HomeMy WebLinkAbout15982 ORD - 01/21/1981jkh:1-21-81 ;1st
F
AN ORDINANCE
AUTHORIZING THE CITY MANAGER TO EXECUTE A CONTRACT
WITH B & E CONSTRUCTION COMPANY FOR CONSTRUCTION OF
STREET IMPROVEMENTS TO TIMBERGROVE LANE; APPROPRI-
ATING $214,000 OUT OF THE NO. 220 STREET BOND FUND,
OF WHICH $206,998 IS FOR THE CONSTRUCTION CONTRACT
AND $7,002 IS FOR ADDITIONAL ENGINEERING, LABORATORY
TESTING, AND RELATED EXPENSES APPLICABLE TO PROJECT
NO. 220-77-2.18, TIMBERGROVE LANE IMPROVEMENTS; AND
DECLARING AN EMERGENCY.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF CORPUS CHRISTI,
TEXAS:
SECTION 1. That the City Manager be authorized to execute a con-
tract with B & E Construction Company for construction of improvements to
Timbergrove Lane, all as more fully set forth in the plans and specifications
and contract documents on file in the office of the City Secretary, all of
which are made a part hereof by reference and according to the bid of B & E
Construction Company, opened on the 12th day of November, 1980 , said
bid being the lowest and most advantageous to the City of Corpus Christi,
Texas.
SECTION 2. That there is hereby appropriated the sum of $214,000
out of the No. 220 Street Bond Fund, of which $206,998 is for the construction
contract and $7,002 is for additional engineering, laboratory testing, and
related expenses applicable to Project No. 220-77-2.18, Timbergrove Lane
Improvements.
SECTION 3. The necessity to execute the aforesaid contract and to
appropriate the sums hereinabove set forth so that the street improvements may
be commenced on Timbergrove Lane at the earliest practicable date creates a
public emergency and an imperative public necessity requiring the suspension
of the Charter rule that no ordinance or resolution shall be passed finally
on the date of its introduction but that such ordinance or resolution shall
be read at three several meetings of the City Council, and the Mayor having
declared that such emergency and necessity exist, and having requested the
suspension of the Charter rule and that this ordinance be passed finally on
the date of its introduction and take effect and be in full force and effect
1.5982 • 'SEP 27 1984
from and after its passage, IT IS ACCORDINGLY SO ORDAINED, this the..V41-•
day of January, 1981.
ATTEST:
Cit Secretary
APPROVED:
21st DAY OF JANUARY, 1981:
J. BRUCE AYCOCK, CITY ATTORNEY
By
Assistant Ci,,j' torney
MAY
E CIT OF CORPUS CHRISTI, TEXAS
APPROVED:
Department Head r lri"J
CITY OF CORPUS CHRISTI, TEXAS
CERTIFICATION OF FUNDS
(City Charter Article IV Section 21)
January 16, 1981
I certify to the City Council that *214,000.00 , the amount required
for the contract, agreement, obligation or expenditures contemplated in the
above and foregoing ordinance is in the Treasury of the City of Corpus Christi
to the credit of:
Fund. No. and Name No. 220 Street Bond Fund
Project No. 220-77-46
Project Name Timbergrove Lane Improvements
from which it is proposed to be drawn, and such money is not appropriated for
any other purpose. •
Director o finance
FIN 2-55
Revised 7/31/69
J
CorpusL Christi, exas
day of -i. , 19 gJ
TO THE MEMBERS OF THE CITY COUNCIL
Corpus Christi, Texas
For the reasons set forth in the emergency clause of the foregoing ordinance, a
public emergency and imperative necessity exist for the suspension of the Charter
rule or requirement that no ordinance or resolution shall be passed finally on
the date it is introduced, and that such ordinance or resolution shall be read
at three meetings of the City Council; I, therefore, request that you suspend
said Charter rule or requirement and pass this ordinance finally,on the date it
is introduced, or at the present meeting of the City Council.
Respectfully,
MAY
THE C OF CORPUS CHRISTI, TEXAS
The Charter rule was suspended by the following vote:
Luther Jones
Edward L. Sample
Dr~. Jack Best
Jack K. Dumphy
Leopoldo Luna
Betty N. Turner
Cliff Zarsky
The above ordinance was pas by the following vote:
Luther Jones
Edward L. Sample 1
Dr. Jack Best
Jack K. Dumphy Of, _
Leopoldo Luna 1
Betty N. Turner / , .-,
Cliff Zarsky ' 1
15982.