AN ORDINANCE
AUTHORIZING THE EXECUTION OF CHANGE ORDER NO. 4 TO THE
CONTRACT WITH F & E ERECTION COMPANY, INC., FOR THE
SECOND PHASE OF THE EXPANSION OF THE OSO WASTEWATER
TREATMENT PLANT WHICH PROVIDES FOR ADDITIONAL ASPHALT AND
CONCRETE PAVEMENT; APPROPRIATING $69,598.06 FOR THE
CHANGE ORDER; AND DECLARING AN EMERGENCY.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF CORPUS CHRISTI,
TEXAS:
SECTION 1. That the City Manager be authorized to execute Change
Order No. 4 to the contract with F & E Erection Company, Inc., for the second
phase of the expansion of the Oso Wastewater Treatment Plant which provides
for additional asphalt and concrete pavement, all as more fully set forth in
Change Order No. 4, a substantial copy of which is attached hereto and made a
part hereof, marked Exhibit "A".
SECTION 2. That there is hereby appropriated $69,598.06 out of the
No. 250 Sanitary Sewer Bond Fund, Project No. 250-77-27 Oso Wastewater
Treatment Plant, Contract 5.
SECTION 3. That upon written request of the Mayor or five Council
members, copy attached, to find and declare an emergency due to the need to
take immediate action to preserve and protect public property by expediting
the construction of public improvements, such finding of an emergency is made
and declared requiring suspension of the Charter rule as to consideration and
voting upon ordinances or resolutions at three regular meetings so that this
ordinance is passed and shall take effect upon first reading as an emergency
measure this the ,day of June, 1983.
ATTEST:
y Secretary
MA
APPROVED:/4 DAY OF JUNE, 1983
THE CITY CORPUS CHRISTI, TEXAS
17658
rr
SEP 2 81984
ROFILMLD
P O. BOX 6355, 2725 SWANTNER
CORPUS CHRISTI, TEXAS 78411 PHONE 854-3101
Pollution Control Project No. W.P.C.-TEX-1214
E.P.A. Step 3 Grant No. C-48-1214
Improvements to the Oso Wastewater Treatment Plant
Corpus Christi, Texas
Contract No. 5, Treatment Plant Expansion
Second Phase of Plant Construction
CHANGE ORDER NO. 4
Job No. 9254.30
This Change Order involves the proposed paving improvements to the Oso Wastewater
Treatment Plant, and should be considered as two (2) separate items.
Item No. 1 - Substitution of the proposed heavy duty asphalt pavement section with
a 6" thick concrete pavement section.
Item No. 2 - An additional 1496 square yards of standard duty asphalt pavement
as requested by the City Wastewater Department.
PART A. NECESSITY OF THE CHANGE ORDER:
Item No. 1 - Two factors have prompted this pavement section substitution.
The first factor concerns the unpredictable and inconsistant soil con-
ditions that have been encountered in this Contract. Past evidence of
these conditions can be cited for the foundation modifications that were
required for the Sludge Dewatering Building. That foundation modifica-
tion established Change Order No. 2 to this Contract. The soil to be
encountered in the roadway construction is very expansive, and subject
to extensive lateral and vertical movement.
The second factor associated with this substitution is the extremely heavy
wheel loads to be transferred to the pavement section by the sludge
handling equipment (sludge hauling truck, 14 and 5 cubic yard containers).
Allowable wheel loads have a direct relationship to not only the type of
pavement section, but also the soil characteristics of the sub -grade
material below this pavement section.
This pavement substitution is an effort to alleviate pavement problems
common to many streets within the City subject to heavy wheel loads.
Item No. 2 - The additional standard duty asphalt pavement is at the
request of the City Wastewater Department for increased access to the
clarifier structures over and above that proposed in the Contract. This
additional pavement poses no problems with existing structures or those
structures proposed under this Contract.
i
Change Order No. 4
Page 2
PART B: DESCRIPTION OF THE WORK:
Item No. 1 - No special construction techniques will be necessary. The
proposed heavy duty equipment layout, as shown on Sheet 38 of the Construc-
tion Drawings, would be substituted with concrete pavement.
