HomeMy WebLinkAboutM2000-365 - 10/10/2000MOTIONS- 10/10/00
12.a.
Motion approving the reimbursement application submitted by Hossein Mostaghasi, owner
and developer of Brighton Village Unit 8A, for the installation of 620 linear feet of an off-site
8-inch PVC sanitary sewer collection line and replacement of an existing manhole.
ATTEST:
Arm~creta ry
City of Corpus Christi
M2000-365
APPLICATION FOR SEWER LINE CREDIT
I, Hossein Mostaghasi, owner and developer of proposed Brighton Village Unit 8A,
hereby apply for $12,366.00 credit towards the sewer lot/acreage fee for the collection line
extension installed in conjunction with Brighton Village Unit 8A Subdivision as provided for by
City Ordinance No. 17396. The construction cost is $26,164.56, including 7-1/2% Engineering,
as shown by the cost supporting documents attached herewith.
(Developer) (Date)
THE STATE OF TEXAS
COUNTY OF NUECES
This instmment was acknowledged before me on
by Hossein Mostaghasi, Owner and Developer of Brighton Village Unit 8A.
7~?~ ,2000
Notary Public in and for Nueces County, Texas
CERTIFICATION
The information submitted with this application has been reviewed and determined to be
correct and a credit for $12,366.00 is herewith approve&
Exhibit C
Page 1 of 4
APPLICATION FOR SEWERLINE REIMBURSEMENT
I, Hossein Mostaghasi, owner and developer of proposed Brighton Village Unit 8A,
hereby request reimbursement of $55,929.71 for the installation of the sewer collection line and
replacement of an existing manhole in conjunction with Brighton Village Subdivision, as
provided for by City Ordinance No. 17396, and as requested by the Wastewater Department.
Said $55,929.71 is the construction cost, including 7-1/2% Engineering, as shown by the cost
supporting documents attached herewith.
(Developer) (Date)
THE STATE OF TEXAS
COUNTY OF NUECES n
This instrument was acknowledged before me on ~ i>~l'e rr~ [~t'- ~. '7_, ,2000
by Hossein Mostaghasi, Owner and Developer of Brighton Village Unit 8A.
Notary Public in and for Nueces County, Texas
CERTIFICATION
The information submitted with this application for reimbursement has been reviewed
and determined to be correct. Reimbursement is subject to:
(a) sufficiency of funds in the Collection Line Trust Fund
(b) appropriation and approval by the City Council
Exhibit C
Page 2 of 4
Special Services
Sept. 7, 2000
CITY REIMBURSEMENT PER PLATTING ORDINANCE V.B.6.1 .(2)
Maximum reimbursement for a sanitary sewer collection line off-site extension is limited to 50%
of the mathematical product obtained by multiplying the off-site average diameter in inches by
the fee value of the property.
A. SUPPORTING DATA FOR OFF-SITE EXTENSION REIMBURSEMENT
Legal Description:
Existing Acreage:
Date Platted:
Off-site Extension:
Fee Value:
Brighton Village Unit 8A
10.45
December 1999
8-inch PVC line, 620 feet
(Lots x WW Lot Fee = Fee Value)
54 lots x $229/lot = $12,366.00 Credit*
Maximum Reimbursement Eligibility: 50%(8")($12,366.00') = $49,464.00
Off-site Sanitary Sewer Actual Construction Costs:
323' x 8" PVC (12'-14' cut) @ $30/LF
297' x 8" PVC (10'-12' cut) @ $26/LF
1 - 4' Manhole @ $1700 EA
Subtotal
General Contractor's Profit and Bond (27.35x$19, 112.00)
Subtotal
Engineering Fee (7.5%)
Total
$ 9,690.00
7,722.00
1,700.00
$19,112.00
$24,339.13
1,825.43
$26,164.56
Allowable Reimbursement: Actual construction cost ($26,164.56) does not exceed maximum
allowable reimbursement ($49,464.00). Lot fees were paid at time of platting. Therefore,
reimbursement requested is $26,164.56.
B. SUPPORTiNG COST DATA FOR MANHOLE REPLACEMENT.
The City's Wastewater Department requested that the developer replace an existing 4-foot
Exhibit C
Page 3 of 4
Special Services
L.F.
Sept. 7, 2000
fiberglass sliplined brick manhole with a new 5-foot fiberglass manhole. The following lists the
cost data for which the developer is eligible for 100% reimbursement:
UNIT
DESCRIPTION QUANTITY UNIT PJ~Ell TOTAL
Pavement repair 50 SY 37.48 $1,873.78
Trench safety 60 LF 14.19 851.20
Remove existing clay pipe 60 LF 21.91 1,314.55
8" Sanitary Sewer (12'-14') 60 LF 80.00 4,800.00
Fiberglass manhole 1 EA 4,197.97 4,197.97
Remove and replace curb &
gutter 15 LF 51.99 779.02
Remove and replace 5'
sidewalk 60 LF 12.13
Haul off excess excavation 145 CY 11.07
Barricades 1 LS 4,337.12
Remove existing manhole 1 EA 1,254.55
Subtotal
General Contractor's Profit and Bond (27.35%)
Subtotal
Engineering Fee (7.5%)
Total
728.02
1,605.85
4,337.12
A,254.55
$21,742.06
5,946.45
$27,688.51
2.,076.64
$ 29,765.15
C. TOTAL REIMBURSEMENT ELIGIBILITY.
Off-site Sanitary Sewer Line Extension (See A above)
Manhole Replacement (See B above)
Total
$ 26,164.56
$ 55,929.71