized and cost estimates were received, the Owner's
Authorized Representative (OAR) issued a field directive to the contractor to proceed while
minimizing the financial impact on Harrison's Landing.
The 2nd issue occurred following the removal of the deck during an extremely low tide, when it
was discovered that several large sections of the bulkhead along Peoples Street had spalled,
causing undermining beneath the asphalt pavement. To prevent the formation of sinkholes under
Peoples Street, officials decided to repair these areas immediately while the decking was
removed. The OAR issued a second field directive for the contractor to pump the voids with a
concrete mixture and repair the surface of the concrete bulkhead.
The 3rd issue contributing to the increased costs and timeline was the presence of unforeseen
debris beneath the mudline encountered during pile driving. Of the 164 concrete piles required
for the new boardwalk and finger piers, over half conflicted with submerged debris. Since each
encounter caused a two-to-three-day delay, the contractor submitted a change request for
additional equipment rentals and labor. Following negotiations, Engineering Services reached an
agreement with the contractor on the final value of this change order.
Change Order No. 1 involved the rewiring of existing electrical lines caused by interference from
the installation of new pile caps under the Harrison's Landing structure, along with the repair of
an existing bulkhead found after a low tide event.
SR Trident, Inc. is currently working according to the revised schedule. As the project approaches
completion, approval of the change order is necessary to prevent a work stoppage before the final
delivery.
PROJECT TIMELINE:
Change Order No. 2 will authorize an additional 154 calendar days to the construction contract.
The anticipated substantial completion date of the project is March 23, 2026.
ALTERNATIVES:
City Council could choose not to approve Change Order No. 2. The bulkhead repairs and
unforeseen pile-driving operations were completed to ensure public safety and structural integrity.
However, failing to award this change order would result in non-payment for necessary work, a
halt in construction, and further project delays.
FINANCIAL IMPACT:
The fiscal impact for FY 2026 is an amount of $703,179.80 for a total contract amount not to
exceed $6,797,367.90 with funding available from the Type A Sales Tax Seawall Capital Fund.
Because the original bid was significantly lower the OPCC, project savings are available to absorb
the costs of this change order without requiring additional budget allocation.
FUNDING DETAIL:
Fund: Seawall Sys CIP (Fund 3271)
Department: Economic Development (57)
Organization: Grants & Capital Projects (89)
Project: New Peoples Boardwalk (Project No. 21027)
Account: Construction (550910)
Activity: 21027
Amount: $703,179.80
TOTAL $703,179.80
RECOMMENDATION:
Staff recommends approval of Change Order No. 2 in an amount of $703,179.80 and a time
extension of 154 calendar days for the Peoples Street Boardwalk Project with SR Trident, Inc., of
Gregory, Texas, due to unforeseen site conditions encountered during the construction phase.
LIST OF SUPPORTING DOCUMENTS:
Change Order
Location and Vicinity Maps
CIP Page
COF
Request For Information
21027 Peoples Boardwalk
RFI # 8 Y
Contractor: SR Trident,INC
Contractor Name: Jerred King
RFI Subject: RFI#8 for 21027: Request for Additional Contract Days
Date Submitted: 01.20.2025
RFI Information
Revision Number: 2
RFI Topic: Request for Additional Contract Days
Discipline:
Drawing Number: Specification Section:
Site Number: Delivery Order Number:
RFI Question: SR Trident is requesting the additional of lost contract days to be added to this project. At the preconstruction meeting it was
agreed that we could recoup days lost during the submittal phase until concrete piles could go into production.These days
will not have a financial impact to the project.
Upon completion of demo up to Harrison's landing.SR Trident was asked to delay demo between Harrison's restaurant and
the bulkhead until an approved concrete mix design was in hand and concrete piles were in production.These days will have a
financial impact as equipment/personnel had already been allocated to this project.
RFI Impact
"Impacts to time and/or money will be reviewed after RFI completion via Change Order Request Process"
Potential Cost Impact? Yes Potential Schedule Impact? Yes
RFI Impact Notes: Total of 92 contract days to be added.49 days without financial impact,43 days with financial impact
Contractor's Supporting Documentation:
Responses& Reviewer Details
Engineer of Record
FOR Status: Does Not Require FOR Response
FOR Name: N/A FOR Reviewed Date:
FOR Comments
# Comment Date Comment/Response Supporting Doc? Document Field Name
FOR Supporting Doc 1: FOR Supporting Doc 2:
FOR Supporting Doc 3: FOR Supporting Doc 4:
City Inspector
City Status: Approved Change Order Required? Yes
Inspector Name: Cesar Estrada Date Approved: 02.26.2025
City Comments
# Comment Date Comment/Response Supporting Doc? Document Field Name
1 02.26.2025 Please submit for days requested on form provided.In the form of an Yes
email.