Item No. 2 - The additional standard dutu asphalt pavement would provide
increased access to the influent side of the Clarifier Structures for inlet
gate operation, scum removal operation and clean-up, scum pump maintenance,
and series pump operation.
PART C: .COST BREAKDOWN:
Item No. 1 - Pavement Section Substitution
I. MATERIALS
a. 2x6 Forms;
353 Board Feet 0 $0.39/B.F.
b. 16 Penny Nails;
200 pounds @ $0.50/Lb.
c. Nailing Stakes;
181 stakes @ $2.20/Each
d. Forming Oil;
30 gallons @ $2.40/Gal.
e. 1/2" Expansion Joint Material;
14 Sheets @ $20.45/Sheet
f. 6" Metal Keyways;
2900 Feet @ $0.52/Foot
g. Keyway Stakes;
1450 Stakes @ $0.25/Each
h. 2 x 4 Form Braces;
300 feet @ $0.27/Foot
i. 6 x 6 x 6 Welded Wire Fabric;
7278 S.Y. @ $1.08/S.Y.
j. #3 Deformed Rebar (3' Long);
1037 Bars @ $0.25/Each
k. 03 Smooth Rebar (3' Long);
329 Bars @ $0.40/Each
1. 2" Rebar Chains;
2282 Chairs @ $0.22/Each
m. #5 Bar Bolsters;
1500 Bars @ $1.03/Bar
n. #5 Dowels;
120 Dowels @ $0.69/Each
_ $ 137.67
= $ 100.00
= $ 398.20
= $ 72.00
= $ 286.30
= $1,508.00
_ $ 362.50
= $ 81.00
= $7,860.24
$ 259.25
= $ 131.60
_ $ 502.04
_ $1,545.00
= $ 82.80
nge Order No. 4
4,4'1416
Page 3
o. 4500 P.S.I. Concrete;
3308 S.Y. @ $10.808/S.Y. = $35,752.86
p. Finishing & Curing Compound;
3308 S.Y. @ $0.27/S.Y. _ $ 893.16
MATERIALS SUB -TOTAL = $49,972.62
II. LABOR:
a. Foreman;
175 Hours @ $11.00/Hr.
b. Carpenters (2);
432 Hours @ $6.00/Hr.
c. Formwork Labor;
648 Hours @ $4.60/Hr.
d. Steel Placement Labor;
1463 Hours @ $4.96/Hr.
e. Concrete Placement & Finishing Labor;
1175 Hours @ $6.00/Hr.
III EQUIPMENT
None Required
= $ 1,925.00
= $ 2,592.00
= $ 2,980.80
= $ 7,256.48
_ $ 7,050.00
= $21,804.28
IV. Credit due to the City of Corpus Christi for specified pavement
Section: (Subcontract work with overhead and profit included in
Subcontractors bid prices)
a. 3" Lime Stabilized Base;
4273 S.Y. @ $1.74/S.Y.
b. 6" Caliche Base;
4273 S.Y. @ $2.03/S.Y.
c. 3" Asphalt;
3272 S.Y. @ $3.81/S.Y.
_ $ 7,435.02
= $ 8,674.19
_ $12,466.32
CREDIT SUB -TOTAL = $28,575.53
Item No. 1 Summary;
a. Material Sub -Total
b. Labor Sub -Total
c. Credit Sub -Total
SUB -TOTAL
Taxes and Insurance for Labor @ 22%
SUB -TOTAL
= $49,972.62
_ $21,804.28
(-) = $28,575.53
= $43,201.37
= $ 4,796.94
_ $47,998.31
Profit @ 15% - = 7,199.75
Item No. 1 Total = $55,198.06
Change Order No. 4
Page 4
Item No. 2 - Additional Standard Duty Asphalt Pavement (Sub -
Contract Work)
I.
