AN ORDINANCE
AUTHORIZING THE CITY MANAGER TO EXECUTE CHANGE ORDER
NUMBERS 4 AND 6 TO THE CONTRACT WITH BEECROFT AND
WILLIAMSON, INC., FOR IMPROVEMENTS TO THE MEMORIAL
COLISEUM AND EXPOSITION HALL, WHICH PROVIDE FOR REPAIRS
TO THE FRONT OF THE COLISEUM AND FOR INSTALLATION OF
ADDITIONAL SEATING IN THE PRESS BOX AREA, A SUBSTANTIAL
COPY OF EACH CHANGE ORDER BEING ATTACHED HERETO AND
MADE A PART HEREOF, MARKED EXHIBIT "A"; APPROPRIATING
$4,396 OUT OF THE NO. 261 COLISEUM BOND FUND OF WHICH
$3,876 IS FOR CHANGE ORDER NO. 4 AND $520 IS FOR CHANGE
ORDER NO. 6, APPLICABLE TO PROJECT NO. 261-77-1,
COLISEUM IMPROVEMENTS; AND DECLARING AN EMERGENCY.
•
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF CORPUS CHRISTI,
TEXAS:
SECTION 1. That the City Manager be and he is hereby authorized
to execute Change Order Numbers 4 and 6 to the contract with Beecroft and
Williamson, Inc., for improvements to the Memorial Coliseum and Exposition
Hall, which provide for repairs to the front of the Coliseum and for instal-
lation of additional seating in the press box area, a substantial copy of
each change order being attached hereto and made a part hereof, marked
Exhibit "A".
SECTION 2. That there is hereby appropriated the sum of $4,396 out
of the No. 261 Coliseum Bond Fund of which $3,876 is for Change Order No. 4
and $520 is for Change Order No. 6, applicable to Project No. 261-77-1,
Coliseum Improvements.
SECTION 3. That the necessity to execute Change Orders No. 4 and 6
to the contract with Beecroft and Williamson, Inc., for improvements above
described and to appropriate the sums necessary to construct the improvements
at the earliest practicable date creates a public emergency and an imperative
public necessity requiring the suspension of the Charter rule that no ordi-
nance or resolution shall be passed finally on the date of its introduction
but that such ordinance or resolution shall be read at three several meetings
of the City Council, and the Mayor having declared that such emergency and
necessity exist, and having requested the suspension of the Charter rule and
that this ordinance be passed finally on the date of its introduction and
up 271984
15710
take effect and be in full force and effect from and after its passage, IT
IS ACCORDINGLY SO ORDAINED, this the 3 day of September, 1980.
ATTEST:
it Secretary MAY
/THE !i' OF CORPUS CHRISTI, TEXAS
APPROVED:
3 DAY OF SEPTEMBER, 1980:
J. BRUCE AYCOCK, CITY ATTORNEY
CITY OF CORPUS CHRISTI, TEXAS
CERTIFICATION OF FUNDS
(City Charter Article IV Section 21)
August 29, 1980
I certify to the City Council that $ 4,396.00 , the amount required
for the contract, agreement, obligation or expenditures contemplated in the
above and foregoing ordinance is in the Treasury of the City of Corpus Christi
to the credit of:
Fund No. and Name 261 Coliseum Bond Fund
Project No. 261-77-1
Coliseum Improvements
Project Name
from which it is proposed to be drawn, and such money is not appropriated for
any other purpose. •
, 19P CD
FIN 2-55
Revised 7/31/69
Dir-ctor of F nano
CHANGE
ORDER
AIA DOCUMENT G701
OWNER
ARCHITECT
CONTRACTOR
FIELD
OTHER
8
•
PROJECT: Memorial Coliseum Improvements
(name, address) Corpus Christi, Texas
TO (Contractor)
(Repairs to front entrance)
r
Beecroft fr Williamson, Inc.
P. 0. Box 2642
Corpus Christi, Texas 78403
L J CONTRACT DATE:
You are directed to make the following changes in this Contract:
CHANGE ORDER NUMBER:
[xurCF,
ARCHITECT'S PROJECT NO: 1325
CONTRACT FOR: General Construction
1. Repair base of column.
November 21, 1979
2. Replace two aluminum and glass (tempered) doors completely and
replace only the glass in one door.
3. Replace hardware for two doors - reuse closers.
(See Contractor's estimate attached)
The original Contract Sum was $ 265,054.00
Net change by previous Change Orders $ 2,064.00 86`f `-
The Contract Sum prior to this Change Order was S. 267,118.00 265.41/e. .
