HomeMy WebLinkAboutM2016-057 - 05/31/2016 File Number: 16-0620 Enactment Number: M2016-057
rr' Corpus Christi 1201 Leopard Street
Corpus Christi,TX 78401
G; zµ. cctexas.corn
-` "4' May 31, 2016
Motion: M2016-057
File Number: 16-0620 Enactment Number: M2016-057
Motion to appoint a three-member task force to investigate the City's water issues, using
the approved scope, and appointing the following individuals to the task force: Chair, Ed
Martin; Technical Advisor, Bob Bowcock; and Acting City Manager, Margie Rose.
At a meeting of the City Council on 5/31/2016, this Motion was passed.
Aye: 6 Mayor Martinez, Council Member Garza, Council Member Magill, Council
Member Rubio, Council Member Rosas, and Council Member Vaughn
Nay: 1 Council Member Hunter
Absent: 2 Council Member McIntyre, and Council Member Scott
Abstained: 0
Nelda MartineF..•r
Attest: ei a,12, '.C' L .l.�t�%1'L--f.�
Rebecca Huerta, City Secretary
Corpus Christi Printed on 6/9/16
INDEXED
CORPUS CHRISTI WATER UTILITY—BOIL WATER NOTICE
INVESTIGATION
1.0 IMMEDIATE ACTION PLAN
1.1 Provide Summaries of Past 3 Boil Water Notices
• Provide summaries regarding the processes that took place(actions
taken,recommendations made, recommendations followed) in the
water department since 2007 as it relates to the water boil
investigation.
• Let TCEQ know our plans moving forward as it relates to them and
our investigation dating back to 2007.
1.2 Conduct a Root Cause Analysis for Past 3 Boil Water Notices- Other
Consider the following factors:
• Nitrification response plan
• Monitoring plan and action triggers
• Regulatory response
• Infrastructure configuration and condition factors
• Organizational factors
• Cross-connection control plan
• Laboratory staffing and resources
• Laboratory procedures
• Maintenance procedures
• Personnel qualifications
• • Overall policies and procedures
• Decision-making processes
1.3 Immediate Recommendations to Avoid a Repeat Boil Water Occurrence in
the Near-term(0-12 months)
Suggest near-term responses to reduce the risk of Boil Water Notices or other
regulatory violations.
• Safety plan
• Process control plan
• Testing and monitoring plan
• Regulatory compliance plan
• Laboratory certification and procedures
• New and revised procedures
• Suggested resource acquisitions
• Organizational maturity assessment
• Recommended organizational changes
2.0 LONG-RANGE ACTION PLAN
2.1 Recommendations for Long-range Improvements (beyond 12 months)
Suggest a series of long range actions to bring the water utility into a stable
operating posture.
• Business plan changes
• Process control and instrumentation improvements
• Operator and staff training plan
• Laboratory management plan
• Quality control plan
• Preventative maintenance management
• Staff#'s, organization structure and qualifications
• Review existing capital projects
• New capital equipment
• New capital projects
• Asset recapitalization plan
• Water resource planning
• Financial plan and rate model