City Supporting Doc 1: Project Change Request Form Time extension.pdf City Supporting Doc 2:
City Supporting Doc 3: City Supporting Doc 4:
Page 1 of 1
Project#:21027 RFI#:8
`N
CHANGE ORDER REQUEST
SRTR DENT .,,,.
This Change Order Request Form is submitted by SRTrident,Inc.to request the following changes.
SRT Job Number: 240129 Purchase Order Number: 21027
Change Order Date: 3/19/2025 Project Name New Peoples Street Boardwalk
Change Order Number: 2 Project Number: 240129
Change Order Type: Owner Project Manager: Curtis Weiss
CHANGE REQUEST INFORMATION
Change Order Scope:
Standbyfor equiupment and personnel:
110 ton crane barge:$1,210/day@ 16 days=$19,360.00
Material Barge:$420/days @ 16 days=$6,720.00
Timber Pile Extractor:$482/day @ 16 days=$7,712.00
Excavator:$354/day @ 16 days=$5,664.00
Tug Boat:$2500/day @ 16 days=$40,000.00
Crew Boat:$1200/day @ 16 days=$19,200.00
6 man barge crew:1,767/day @ 16 days=$28,272.00
Reason for Change:
Directed by City of Corpus construction team to pause demolition between Harrison's Landing and the existing bulkhead.
CHANGE REQUESTIMPACT
Costlmpact: Schedule Impact
Original Order Amount: $ 5,999,753.60 Change Order Amount Includes: Q Tax 1 Q lFreight
Previous Change Orders $ 48,775.00 Schedule Impact Q 1yes 1 ❑ INo
Current Change Order: $ 126,928.00 Current Finish Date:
Revised Total: $ 6,175,456.60 Impact Finish Date:
Schedule Impact Days 43 Revised Schedule Attached: Q 1yes 1 ❑ INo
SUPPORTING DOCUMENTATION&ATTACHEMENTS
List Supporting Documentation and Attachments Attachment
1. Email from City of Corpus with approval for this SOW. Q Yes ❑ No
2 ❑ Yes ❑ No
3 ❑ Yes ❑ No
4 ❑ Yes ❑ No
5 ❑ Yes ❑ No
6 1 ❑ IYes INo
REPRESENTATIVE'S RECOMMENDATION(Completed by Owner)
Recommendation of this Change Order: 10 JAccept I ❑ lReject I lHold
Reason for Reject or Hold
OWNERAUTHORIZED SIGNATURE I ISRTRIDENTINC.REPRESENTATIVE
Authorized Signature: Authorized Signature:
Name: Name: Jer06 King 61
Title: Title: P.M.
Change Order Effective Date: Date: 3/19/2025
Request For Information
21027 Peoples Boardwalk
RFI # 19 Y
Contractor: SR Trident,INC
Contractor Name: Jerred King
RFI Subject: RFI#19 for 21027: Pile Driving Logs&Other Backup Data for SRT CO
Date Submitted: 10.22.2025
RFI Information
Revision Number: 0
RFI Topic: Pile Driving Logs&Other Backup Data for SRT CO
Discipline:
Drawing Number: Specification Section:
Site Number: Delivery Order Number:
RFI Question: RFI for CO document sharing.
RFI Impact
"Impacts to time and/or money will be reviewed after RFI completion via Change Order Request Process"
Potential Cost Impact? Yes Potential Schedule Impact? Yes
RFI Impact Notes:
Contractor's Supporting Documentation:
Responses& Reviewer Details
Engineer of Record
FOR Status: Does Not Require FOR Response
FOR Name: John Garcia FOR Reviewed Date: 01.22.2026
FOR Comments
# Comment Date Comment/Response Supporting Doc? Document Field Name
FOR Supporting Doc 1: FOR Supporting Doc 2:
FOR Supporting Doc 3: FOR Supporting Doc 4:
City Inspector
City Status: Approved Change Order Required? No
Inspector Name: Cesar Estrada Date Approved: 01.26.2026
City Comments
# Comment Date Comment/Response Supporting Doc? Document Field Name
1 01.26.2026 The city agrees with EOR. No N/A
City Supporting Doc 1: City Supporting Doc 2:
City Supporting Doc 3: City Supporting Doc 4:
Page 1 of 1
Project#:21027 RFI#: 19
-N'-i
CHANGE ORDER REQUEST
SRTR DENT, I ,,.