Materials; Subcontractor Labor and Equipment Included:
= $ 3,515.00
a.
6" Lime Stabilized Sub -Grade;
1496 SY @ $2.35/SY
b. 6" Caliche Base;
1496 SY @ $2.77/SY = $ 4,147.00
c. 1-1/2" Asphalt;
1145 SY @ $4.06/SY = $ 4,653.00
SUB -CONTRACTOR SUB -TOTAL
II. Prime Contractor Labor:
a. Layout Instrument Man;
16 Hours @ $6.00/Hr.
b. Laborer:
16 Hours @ $4.60/Hr.
LABOR SUB -TOTAL
SUB -TOTAL = $ 12,485.00
Taxes and Insurance for Prime Contractor's
Labor @ 22% = $ 37.00
= $ 12,315.00
_ $ 96.00
_ $ 74.00
_ $ 170.00
SUB -TOTAL
= $ 12,522.00
Profit @ 15% = $ 1,878.00
Item No. 2 total = $ 14,400.00
ITEM NO. 1 TOTAL = $ 55,198.06
ITEM NO. 2 TOTAL = $ 14,400.00
CHANGE ORDER NO. 4 TOTAL
= $ 69,598.06
THE ORIGINAL SUM WAS
THE MAXIMUM NET CHANGE BY PREVIOUS CHANGE ORDERS
THE MAXIMUM CONTRACT SUM PRIOR TO THIS CHANGE ORDER WAS
THE CONTRACT AMOUNT WILL BE INCREASED BY THIS CHANGE ORDER
$ 6,685,759.00
$ 34,951.86
$ 6,720,710.86
$ 69,598.06
MillPagenge5 Order No. 4
•
THE NEW CONTRACT AMOUNT INCLUDING THIS CHANGE ORDER
THE ORIGINAL COMPLETION TIME WAS
THE NET CHANGE BY PREVIOUS CHANGE ORDERS
THE COMPLETION TIME PRIOR TO THIS CHANGE ORDER WAS
THE COMPLETION TIME WILL BE INCREASED BY THIS CHANGE ORDER
THE (CONTRACCT\,COMPLETION TIME INCLUDING THIS CHANGE ORDER
1
ENGINEER:
BY:
\ n.
Larry J. Urban P.E.
Partner /
5 -
Date:
OWNER:
CITY OF CORPUS CH•ISTI/
BY:
J s K. Lantos, P.
istant City Manager
CONTRACTOR:
BY:
$ 6,790,308.92
500 Working Days
500 Working Days
500 Working Days
Vance Davis
Project Superintendent�j
Date: 5- 24' - OJ
CITY OF CORPUS CHRISTI, TEXAS
CERTIFICATION OF FUNDS
(City Charter Article IV Section 21)
June 22, 1983
I certify to the City Council that $ 69,598.06 , the amount required for
the contract, agreement, obligation or expenditures contemplated in the above
and foregoing ordinance is in the Treasury of the City of Corpus Christi to the
credit of:
Fund No. and Name
Project No.
Project Name
250 - Sanitary Sewer Bond Fund
250-77-27
Oso Wastewater Treatment Plan+ r- -'-.c- nuc 5
from which it is proposed to be drawn, and such money is not appropriated for any
other purpose.
r
41
FIN 2-55
Revised 7/31/69
y/,19 '
Corpus Christi, Te
.207/4 day of
IP
, 1983
TO THE MEMBERS OF THE CITY COUNCIL
Corpus Christi, Texas
For the reasons set forth in the emergency clause of the foregoing ordinance
or resolution, an emergency exists requiring suspension of the Charter rule
as to consideration and voting upon ordinances or resolutions at three
regular meetings; I/we, therefore, request that you suspend said Charter rule
and pass this ordinance or resolution finally on the date it is introduced,
or at the present meeting of the City Council.
Respectfully,
Council Members
Respectfully,
THE CITY dF CORPUS CHRISTI, TEXAS