HomeMy WebLinkAbout09748 ORD - 05/13/1970BJW:5/13/70
TEXAS:
AN ORDINANCE
AUTHORIZING'THE ISSUANCE OF CHANGE ORDER NO. 1 IN THE
AMOUNT OF $18,657.30 TO REDUCE SIZES AND GAGES OF CAS-
INGS, ADDING ITEMS TO THE CONTRACT, REDUCING THE QUANTI-
TIES ON CERTAIN ITEMS OF THE CONTRACT, PROVIDING STEEL
WALL COLLARS ON STEEL PIPE, PROVIDING FLANGED ADAPTERS
AND THICKENING WALLS OF VALVE VAULTS AT COLLARS, IN
CONNECTION WITH THE LEOPARD STREET WATER TRANSMISSION
LINE, ALL AS MORE FULLY DESCRIBED IN CHANGE ORDER NO.1,
ATTACHED HERETO AND MADE A PART HEREOF; APPROPRIATING
OUT OF NO. 202 WATER SYSTEM BOND FUND THE SUM OF
$18,657.30 FOR PAYMENT OF CHANGE ORDER NO. 1 IN CONNEC-
TION WITH PROJECT NO. 202 -68 -29.1, LEOPARD STREET WATER
TRANSMISSION LINE; AND DECLARING AN EMERGENCY.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF CORPUS CHRISTI,
SECTION 1. AUTHORIZATION IS HEREBY GIVEN FOR THE ISSUANCE OF
CHANGE ORDER N0. 1, IN THE AMOUNT OF $18,657.30 FOR THE REDUCTION OF SIZES
AND GAGES OF CASINGS, ADDING ITEMS TO THE CONTRACT, REDUCING THE QUANTITIES
ON CERTAIN ITEMS OF THE CONTRACT, PROVIDING STEEL WALL COLLARS ON STEEL
PIPE, PROVIDING FLANGED ADAPTERS AND THICKENING WALLS OF VALVE VAULTS AT
COLLARS, IN CONNECTION WITH THE LEOPARD STREET WATER TRANSMISSION LINE,
PROJECT N0. 202 -68 -29.1.
SECTION 2. THERE IS HEREBY APPROPRIATED OUT OF N0. 202 WATER
SYSTEM BOND FUND THE SUM OF $18,657.30 FOR PAYMENT OF CHANGE ORDER NO. 1
OUTLINED ABOVE.
SECTION 3. THE NECESSITY TO MAKE THE HEREINABOVE DESCRIBED
APPROPRIATIONS AND TO AUTHORIZE THE CHANGE ORDER HEREIN SET FORTH SO THAT
THE PROJECT MAY CONTINUE WITHOUT DELAY CREATES A PUBLIC EMERGENCY AND IM-
PERATIVE PUBLIC NECESSITY REQUIRING THE SUSPENSION OF THE CHARTER RULE THAT
NO ORDINANCE OR RESOLUTION SHALL BE PASSED FINALLY ON THE DATE OF ITS
INTRODUCTION AND THAT SUCH ORDINANCE OR RESOLUTION SHALL BE READ AT THREE
SEVERAL MEETINGS OF THE CITY COUNCIL, AND THE MAYOR HAVING DECLARED SUCH
EMERGENCY AND NECESSITY TO EXIST, AND HAVING REQUESTED THE SUSPENSION OF
THE CHARTER RULE AND THAT THIS ORDINANCE BE PASSED FINALLY ON THE DATE OF
ITS INTRODUCTION AND TAKE EFFECT AND BE IN FULL FORCE AND EFFECT� FROM AND
AFTER ITS PASSAGE, IT IS ACCORDINGLY SO ORDAINED, THIS THE /�T'v DAY OF
MAY. 1970. ,y
ATTEST -
0
THE CITY OF CORPUS CHRISTI, TEXAS
CIT SECRET RY
APPROVE OF MAY, 19
ITY ATTORNEY'p
�'d QCs
:hinge Order No. 1
CHANCE ORDER
PUBLIC WORKS DEPARDfENT
Engineering Division
City of Corpus Christi, Texas
Project No. 202 -68 -2901
)perating Department Water Date May 6, 1970
lame of Project LEOPARD STREET WATER TRANSMISSION LINE
, ontractor BURTEX CONSTRUCTORS, INC.
C i3A NCE
1, Reduce sizes and gages of casings as per attached, adding Pay Items
57 -61 incl, to contract, and reducing to zero the quantities on Pay
Items 13 -16 Incl.