This Change Order Request Form is submitted by SRTrident,Inc.to request the following changes.
SRT Job Number: 240129 Purchase Order Number: 21027
Change Order Date: 8/12/2025 Project Name New Peoples Street Boardwalk
Change Order Number: 7 Project Number: 240129
Change Order Type: Owner Project Manager: Curtis Weiss
CHANGE REQUEST INFORMATION
Change Order Scope:
Additional labor,materials,and additional equipment required to drive piling with the unforeseen site conditions.
Multiple handling of pilings.Setting and resetting templates due to having to dig debris.
Reason for Change:
Increased cost detailed in the"claim for time extension and compensation"
CHANGE REQUESTIMPACT
Cost Impact: Schedule Impact
Original Order Amount: $ 5,999,753.60 Change Order Amount Includes: Q Tax 1 Q lFreight
Previous Change Orders $ 221,362.00 Schedule Impact Q 1yes 1 ❑ INo
Current Change Order: $ 558,638.00 Current Finish Date:
Revised Total: $ 6,779,753.60 Impact Finish Date:
Schedule Impact Days 95 Revised Schedule Attached: Q 1yes 1 ❑ INo
SUPPORTING DOCUMENTATION&ATTACHEMENTS
List Supporting Documentation and Attachments Attachment
1 Submitted with the Claim for Time Extension and Compensation documentation Q Yes ❑ No
2 ❑ Yes ❑ No
3 ❑ Yes ❑ No
4 ❑ Yes ❑ No
5 ❑ Yes ❑ No
6 IYes I INo
REPRESENTATIVE'S RECOMMENDATION(Completed by Owner)
Recommendation ofthis Change Order: 10 JAccept I I Reject I lHold
Reason for Reject or Hold
OWNER AUTHORIZED SIGNATURE I ISRTRIDENTINC.REPRESENTATIVE
Authorized Signature: Authorized Signature:
Name: Name: J ed King
Title: Title: P.M.
Change Order Effective Date: Date: 8/12/2025
SR R DENT, INC.
Inland Marine • Civil • Pipeline • Soft Craft Services* Fabrication • Excavation • Mechanical
Veteran Owned& Operated
DATE: JANUARY
ATTENTION: CURTIS WEISS CITY OF CORPUS CHRISTI
REFERENCE: ADDITIONAL NEUTRAL WIRE REQUIRED
SUBJECT: SR TRIDENT, INC. PROPOSAL LETTER
Mr. Weiss,
On behalf of SR Trident, Inc. We are pleased to offer this proposal letter for your review. In accordance with the
requirements set forth in the bid walk and as outlined below,we have made every effort to capture your request for pricing in its
entirety. Upon your review, please contact me with any questions you may have.
Scope Overview
DESCRIPTION: The cable schedule calls for 2- 1/C 93/0 Awg+94 Awg for a ground to be pulled from Substations 13 & 14 to
each pedestal. The circuit voltage being fed to the pedestals is 240VAC. The pedestals include a 9W photocell, activated LED light,
and a 120VAC receptacle.The light and receptacle will not work properly if a neutral wire is not pulled to the pedestal.A 240VAC
system consists of four wires,two hots,one neutral,and one ground.A 120VAC system consists of three wires,one hot,one
neutral, and one ground.CEC is requesting that an additional neutral wire be pulled
from the substations to each pedestal.
Proposal Pricing Includes:
• All direct and indirect site labor, insurances,overhead, and profit
• Labor, material, consumables, and equipment to perform the above-mentioned activities
• Freight for equipment in/out.
• One mobilization and one demobilization
Proposal Pricing Excludes:
• Any underground item not indicated by the one call
• Scaffolding
• Work stoppages/stand by
• Any decking modification
Proposal Clarifications/Assumptions:
• This proposal is based upon work being released in a manner that allows SR Trident to have continuous work from start
to finish,without any delay.Any delays to the work other than those attributable to SR Trident, Inc. employees,shall be
basis for additional compensation.
• Scope increase or modifications that differ from what is outlined in this proposal letter shall also be basis for additional
compensation.
