AN ORDINANCE
AUTHORIZING THE CITY MANAGER TO EXECUTE A CHANGE ORDER TO
THE CONTRACT WITH B F W CONSTRUCTION COMPANY FOR TONSTRUC-
TION OF THE CORPUS CHRISTI COMMUNITY CONVENTION CENTER WHICH
PROVIDES FOR INSTALLATION OF ADDITIONAL ELECTRICAL CIRCUITRY,
A SUBSTANTIAL COPY OF WHICH CHANGE ORDER IS ATTACHED HERETO
AND MADE A PART HEREOF, MARKED EXHIBIT "A"; APPROPRIATING
}
'$20,275.02 OUT OF THE NO. 209 COMMUNITY CONVENTION FACILITY
BOND FUND APPLICABLE TO PROJECT NO. 209-76-1.3, CONVENTION
CENTER CONSTRUCTION; AND DECLARING AN EMERGENCY.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF CORPUS CHRISTI,
' TEXAS:
k
SECTION 1. That the City Manager be and he is hereby authorized to
execute a Change Order to the contract with B F W Construction Company for
construction of the Corpus Christi Community Convention Center which provides
for installation of additional electrical circuitry, a substantial copy of
which Change Order is attached hereto and made a part hereof, marked Exhibit
SECTION 2. That there is hereby appropriated the sum of $20,275.02
out of the No. 209 Community Convention Facility Bond Fund applicable to
Project No. 209-76-1.3, Convention Center Construction.
SECTION 3. The necessity to authorize execution of the aforesaid
Change Order and the appropriation of said sums creates a public emergency
and an imperative public necessity requiring the suspension of the Charter
rule that no ordinance or resolution shall be passed finally on the date of
is introduction but that such ordinance or resolution shall be read at three
several meetings of the City Council, and the Mayor having declared that such
emergency and necessity exist, having requested the suspension of the Charter
rule and that this ordinance be passed finally on the date of its introduction
and take effect and be in full force and effect from and after its passage, IT
IS ACCORDINGLY SO ORDAINED, this the /i day of November, 1980.
ATTEST:
City ecretary
AP OVED:
DAY OF NOVEMBER, 1980:
J. BRUCE AYCOCK, CITY ATTORNEY;
By
Assistant t or—ney
/ /
CITY OF CORPUS CHRISTI, TEXAS
15873
MICROFILMED
SEP 271984
W
SHWC, INC.
ARCHITECTS
E N GINE E R S
PLANNERS
O 10300 NORTH CENTRAL EXPWY., BLDG. 4, SUITE 100 DALLAS, TEXAS 75231
O 13231 CHAMPION FOREST DR., SUITE 401 HOUSTON, TEXAS 77069
O 5314 EVERHART, SUITE B CORPUS CHRISTI, TEXAS 78411
O 1220 WEST HARRISON HARLINGEN, TEXAS 78550
O 1801 CENTRAL BLVD., P. O. BOX 3347 BROWNSVILLE, TEXAS 78520
0 Etn M'
DATE: October 28, 1980
CHANGE ORDER NUMBER
CONTRACT DATE: July 19, 1978
CONTRACT COMPLETION DATE: November. 3, 1980
CONTRACTOR: PROJECT:
B F W Construction Company 03-75012: Corpus Christi Community
P. 0. Box 628 Convention Center
Temple, Texas 76501
ADD
riagtfr $ 20.275.02
TO: 6 F W Construction Company
You are authorized to make the following changes in the subject contract:
CONTRACTOR .
1. To furnish all labor, materials, apparatus and connections
to complete, in finished operating condition, to install
road show switches as per the attached sheet and drawing....ADD: $ 20,275.02
The amount of the contract will be (increased) tchgcgmeA by the sum of: ($ 20, 275.02 )
There wit be an extension of zero days for completion. The date of completion of contract was
November 8 19 80 and will now be—Nnvwmhrr R 19 Qn
Amount of Original Contract Total Additions
$ 13,264,142.00 + $ 186 704 92
OWNER:
Total Deductions Contract to Date
-$ 14,36tL00
CONTRACTOR.