2. Provide steel wall collars on steel pipe as per attached list and
Dwg. No, 6265C, adding Pay Items 63 -65 incl. to contract
3. Provide flanged adapters (Smith -Blair No, 913) as per attached list,
adding Pay Item 62 to contract
4. Thicken walls of valve vaults at collars,
Add: Item 24, 71 CY Class A Concrete @ $105, 00
Adds Item 25, 14.570 Lbs, Reinf. Steel @ $0.15 =
Totals
Net for this Change Order
ADD DEDUCT
5,124.20
11,158.0(
2,983.00
7,455, 0
2,185.50
23, 781, 5 3,124.20
18, 657.3
any was this change necessary? (If left off the plans and specifications, explain why,)
PP s were based on the use of DuctUe Pine. Contract was awarded on basis of steel pipe, This
allows use of smaller casings but requires adapters for flexibility and wall collars and thicker
v,a of vaults to esastt ®aspe.at,a�e- stresses.
Sow can similar changes be avoided in the future?
Include additional alternate items in plans and specifications
3ontract Price 30125,628.50
this Change Order + 18,,_657.30 Assistant Director of Public Works
iew Contract Price '144-285-80 REAGAN & McCAUGHAN
\mount Appropriated 3, 225, 000, 00
onsulting xStEngineer
,ITY OF CORPUS CHRISTI, TEXAS
ay.
Director of Public Works
1PPROVED City Manager
City Attorney
Director of Finance
CONTRACTOR BURTEX CONSTRUC TORS, INC
By— Cs
Title Ager-��e.vr
NOTE: Contractor, please sign one copy and
return it to the Director of Public
Works.
CHANGE ORDER NO. 1
ESTIMATED COSTS FOR REVISIONS AT VALVE VAULTS
New Item 62. Adapters 19 Ea. @ $157. 00 $ 2, 983. 00
New Item 63. Wall Collars on 36" Pipe, 6 Ea. @ $323. 00 1,938.00
New Item 64. Wall Collars on 4211 x 36" Reducers 5 Ea. @ $348. 00 1,740.00
New Item 65. Wall Collars on 48" x 36" Reducers 20 Ea. @ 374. 00 7,480.00
Not new Item. Concrete Class "A" 71 C. Y. @ $105. 00 7,455.00
Not new Item. Reinforcing Steel 14,570 Lbs. @ $0.15 2,185.50
CHANGE ORDER NO. 1
PROPOSED REVISIONS AT VALVE VAULTS'
Note: D. S. designates downstream side or on side of increasing stationing.
U.S. designates upstream side, or on side of decreasing stationing.
- -- -Wall Collars--- -
Line
Approx.
Valve
Adapters
Size Pipe
Estimated
Addn.
No.
Station
Size
No.
Loca.
No. Loca.
or Reduc.
Concrete
Steel
A
0+ 70
36"
0
1
DS
36" Pipe
2.3
470
A
-
24"
0
0
0
0
A
19+ 45
36"
1
US
1
US
36" Pipe
2.3
470
B
In Exist.
Line
36"
0
0
0
0
B
0+ 11
36"
1
DS
1
DS
48" x 36"
2.3
470
B
9+ 20
36"
0
0
0
0
B
9+ 50
36"
0
0
0
0
B
55 + 80
36"
1
DS
1
DS
48" x 36"
Z. 3
470
B
99+ 00
36"
1
DS
2
48" x 36"
4.6
940
B
148+ 20
36"
1
DS
2
48" x 36"
4.6
940
B
196 + 60
36"
1
DS
2
48" x 36"
4.6
940
B
250+ 72
36"
1
DS
2
48" x 36"
4.6
940
B
291 + 90
36"
1
US
2
48" x 36"
4.6
940
B
335 + 30
36"
1
DS
2
48" x 36"
4.6
940
B
391 + 05
36"
1
DS
2
48" x 36"
4.6
940
B
453 + 60
36"
1
DS
2
48" x 36"
4.6
940
B
512 + 55
36"
1
DS
2
48" x 36"
4.6
940
B
542+ 07
36"
1
DS
1
DS
42" x 36"
Z. 3
470
C
1 + 37
36"
1
DS
1
DS
36" Pipe
Z. 3
470
C
62+24
36"
1
DS
2
36" Pipe
4.6
940
C
112 + 40
36"
1
US
1
US
36" Pipe
Z. 3
470
In Omaha
30"
0
0
0
0
In Omaha
30"
0
0
0
0
In Omaha
24"
0
0
0
0
D
53 + 10
36"
1
DS
2
42" x 36"
4. 6
940
D
81 + 57
36"
1
US
1
US
42" x 36"
2.3
470
Relocation 48"
36"
0
0
Relocation 48"
36"
0
0
D
0+ 30
36"
1
DS
1
DS
42" x 36"
2.3
470
Note: D. S. designates downstream side or on side of increasing stationing.
