HomeMy WebLinkAbout16901 ORD - 02/24/1982lw;2-22-82;lst
AN ORDINANCE
AUTHORIZING THE CITY MANAGER TO EXECUTE CHANGE ORDER
, NO. 4 TO THE CONTRACT WITH SOUTHERN FOOD EQUIPMENT,
INC., FOR INSTALLATION OF KITCHEN AND CONCESSION
EQUIPMENT AT THE CORPUS CHRISTI CONVENTION CENTER
(THE PURCHASE AND INSTALLATION OF A HOT WATER HEATER
AND WATER SOFTENER IN THE KITCHEN) A SUBSTANTIAL COPY
OF SAID CHANGE ORDER BEING ATTACHED HERETO AND MADE A
PART HEREOF, MARKED EXHIBIT "A"; APPROPRIATING $9,025
OUT OF THE NO. 209 CONVENTION FACILITY BOND FUND FOR THE
AFORESAID CHANGE ORDER, APPLICABLE TO PROJECT NO. 209-
76-1.4, CONVENTION CENTER EQUIPMENT; AND DECLARING AN
EMERGENCY.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF CORPUS
CHRISTI, TEXAS:
SECTION 1. That the City Manager be and he is hereby authorized
to execute Change No. 4 to the contract with Southern Food Equipment,
Inc., for purchase and installation of a hot water heater and water softener
in the kitchen at the Corpus Christi Convention Center, a substantial copy
of which change order is attached hereto and made a part hereof, marked
Exhibit A.
SECTION 2. That there is hereby approprigWd-Dout of the No. 209
Convention Facility Bond Fund the sum of $9,025 for the above described
change order, applicable to Project No. 209-76-1.4 Convention Center
Equipment.
SECTION 3. That upon written request of the Mayor or five
Council members, copy attached, to find and declare an emergency due to
the need for efficient administration of City affairs by executing the
change order aforesaid and appropriation of sums necessalii therefor,
such finding of an emergency is made and declared requiring suspension
of the Charter rule as to consideration and voting upon ordinances or
resolutions at three regular meetings so that this ordinance is passed
and shall take effect upon first reading as an emergency measure this the
24 day of:February, 1982.
ATTEST:
y Secretary
APPROVED:
DAY OF FEBRUARY, 1982:
J. BRUCE
By
YCOCK, CT( ATTO
t4A.
16901
MAVOR
THE C OF CORPUS CHRISTI, TEXAS
SEP 2 8 1984
1.9841\flICROFILMED
SHWC, NC.
ARCHITECTS
ENGI NEERS
PLANNERS
0 10300 NORTH CENTRAL EXPWY., BLDG. 4, SUITE 100 DALLAS.TEXAS75231
0 13231 CHAMPION FOREST DR., SUITE 401 .HOUSTON,TEXAS77069
0 5314 EVERHART, SUITE 8 CORPUSCHRISTLTEXAS78411
0 1220 WEST HARRISON HARLINGEN, TEXAS 78550
0 1801. CENTRAL BLVD., P. 0. BOX 3347 BROWNSVILLE, TEXAS 78520
M
DATE: January 19, 1982
— CONTRACT DATE: February 25, 1981
CONTRACTCOMPLETIONDATE: ?lay 31, 1981
CONTRACTOR: Southern Food Equipment, Inc. PROJECT: Corpus Christi Convention Center
1611 S. Staples Street Kitchen & Concession Equipment
Corpus Christi, Texas Project #03-81310
CHANGE ORDER NUMBEFLifila___
ADD
MOM= 9.025 00 .
TO: Southern Food Equipment, Inc. CONTRACTOR
YouareauthorizedbrnakethefolIowMgchangesinthesOjectcaMatct
1. Fabricate frameof 2" x 2" x 1/4" angle iron welded 3' 0" Dx6' 0" L
with 3/4" plywood decking mounted to wall with cantilever brackets '
of angle iron construction and with stainless steel strips mounted
on front side of frame to ceiling joist ADD$ 375.00
2. Hatco Heavy Duty Hot Water Storage Heater, Model HD11-54, 185,000
BTU, 54KW with 277 G.P.H. recovery @.80° F. 480 volt/3 phase ADD$1,750.00
3. Electrical connection for Hatco Electrical Recovery Heater, from
pent house panel to heater . ADD$1,440.00
4. Plumbing connection to Hatco Recovery Heater and Water Softening
•
sysAem. Connect Recovery heater to Hatco Booseter Heater with
140H.W. By pass steam heater to dishwashing machine ADD$ 480.00
5. Miracle Water Softening Model A 45011-2 for dishwashing machine,
hot water heater, ice machine and coffee burns ADD$4,980.00
T
The amount of the contract will be (increased)X•decteassti) by.the sum of: ($ 9 ,0 25OTAL 9,025.00 . IJU
There will be an extension of Zero • days for completion. The date of completion of contract was
May 31 1981 and will now be May 31 19_.L..
AmountofOriginalConyact Total Additions TotalDeductfOns Contractto Date
$ 187.781.00 1.$ 13,524,50' —$ 0.00 .$ 201 .105 5n
OWNER:
CONTRACTOR.
ARCHITECT:
DATE.
DATE-
DATE -
f
CITY OF CORPUS CHRISTI, TEXAS
CERTIFICATION OF FUNDS
(City Charter Article IV Section 21) -
February 17, 1982
I certify to the City Council that $ 9,025 , the amount required for
the contract, agreement, obligation or expenditures contemplated in the above
and foregoing ordinance is in the Treasury of the City of Corpus Christi to the
credit of:
Fund NO. and Name No. 209 Convention Facility Bond Fund
Project NO. 209-76-1.4
Project Name Convention Center Equipment
from which it is proposed to be drawn, and such money is not appropriated for any
other purpose.
r..4.44 .4 ¥,
irector o/E7inan447
FIN 2-55
Revised 7/31/69
ty
pm we
Corpus Christi, Texas
.4,31 day o
1982
TO THE MEMBERS OF THE CITY COUNCIL
Corpus Christi, Texas
For the reasons set forth in the emergency clause of the foregoing ordinance or resolution,
an emergency exists requiring suspension of the Charter rule as to consideration and voting
upon ordinances or resolutions at three regular meetings; 1/we, therefore, request that you ,
suspend said Charter rule and pass this ordinance or resolution finally on the date it is.
introduced, or at the present meeting of the City Council.
Respectfully, Respectfully,
Council Members
The above ordinance was passed by the
Luther Jones
Betty N. Turner
Jack K. Dumphy
Bob Gulley
Herbert L. Hawkins, Jr.
Dr. Charles W. Kennedy
Cliff Zarsky
/44
40i 41/1101".'
.r4/Ardl
MA (f" dir
THE CI OF CORPUS CHRISTI, TEXAS
16901