ARCHITECT:
- $ 13,437,486.92
DATE -
DATE: LO /2e /en
DATE.
ATTACHMENT FOR CHANGE ORDER NO. 32
Convention Center
Project # 03-75012
1. Connect to MSB -7C, spare 200 ampere switch (fuse - 115A) in Main
Switchboard "MSB" in Main Mechanical Room (E-6), 4-#2 THW, 1-1/2"
conduit and extend up to Storage Room 201 (E-13, E-14). In Room
201, install a 75 KVA transformer (480 volt to 120/280 volt, 3 phase,
4 wire) and feed transformer with feeder from MSB -7C. Install a
200 ampere, 3P, 3F, S/N switch (fuse - 200 A) at transformer. From
switch, install 4 - #250 MCM, THW, 2-1/2" conduit to a 200 ampere, 3P,
3F, S/N switch in Room 202 (E-14) $ .6,522.31
2. On bus duct, located near column line 5 and at column line H
(Parking Level Plan "A", E-3), install a 400 ampere, 3 Pole,
circuit breaker. From this breaker extend 8 - #250 MCM, THW,
3-1/2" conduit along column line H down to column line 4 and
rise to First Level Plan "A" (E-8). At column lines 4 and H
on the First Level, install a 400 ampere, 3P, 3F, S/N switch
and connect to new feeder. Switch is to be located in
Exhibition Hall $ 4,306.64
3. 30 - 20 amp circuits, three pin locking female connectors flush
mounted in ceiling and terminate in Room 201. The 3 pin
connectors shall be similar to the ones used in the Auditorium.
Circuit termination panel wall mounted Room 201. 6'.0" retractable
cable with neoprene roller guides with 3 pin male connectors.
Circuits 1-30 located as per drawings. Circuits 31 to 40
refer to page E-14 of the contract documents.
Change 10 outlets which terminate at switch bank "N" to terminate
at the new circuit termination panel in Room 201. See attached
drawing for additional notes and details $ 4,817.00
4. To add support pipe for road show lights above the ceiling
in the Banquet/Assembly Room 203 $ 1,984.50
TOTAL ADD $17,630.45
PLUS 15% OVERHEAD AND PROFIT $ 2,644.57
TOTAL ADD THIS CHANGE ORDER $20,275.02
CITY OF CORPUS CHRISTI, TEXAS
CERTIFICATION OF FUNDS
(City Charter Article IV Section 21)
November 6, 1980
I certify to the City Council that $ 20,275.02 , the amount required
for the contract, agreement, obligation or expenditures contemplated in the
above and foregoing ordinance is in the Treasury of the City of Corpus Christi
to the credit of: ,
Fund No. and Name No. 209 Community Convention Facility Bond Fund
Project No. 209-76-1.3
Project Name Convention Center Construction
from which it is proposed to be drawn, and such money is not appropriated for
any other purpose. •
190
FIN 2-55
Revised 7/31/69
Corpus Christi, :xas
/L day of
TO THE MEMBERS OF THE CITY COUNCIL
Corpus Christi, Texas
For the reasons set forth in the emergency clause of the foregoing ordinance, a
public emergency and imperative necessity exist for the suspension of the Charter
rule or requirement that no ordinance or resolution shall be passed finally on
the date it is introduced, and that such ordinance or resolution shall be read
at three meetings of the City Council; I, therefore, request that you suspend
said Charter rule or requirement and pass this ordinance finally on the date it
is introduced, or at the present meeting of the City Council.
t 0. ,
910
0
Respectfully,
MAYO
THE C TY OF CORPUS CHRISTI, TEXAS
The Charter rule was suspend by the following vote:
Luther Jones
Edward L. Sample
Dr. Jack Best
David Diaz
Jack K. Dumphy 1
Betty N. Turner OF
Cliff Zarsky /
The above ordinance was passed
Luther Jones
Edward L. Sample
Dr. Jack Best
David Diaz
Jack K. Dumphy
Betty N. Turner
Cliff Zarsky
by
•
the following vote:
9_5873