HomeMy WebLinkAbout16236 ORD - 05/13/1981TEXAS:
AN ORDINANCE
AUTHORIZING THE CITY MANAGER TO EXECUTE CHANGE ORDER
NO. 5 TO THE CONTRACT WITH PERMIAN -REPUBLIC, CONTRACTOR
FOR IMPROVEMENTS TO THE OSO WASTEWATER TREATMENT PLANT,
A SUBSTANTIAL COPY OF WHICH CHANGE ORDER IS ATTACHED
HERETO AND MADE A PART HEREOF, MARKED EXHIBIT "A",
WHICH PROVIDES FOR RECONSTRUCTION OF DAMAGED STEEL
SECTIONS IN CHLORINE CHAMBERS NOS. 3 AND 4 AT THE OSO
WASTEWATER TREATMENT PLANT; APPROPRIATING $11,834.27
OUT OF THE NO. 250 SANITARY SEWER BOND FUND, APPLICABLE
TO PROJECT NO. 250-77-4, OSO WASTEWATER TREATMENT PLANT
CONTRACT NO. 4, 75% OF WHICH WILL BE FUNDED BY THE
ENVIRONMENTAL PROTECTION AGENCY AND 25% OF WHICH WILL
BE FUNDED BY CITY LOCAL SHARES, SAID APPROPRIATION
BEING SUBJECT TO APPROVAL AND CONCURRENCE BY THE
ENVIRONMENTAL PROTECTION AGENCY; AND DECLARING AN
EMERGENCY.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF CORPUS CHRISTI,
SECTION 1. That the City Manager be and he is hereby authorized
to execute Change Order No. 5 to the contract with Permian -Republic, con-
tractor for improvements to the Oso Wastewater Treatment Plant, a substantial
copy of which change order is attached hereto andlmade a part hereof, marked
Exhibit "A", which provides for reconstruction of damaged steel sections in
chlorine chambers Nos. 3 and 4 at the Oso Wastewater Treatment Plant.
SECTION 2. That there is hereby appropriated out of the No. 250
Sanitary Sewer Bond Fund the sum of $11,834.27, applicable to Project
No. 250-77-4, Oso Wastewater Treatment Plant Contract No. 4, 75% of which will
be funded by the Environmental Protection Agency and 25% of which will be
{
funded by City local shares, said appropriation being subject to approval
and concurrence by the Environmental Protection Agency.
SECTION 3. The necessity to authorize execution of the aforesaid
change order and appropriation of the sums necessary to effect the said
change order at the earliest practicable date creates an imperative public
necessity requiring the suspension of the Charter rule that no ordinance
or resolution shall be passed finally on the date of its introduction but
16236
MICROFILMED
271Y84.
12
that such ordinance or resolution shall be read at three several meetings
of the City Council, and the Mayor or Council Members, having declared that
such emergency and necessity exist, having requested the suspension of the
Charter rule and that this ordinance be passed finally on the date of its
introduction and take effect and be in full force and effect from and after
its passage, IT IS ACCORDINGLY SO ORDAINED, this the )3 day of
May, 1981.
ATTEST:
or
, Secretary MAYOR
THE CI OF CORPUS CHRISTI, TEXAS
APPROVED: 43 DAY OF MAY, 1981:
J. BRUCE AYCOCK, CITY ATTORNEY
By /6)
Assistant Cit rney
Pollution Control Project No. W.P.C.-TEX-1214
E.P.A. Step 2 Grant No. C-48-1214
Improvements to the Oso Wastewater Treatment Plant
Corpus Christi, Texas
Contract No. 4, Treatment Plant Expansion
First Phase of Plant Construction
CHANGE ORDER NO. 5
PART A. Necessity of the Change Order:
When existing Chlorine Chamber Nos. 3 and 4 were drained for cleaning, it
was discovered the sludge scraper mechanism had structural damage. The
sludge scraper mechanism in these two structures needs to operate prop-
erly and reliably, because this is the last place from which sludge can
be removed before the effluent is discharged into the receiving waters.
The reason the work was not -included in the current Contract is -because
these two structures were full and operating as final clarifiers until
By -Pass Occurrence No. 5 began, and then the structures were drained
and the damaged noticed. }
The original -clarifiers had a full circle sludge trough with the scraper.
equipment in the trough. 'This is now considered a poor design and is the
major source_of damage to the sludge scraper mechanism. To eliminate
the possibility of similar damage in the future, the circular trough
will be filled with concrete.
-Most of the_existing bolts that hold the truss arms of the scraper mechan -
ism to the center cage are in very bad condition and _need replacing.