• Scope increase or modifications to the work shall not begin until an approved change order and/or amended purchase
order has been received by SR Trident, Inc.
Estimated Pricing:
• $17,613.80
P. O. Box 592 0 Portland, Texas 78374 • 361-776-2662 0 fax: 888-980-9575
SR Trident, Inc. Page 2
Price is based on materials and equipment that is readily available. With approval,work for this electrical reroute can
begin immediately.
Duration:
• Procurement—10 days
• Install—6 days
Payment Terms:
• Per contract
Thank you for giving SR Trident Inc. the opportunity to prepare this proposal letter for your review. Please feel
free to contact me directly if you have any questions or comments.
Respectfully Submitted,
SR Trident, Inc.
fevred 'C'OZ5�
Project Manager
0erred.kingCa-srtrident.com
Approved for scope of work, not to exceed the amount of$17,613.80. Contractor may proceed. Any
cost presented for the change will be approved as an allowance, final payment is to be determined upon
completion of work per Article 15 of General Conditions 007200 and receipt of documentation of actual
cost including approved markup. 16 Days will added to the contract.
Cesar Estrada 02-02-2026
(?a4t.� 2-2-26
P. O. Box 592 0 Portland, Texas 78374 • 361-776-2662 9 fax: 888-980-9575
CHANGE ORDER REQUEST
SRTR DENT INC.
This Change Order Request Form is submitted by SR Trident,Inc.to request the following changes.
SPIT Job Number: 240129 Purchase Order Number: 21027
Change Order Date: 1/21/2025 Project Name New Peoples Street Boardwalk
Change Order Number: 8 Project Number: 240129
Change Order Type: Owner Project Manager: Curtis Weiss
CHANGE REQUEST INFORMATION
Change Order Scope:
Listed in the attached proposal letter.
Reason for Change:
Error on the electrical wiring drawings.
CHANGE REQUEST IMPACT
Costlmpact: Schedule Impact
OriginalOrderAmount: $ 5,999,753.60 Change OrderAmount Includes: Q Tax Q Freight
Previous Change Orders $ 780,000.00 Schedule Impact a IYes 1 ❑ INo
Current Change Order: $ 17,613.80 Current Finish Date:
Revised Total: $ 6,797,367.40 Impact Finish Date:
Schedule Impact Days 16 Revised Schedule Attached: Q 1yes 1 ❑ INO
SUPPORTING DOCUMENTATION&ATTACHEMENTS
List Supporting Documentation and Attachments Attachment
1 FOR approved RFI found in E-builder ❑ Yes ❑ No
2 ❑ Yes ❑ No
3 ❑ Yes ❑ No
4 ❑ Yes ❑ No
5 ❑ Yes ❑ No
6 1 ❑ 1Yes 1 ❑ 1 No
REPRESENTATIVE'S RECOMMENDATION(Completed by Owner)
Recommendation of this Change Order: 10 JACcept I ❑ I Reject I ❑ I Hold
Reason for Reject or Hold
OWNER AUTHORIZED SIGNATURE SR TRIDENT INC.REPRESENTATIVE
Authorized Signature: Authorized Signature:
Name: Name: Jerred Kin
Title: Title: P.M.
Change Order Effective Date: Date: 1/21/2025
0 0 0 0 0 0 O1
0 0 0
m o 00 o 0 0 0 0 0 0 o 0 0 o 0 o o o 0 0 0 o 0 0 0 0 o m �^
0 1O o 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 o m
N N N N N N N N N N N N N N N N N N N N N N N N 01
m
N � N N VF N O N IA tp
N N N
O 0 O
0 0 0 0
O O 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
� O � n N N N N N N N N N N N N N N N N N N N N N N N �
n a m n m
N
O
m O
>
u
m 1D
M
C
O
U
3 v1Di
v
z
v �
m �
> Oi
u O�1
O
V
N
O N 0 0 0 0 0 0 0 0
W �
t N
a
m
0
L
E a °- o ° `Y - o O
m O
z m
OD
67 y I m o
tko
y O
@ r_
C m L:J
m 0 (V
s
u _v
u
z° _ t
bd m a1 N � N ti m N Q
cc
�L ,O
1 L
W
V!
Signature:
Email: stephanieb2@corpuschristitx.gov
Signature: sa.� Evwkeilhoe414
Sarah&unkenhoefer(Mar 26,2026 09:14:2 CDT)
Email: sarahb@corpuschristitx.gov