The Contract Sum will be (increased) (WHAM) (tIllt `J ll) by this Change Order . . . $ 3,876.00
The new Contract Sum including this Change Order will be a 27p,g _ 00- 2-69,744-
(
6x,7'4( ) Days
The Contract Time will be (¢tc,F ea (10 ) (unchanged) by
The Date of Completion as of the date of this Change Order therefore is unchanged
Brock Mabrey Designs
ARCHITECT
720 MF$feITTF
Address
CORPUS CHRISTI, TEXAS 78401
BV 4
Beecroft a Williamson
CONTRACTOR
P 0 ROX 2642
Address
CORPUS CHRISTI, TEXAS
BY
DATE 4 • /L . 9.6 DATE
City of Corpus Christi
OWNER
P n ROX 9277
Address
78403 CORPUS CHRISTI. TEX.
BY
DATE '{^ 3t7—
AIA DOCUMENT 6701 • CHANGE ORDER • APRIL 1970 EDITION • AIA® • O 1970 • THE
AMERICAN INSTITUTE OF ARCHITECTS, 1735 NEW YORK AVE, NW, WASHINGTON, D.C. 201305
ONE PAGE
P. 0 00X 213.12
ccRPU."i C6-+25TI. TEXAS 713.03
8 E OEEC SET
TOM WILLIAMSON
April 1, 1980
BEECROFT & WILLIAMSON, INC.
GENERAL CONTRACTORS
Brock Maybrey Designs
722 N. Mesquite
Corpus Christi, Texas
Re: Memorial Coliseum - Repairs to Front Entrance
Gentlemen:
P+- OME 512E 82-B75T
PPP., LARE00
The cost of repairing the damaged front entrance is $3,876:00+ Included
in this price are the following:
1. Re -set column
2. Remove the bottom 18 inches of column and replace with new
section and base plate.
3._Anchor base plate with expansion bolts.
4. Furnish two new doors, frames, and panic hardware.
5. Re -wrap column with new break metal.
6. Replace glass in one door where the frame was not damaged.
7. Re -use existing threshold.
8. Re -use existing door closure arm and hold open arms.
The delivery time on the door and panic hardware will be 4 to 6 weeks.
Please let us know as soon as possible if you want us to do this work.
Sincerely,
Beecroft & Williamson, Inc.
Ems , {\ ���, \.. l • 0 t• ---
Tom
. —Tom Williamson
TW/dt
•
CHANGE
ORDER
AIA DOCUMENT G701
OWNER
ARCHITECT
CONTRACTOR
FIELD
OTFIER
{
PROJECT: Memorial Coliseum Improvements
(name, address) Corpus Christi, Texas
TO (Contractor)
✓ Beecroft $ Williamson, Inc.
P. 0. Box 2642
Corpus Christi, Texas 78408
CHANGE ORDER NUMBER: Six (6)
- ARCHITECT'S PROJECT NO: 1325
CONTRACT FOR: General Construction
L J CONTRACT DATE: November 21, 1979
You are directed to make the following changes in this Contract:
Furnish and install five additional twenty-two inch
wide seats at pressbox area.
Seats shall be identical in color and style to the
twenty-eight seats already purchased for this
project.
The original Contract Sum was $ 265,054.00
Net change by previous Change Orders $ 4,815..00
The Contract Suni prior to this Change Order was $ 269,869.00
The Contract Sum will be (increased) (decreased) (undated) by this Change Order . - - $ 520.00
The new Contract Sum including this Change Order will be $ 270,389.00
The Contract Time will be (imatarsa b (dearess nl) (unchanged) by -0- ( .J Days.
The Date of Completion as of the date of this Change Order therefore is
Brock Mabrey Designs Beecroft C Williamson, Inc. City of Corpus Christi
AR, Ygic. Alameda
Address
Corpus Christi, Texas
CCrR®Crclr%x 2642 0ERO. Box 9277
Address Address
Corpus Christi, Texas Corpus Christi
BY GI.t� BY • B'Jr
DATE /1r J/, L /4 gel DATE S itit- .10
AIA DOCUMENT G701 • CHANGE ORDER • APRIL 1970 EDITION • AIA® • ® 1970 • THE ONE PACE
AMERICAN INSTITUTE OF ARCHITECTS, 1735 NEW YORK AVE., NW, WASHINGTON, D.C. 20006
Corpus Christi, texas p
Ai day `�' "taw , 19 6 d
TO THE MEMBERS OF THE CITY COUNCIL
Corpus Christi, Texas
For the reasons set forth in the emergency clause of the foregoing ordinance, a
public emergency and imperative necessity exist for the suspension of the Charter
rule or requirement that no ordinance or resolution shall be passed finally on
the date it is introduced, and that such ordinance or resolution shall be read
at three meetings of the City Council; I, therefore, request that you suspend
said Charter rule or requirement and pass this ordinance finally on the date it
is introduced, or at the present meeting of the City Council.
Respectfully,
The Charter rule was suspend
Luther Jones
Edward L. Sample
Dr. Jack Best
David Diaz
Jack K. Dumphy
Betty N. Turner
Cliff Zarsky
THE t F CORPUS CHRISTI, TEXAS
by the following vote:
The above ordinance was pass _ by the following vote:
Luther Jones
Edward L. Sample
Dr. Jack Best
David Diaz
Jack K. Dumphy
Betty N. Turner
Cliff Zarsky
15740
1