PART B. Description of the Work:
The-sludgescraper mechanism is constructed from structural steel channel
and angle sections. The damaged steel sections will' be i'eplaced-with-new
sections of equal size. All new sections will be sandblasted and painted
as per the specifications of this Contract.
The -existing full circle sludge trough will -be filled with 2000 psi -=-concrete
leaving a sump at the -sludge drain pipe.
r
Ali bolts attaching the -scrape mechanism truss arms-to•.the=center-cage-'i ill :.-
be replaced with. bolts of equal size and strength..
PART C. Construction Method:
The new structural sections will be installed by fieldwelding, prior
sandblasting and painting.
The 2000 psi concrete will be placed and all new bolts will be installed
by conventional construction methods with no special installation techni-
ques required.
•
PART D. Cost Breakdown:
I. Materials:
a. Structural Steel
b. Paint and Sandblasting Sand
c. Concrete
d. Welding Rods, Oxygen, Acetylene,
Bolts, etc.
II. Labor:
$ 2,300.00
450.00
2,880.00 •
350.00
Materials Sub -Total $ 5,980.00
a. Concrete Fill at Sludge Sumps;
88 Manhours @ $8.25/Hr.
b. Remove existing and install
new scrapers;
168 Manhours @ $8.25/Hr.
c. Remove and repair existing
scraper arms;
62 ;labours @ $8.25/Hr.
III. Equipment:
a. 18 Ton Crane
b. Welding Machine
c. Pickup Truck
d. Fuel, Oil & Grease
Labor Sub --Total
$ 726.00
$ 1,386.00
$ 511.50
$ 2,623.50
$ 875.00
60.00
75.00
100.00
Equipment Sub -Total $ 1,110.00
Sub -Total -S 9,713,50
Taxes and Insurance at '22%--$ -577.17
Sub -Total $10,290.67
Overhead and Profit=at 15% $-1,543_60-
Change Order No. 5-Total_$11,834.27
The Original Contract Sum
Net_Increase By Previous Change Orders
Contract Sum Prior to this Change Order
Contract Amount Increased by this Change Order
New Contract Amount
Orginal Contract Time
Net Time Increase by Previous Change Orders
Contract Time Prior to this Change Order
$ 7,411,000.00
t!:231:, -38O.54
$ 7,4344380.54
$ 11,834.27
$ 7,446,214.81
500 Working Dt
-0-
500 Working De
•
act Time Increased by this Change Order
act Time
ENGI
Ur
By:
By:
P.E.
Partner
Date: I
g1
CONTRACTOR: OWNER:
Permian/Republic
T
-0-
500 Working D
City of Corpus Christi
By:
Date;
Robert M. wns .lames K. Lontos.,P.E.
Project Superintendent Assistant City Manager
Date:
12'
_
CITY OF OORPUS CHRISTI, TEXAS
CERTIFICATION OF FUNDS
(City Charter Article IV Section 21)
May 12, 1981
I certify to the City Council that $ 11,834.27 , the amount required for
the contract, agreement, obligation or expenditures contemplated in the above
and foregoing ordinance is in the Treasury of the City of Corpus Christi to the
credit of:
Fund No. and Name
Project No.
Project Name
250 Sanitary Sewer Bond Fund
250-77-26
Oso Wastewater Treatment Plant, Contract 4
from which it is proposed to be drawn, and such money is not appropriated for any
other purpose.
FIN 2-55
Revised 7/31/69
19 al/
TO THE MEMBERS OF THE CITY COUNCIL
Corpus Christi, Texas
Corpus Christi,
/.3 day of
For the reasons set forth in the emergency clause of the foregoing ordinance, a
public emergency and imperative necessity exist for the suspension of the Charter
rule or requirement that no ordinance or resolution shall be passed finally on
the date it is introduced, but that such ordinance or resolution shall be read
at three meetings of the City Council; I/we, therefore, request that you suspend
said Charter rule or requirement and pass this ordinance finally on the date
it is introduced, or at the present meeting of the City Council.
{
Respectfully, Respectfully,
Council Members
MAYORS
The C
%a:
y of Corpus Christi, Texas
The Charter rule was suspended by the following vote:
Luther Jones
Betty N. Turner
Jack K. Dumphy
Bob Gulley
Herbert L. Hawkins, Jr.
Dr. Charles W. Kennedy
Cliff Zarsky
The above ordinance was passed
Luther Jones
Betty N. Turner
Jack K. Dumphy
Bob Gulley
Herbert L. Hawkins, Jr.
Dr. Charles W. Kennedy
Cliff Zarsky
by the
following
vote:
1823