U.S. designates upstream side, or on side of decreasing stationing.
CHANGE ORDER NO. 1
PROPOSED CHANGES IN CASING SIZES AND GAGES
--- - - - - -- Reduce Contract-- - - - - --
- - - - - -- -Add to Contract--- - - - - --
Reduc.
Savings
Starting Length Item Unit
New
Unit
in Unit
to
Line
Station (L. F. No. Size Gage & Type Price
Item
Size Gage & Type
Price
Price
City
B
14+ 06 90 13 72" 10 Ga. L. P. $97.00
57
60" 10 Ga. L. P.
$91.50
$5. 50
$ 495.00
C
32+40 70 16 60" 12 Ga. L. P. 82.50
58
54" 12 Ga. L. P.
80. 00
2.50
175.00
C
33+ 57 140 16 60" 10 Ga. CMP 82.50
59
54" 10 Ga. CMP
80.70
1.80
252. 00
C
35+54 70 16 60" 12 Ga. L. P. 82. 50
58
54" 12 Ga. L. P.
80. 00
2.50
175.00
D
40+77 80 14 66" 10 Ga. CMP 69.50
61
54" 12 Ga. CMP
63, 10
6.40
512.00
D
42+79 83 14 66" 10 Ga. CMP 69.50
61
54" 12 Ga. CMP
63. 10
6.40
531. 20
D
44+20 130 15 66" 8 Ga. CMP
10 Ga. CMP
in Open Cut 47.00
60
54" in Open Cut
43. 00
4.00
520. 00
D
53+ 53 35 14 66" 10 Ga. CMP 69.50
61
54" 12 Ga. CMP
63. 10
6.40
224. 00
D
54+20 60 14 66" 10 Ga. CMP 69.50
61
54" 12 Ga. CMP
63. 10
6.40
384.00
D
55+ 00 120 14 66" 10 Ga. CMP 69.50
61
54" 12 Ga. CMP
63, 10
6.40
768.00
D
56+ 50 40 14 66" 10 Ga. CMP 69.50
61
54" 12 Ga. CMP
63. 10
6.40
256. 00
D
62+64 ' 130 14 66" 10 Ga. CMP 69.50
61
54" 12 Ga. CMP
63. 10
6.40
832, 00
$5, 124, 20
NOTES:
(1)
This Change eliminates Pay Items 13 -16 incl. and adds Pay
Items
57 -61 inclusive.
(2)
Casings on Lines C & D are all in or crossing Padre Island
Drive and the new sizes and
gages have been approved
by the State Highway Department provided the water lines are installed at the same flow line elevations as proposed,
except that the casing on Line C starting at Station 33 + 57 shall be laid level with the top of the casing at
Elevation
20. 5 or below.
Casing on Line B is at Missouri Pacific Railroad Crossing.
CITY OF CORPUS CHRISTI, TEXAS '
CERTIFICATION of FUNDS
(City Charter Article IV Section 21)
May 8, 1970
I certify to the City Council that $ , 18,658. , the amount required
for the contract, agreement, obligation or expenditures contemplated in the
above and foregoing ordinance is in the Treasury of the City of Corpus Christi
to the credit of;
Fund No. and Name 202 Water System Bond Fund
Project No. 202 -68 -29.1
Project Name 1+8" Transmission Main from Calallen
from which it is proposed to be drawn, and such money is not appropriated for
any other purpose.
FIN 2 -55
Revised 7 -31 -69
Direct or Finance
Corpus Christi, Texas
�- day of 1�®
TO THE MEMBERS OF THE CITY COUNCIL
Corpus Christi, Texas
For the reasons set forth in the emergency clause of the foregoing
ordinance, a public emergency and imperative necessity exist for the suspen-
sion of the Charter rule or requirement that no ordinance or resolution shall
be passed finally on the date it is introduced, and that such ordinance or
resolution shall be read at three meetings of the City Council; I, therefore,
request that you suspend said Charter rule or requirement and pass this ordi-
nance finally on the date it is introduced, or at the present meeting of the
City Council.
Respectfully,
MAYOR
THE CITY OF CORPUS CHRISTI, TEXAS
The Charter rule was suspended by the following vote:
Jack R. Blackmon
Gabe Lozano, Sr.
V. A. "Dick "Bradley. Jr.
Eduardo E. de Ases
Ken McDaniel
W. J. "Wrangler" Roberts
Ronnie Sizemore
The above ordinance was passed by the following vote: