HomeMy WebLinkAbout17880 ORD - 10/12/1983AN ORDINANCE
AUTHORIZING THE EXECUTION OF CHANGE ORDER NOS. 5, 7, 8, 9,
10, 11, and 15 TO THE CONTRACT WITH F & E ERECTION COMPANY,
INC. FOR THE SECOND PHASE OF THE EXPANSION AT THE OSO
WASTEWATER TREATMENT PLANT; APPROPRIATING $133,087.06; AND
DECLARING AN EMERGENCY.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF CORPUS CHRISTI,
TEXAS:
SECTION 1. That the City Manager be authorized to execute Change
Order Nos. 5, 7, 8, 9, 10, 11, and 15 to the contract with F & E Erection
Company, Inc. for the second phase of the expansion at the Oso Wastewater
Treatment Plant, copies of which change orders are attached hereto and made a
part hereof marked Exhibits "A", "B", "C", "D", "E", "F", and "G"
respectively.
SECTION 2. That there is hereby appropriated $133,087.06 from the
No. 250 Sanitary Sewer Bond Fund applicable to Project No. 250-77-27, Oso
Wastewater Treatment Plant, Contract 5.
SECTION 3. That upon written request of the Mayor or five Council
members, copy attached, to find and declare an emergency due to the need to
take immediate action to preserve and protect public property by expediting
the construction of public improvements, such finding of an emergency is made
and declared requiring suspension of the Charter rule as to consideration and
voting upon ordinances or resolutions at three regular meetings so that this
ordinance is passed and shall take effect upon first reading as an emergency
measure this the 12th day of October, 1983.
ATTEST:
Ci y Secretary
APPROVED:) '—DAY OF OCTOBER, 1983
"Bruce ycock, Ciy 't orney
•
MAY RI'to I / J ��7Z A ki L
THE CITY OF CORPUS CHRISTI, TEXAS
17$60
SEP 2 81984
Attali 1LMED
FR N
ENGINEERING
CORPUS CHRISTI, TEXAS
P O. BOX 6355, 2725 SWANTNER
CORPUS CHRIST!, TEXAS 78411 PHONE 854-3101
Pollution Control Project No. W.P.C.-TEX-1214
E.P.A. Step 3 Grant No. C-48-1214
Improvements to the Oso Wastewater Treatiaent Plant
Corpus Christi, Texas
Contract No. 5, Treatment Plant Expansion
Second Phase of Plant Construction
CHANGE ORDER NO. 5
Job No. 9254.30
PART A: NECESSITY OF THE CHANGE ORDER:
Item No. 1 - This Change Order involves lowering of the clarifier
influent target walls to aid in scum removal from the clarifiers to
the plant's digestive system. Lowering of these target walls will
allow for increased scum flow to the slotted pipe skimmer, and
eliminate the "dead area" that now exists at the influent side of
the dlarifiers. The target walls on both the east and west plants
are proposed to be lowered by this Change Order.
PART B: DESCRIPTION OF THE WORK:
The clarifier reinforced concrete target walls will be saw cut with
special equipment and grout will be placed over the cut surface to
provide for smooth wall edges.
PART C: COST BREAKDOWN:
I. Materials:
a. Scaffold Brackets
6 Brackets @ $89.00/Each
b. 2 x 12 Walk Boards
360 Board Feet @ $0.43/B.F.
c. 2 x 4 Board Handrails
45 Board Feet @ $0.35/B.F.
d. 2 x 4 Forms
63 Board Feet @0.35/B.F.
e. Form Anchors
480 Anchors @ $0.75/Each
_ $ 534.00
$ 154.80
• $ 15.75
$ 22.05
• $ 360.00
Eh 17.,�ne
hange Order No. 5
gage 2
f. Grout
45 Cubic Feet @ $3.00/C.F.
g. Epoxy
6 Gallons @ $15.00/Gal.
• $ 135.00
• $ 90.00
MATERIAL SUB -TOTAL $ 1,311.60
II. Labor
a. Foreman
92 Hours @ $11.50/Hr.
b. Carpenters
60 Hours @ $6.00/Hr.
c. Finishers
60 Hours @ $6.50/Hr.
d. Laborers
286 Hours @ $4.60/Hr.
e. Operators
90 Hours 0 $8.00/Hr.
f., Surveyor
22 Hours @ $8.00/Hr.
•
g. Rodman
22 Hours @ $4.60/Hr.
LABOR SUB -TOTAL
III. Equipment:
a. 25 Ton Crane
90 Hours 0 $30.15/Hr. •
b. Crew/Equipment Truck
9 Hours @ $25.00/Hr. _
c. Air Compressor w/Tools
60 Hours @ $11.00/Hr.
• $ 1,058.00
• $ 360.00
• $ 390.00
• $ 1,315.60
• $ 720.00
• $ 176.00
• $ 101.20
• $ 4,120.80
• • $ 2,713.50
• $ 225.00
• $ 660.00
EQUIPMENT SUB -TOTAL $ 3,598.50
IV. Sub -Contractor -
Labor & Equipment Included
Saw 300 Feet of
Concrete Wall @ $31.50/Ft.
• $ 9,450.00
hange Order No. 5
age 3
SUB -CONTRACTOR SUB -TOTAL
SUB -TOTAL
Taxes & Insurance For
Labor @ 22% of $4,120.80
SUB -TOTAL
Profit @ 15%
CHANGE ORDER #5 TOTAL
$ 9,450.00
$ 18,480.90
$ 906.58
$ 19,387.48
= 2,908.12
_ $ 22,295.60
THE ORIGINAL SUM WAS
THE MAXIMUM NET CHANGE BY PREVIOUS CHANGE ORDERS
THE MAXIMUM CONTRACT SUM PRIOR TO THIS CHANGE ORDER WAS
THE CONTRACT AMOUNT WILL BE INCREASED BY THIS CHANGE ORDER
THE NEW CONTRACT AMOUNT INCLUDING THIS CHANGE ORDER
THE ORIGINAL COMPLETION TIME -WAS
THE NET CHANGE'BY,PREVIOUS CHANGE ORDERS
THE COMPLETION TIME PRIOR TO THIS CHANGE ORDER WAS
THE COMPLETION TIME WILL BE INCREASED BY THIS CHANGE ORDER
THE
ENGI
BY:
T COMPLETION TIME INCLUDING THIS CHANGE ORDER
CONTRACTOR:
BY
L ry J.
Partner
P.E.
Date: August 25, 1983
OWNER: •
CITY OF CORPUS CHRISTI
BY:
James K. Lontos, P.E.
Assistant City Manager
Date:
$ 6,685,759.00
$ 104,549.92
$ 6,790,308.92
$ 22,295.60
$ 6,812,604.52
500 Working Days
500 Working Days
500 Working Days
Vance Davis
Project Superintendent
Date: August 25, 1983
1'
P.O. BOX 6355, 2725 SWANTNER
CORPUS CHRISTI. TEXAS 78411 PHONE 854-3101
Pollution Control Project No. W.P.C.-TEX-1214
E.P.A. Step 3 Grant No. C-48-1214
Improvements to the Oso Wastewater Treatment Plant
Corpus Christi, Texas
Contract No. 5, Treatment Plant Expansion
Second Phase of Plant Construction
CHANGE ORDER NO. 7
PART A: NECESSITY OF THE CHANGE ORDER:
Job No 9254.30
This Change Order involves additional heavy-duty chain link fencing to the
Oso W.W.T.P. at the request of the City of Corpus Christi.
PART B: DESCRIPTION OF THE WORK:
Additional chain link fencing will be installed at five different locations
on the Oso W.W.T.P. site.
One Thousand Five Hundred feet (1500') will be installed on the west side of
the plant site to replace existing fencing that has deteriorated. In this
new section, a 24' wide double gate will be installed for plant site access.
At the South Outdoor Switchgear, Forty -Eight feet (48') of fence and one •
Sixteen feet (16') wide gate will be installed. The East Outdoor Switchgear
will also be fenced and one Sixteen feet (16') wide gate. The transformer
bank adjacent -to Lift Station #2 will be fenced with Thirty -Three feet
(33') of fence and one Twenty -Four feet (24') wide gate. One Thousand
Two Hundred Forty -Five (1,245) feet of fence will be installed between the
new plant entrance road and the back of Pharoah Valley Subdivision,
paralleling Nile Road. This new section of fence will include a 30' wide
gate at the entrance road. Finally, a 30' wide gate will be installed at
the entrance off Ennis JosIin Road. -
PART C: COST BREAKDOWN:
I. Labor for removing existing fence and layout work for new fencing.
a. Foreman
8 hours @ $11.50/hr.
b. Operator
8 hours @ $8.00/hr.
c. Laborers (2)
16 hours @ $4.60/hr
_'$ 92.00
_ $ 64.00
a $ 73.60
�xb."(3"
.ange Order 8 '7
•
Page 2
d. Surveyor
20 hours @ $8.00/hr. = $160.00
e. Rodman
20 hours @4.60/hr. _ $ 92.00
LABOR SUB -TOTAL = $481.60
II. Equipment for removing existing fence.
a. Front, End Loader
8 hours @ $21.93/hr. = $175.44
b. Flat Bed Truck
4 hours @ $6.59/hr. _ $ 26.36
EQUIPMENT SUB -TOTAL = $201_80
III. Subcontract for installation of new fencing and gates. The unit prices
include the subcontractor's labor, equipment, and materials_
a. Heavy -Duty Chain -Link Fence
2,874 feet @ $8.00/ft.
b. 30' Wide Gate
2 Gates @ $1,000.00/each
c. 24' Wide Gate
2 Gates @ $1,000.00/each
d. 16' Wide Gate
2 Gates @ $750.00/each
= $22,992.00
= $ 2,000.00
= $ 2,000.00
= $ 1,500.00
SUBCONTRACT SUB -TOTAL = $28,492.00
SUB -TOTAL = $29,175.40
Payroll Taxes & Insurance for _
Labor @ 22% of $481.60 = $ 105.95
SUB -TOTAL
PROFIT 0 15%
-CHANGE ORDER 117 TOTAL
= $29,28I.35
= $ 4,392.20
= $33,673.55
Change Order ill '
Page 3
THE ORIGINAL SUM WAS
THE MAXIMUM NET CHANGE BY PREVIOUS CHANGE ORDERS
THE MAXIMUM CONTRACT SUM PRIOR TO THIS CHANGE ORDER WAS
THE CONTRACT AMOUNT WILL BE INCREASED BY THIS CHANGE ORDER
THE NEW CONTRACT AMOUNT INCLUDING THIS CHANGE ORDER
THE ORIGINAL COMPLETION TIME WAS
THE NET CHANGE BY PREVIOUS CHANGE ORDERS
THE COMPLETION TIME PRIOR TO THIS CHANGE ORDER WAS
THE COMPLETION TIME WILL BE INCREASED BY THIS CHANGE ORDER
THP2COATRACT COMPLETION TIME INCLUDING THIS CHANGE ORDER
ENGINEER: \l
URBAN ENGINEERING F & E ERECTN
CONTRACTOR:
BY:
Larry J.
Partner
an,P.E.
Date: August 29, 1983
OWNER:
CITY OF CORPUS CHRISTI
BY:
Date:
James K. Lontos, P.E.
Assistant City Manager
BY:
$6,685,759.00
$ 148,549.23
$6,834,308.23
$ 33,673.55-
$6,867,981.78
500 Working Days
500 Working- Days
500 Working- Days
Vance Davis
Project Superintendent
Date: August 29, 1983
P.O. BOX 6355, 2725 SWANTNER
CORPUS CHRISTI, TEXAS 78411 PHONE 854-3101
Pollution Control Project No. W.P.C.-TEX-1214
E.P.A. Step 3 Grant No. C-48-1214
Improvements to the Oso Wastewater Treatment Plant
Corpus Christi, Texas
Contract No. 5, Treatment Plant Expansion
Second Phase of Plant Construction
CHANGE ORDER NO. 8
PART A: NECESSITY OF THE CHANGE ORDER:
Job No, 9254.30
This Change Order involves structural repairs to an existing junction box
on the plant effluent line at the request of the City of Corpus Christi.
The junction box is located on the plant's existing 72" R.C.P. effluent
line at plant coordinates 56+52N and 112+32E, and shown orr Sheet 24 of
the construction drawings.
PART B: DESCRIPTION OF THE WORK:
The northern most corner of the junction box has deteriorated to such a
degree that one-half of the concrete wall section is gone, and reinforcing
steel exposed. New reinforcing steel will be doweled into existing walls,
concrete formwork installed, and epoxy grout placed to repair the box
corner.
PART C: COST BREAKDOWN:
I. Materials:
a. Scaffolding
1 Lump Sum @ $80.00
b. Reinforcing Steel
180 Pounds @ $0.20/LB.
c. Epoxy
1 Gallon @ $15.00/Gal.
d. Grout
•
27 Cubic Feet @ $3.00/C.F.
= $ 80.00
= $ 36.00
= $ 15.00
_ $ 81.00
MATERIAL SUB -TOTAL = $ 212.00
b. t'
flange Order No. 8
ige 2
II. Labor
a. Foreman
32 Hours @ $11.50/Hr. _ $ 368.00
b. Finisher
24 Hours @ $7.00/Hr. = $ 168.00
c. Ironworker
4 Hours @ $5.00/Hr. _ $ 20.00
d. Laborers
36 Hours @ $4.60/Hr. _ $ 165.60
LABOR SUB -TOTAL = $ 721.60
III. Equipment
Air Compressor w/Tools
16 Hours @ $6.68/Hr.
EQUIPMENT SUB -TOTAL
SUB -TOTAL
Payroll Taxes & Insurance
@ 220 of $721.60
= $ 106.88
= $ 106.88
$ 1,040.48
_ $ 158.75
SUB -TOTAL $ 1,199.23
Profit @ 15%
CHANGE ORDER NO. 8 TOTAL
THE ORIGINAL SUM WAS
THE MAXIMUM NET CHANGE BY PREVIOUS CHANGE ORDERS
THE MAXIMUM CONTRACT SUM PRIOR TO THIS CHANGE ORDER WAS
THE CONTRACT AMOUNT WILL BE INCREASED BY THIS CHANGE ORDER
THE NEW CONTRACT AMOUNT INCLUDING THIS CHANGE ORDER
THE ORIGINAL COMPLETION TIME WAS
THE NET CHANGE BY PREVIOUS CHANGE ORDERS
THE COMPLETION TIME PRIOR TO THIS CHANGE ORDER WAS
THE COMPLETION TIME WILL BE INCREASED BY THIS CHANGE ORDER
THE CONTRACT COMPLETION TIME INCLUDING THIS CHANGE ORDER
= $ 179.88
_ $ 1,379.11
$ 6,685,759.00
$ 182,222.78
$ 6,867,981.78
$ 1,379.11
$ 6,869,360.89
500 Working Days
500 Working Days
500 Working Days
range Order No. 8
jge 3
ENGIN ER: CONTRACTOR:
URBAN ENGINEERING
BY:
p
La ry J. Urb
Partner
Date: August 29, 1983
OWNER:
CITY OF CORPUS CHRISTI
BY:
James K. Lontos, P.E.
Assistant City Manager
Date:
F & E ERECTSONJCOMPANY
BY:
Vance Davis
Project Superintendent
Date: August 29, 1983
LINEMAN
ENGINEERING
CORPUS CHRISTI, TEXAS
P.O. BOX 6355, 2725 SWANTNER
CORPUS CHRISTI. TEXAS 78411 PHONE 854-3101
Pollution Control Project No. W.P.C.-TEX-1214
E.P.A. Step 3 Grant No. C-48-1214
Improvements to the Oso Wastewater Treatment Plant
Corpus Christi, Texas
Contract No. 5, Treatment Plant Expansion
Second Phase of Plant Construction
CHANGE ORDER NO. 9
Job No. 9254.30
PART A: NECESSITY OF THE CHANGE ORDER:
This Change Order involves replacement of existing suction and discharge
valves with new valves in both Lift Stations 01 & 02 as requested by the
City of Corpus Christi. It was the intent of the original contract to
reuse ,the existing valves in both lift stations. However, at this time,
several valves are inoperable and others have deteriorated beyond repair_
PART B: DESCRIPTION OF THE WORK:
No special construction techniques will be required. Lift Station 01
will receive: Two new 18" gate valves on the suction piping, and two
new 18" gate valves with chain operators on the discharge piping. Lift
Station 02 will receive: two new 24" gate valves, one new 20" gate
valve, and one new 16" gate valve on the suction piping, and one new
24" gate valve with chain operator, one new 20" gate valve with chain
operator, and one new 14" gate valve with chain operator on the discharge
piping. The pressure relief line back into the lift station wet well
will receive one new 12" gate valve and one new 12" check valve. A total
of thirteen (13) existing valves will be replaced with new valves.
PART C: COST BREAKDOWN:
I. Materials:
a. 24" Gate Valve w/Chain Operator
1 valve @ $5,295.00/Each
b. 24" Gate Valve
2 Valves @ $4,700.00/Each
c. 20" Gate Valve w/Chain Operator
1 Valve @ $3,720.00/Each
d. 20" Gate Valve
1 Valve @ $3,125.00/Each
= $ 5,295.00
= $ 9,400.00
_ $ 3,720.00
= S 3,125.00
hange Order No. 9
gage 2
e. 18" Gate Valve w/Chain Operator
2 Valves @ $2,838.00/Each
f. 18" Gate Valve
2 Valves @ $2,243.00/Each
g. 16" Gate Valve
1 Valve @ $1,700.00/Each
h. 14" Gate Valve w/Chain Operator
1 Valve @ $1,933.00/Each
i. 12" Gate Valve
• 1 Valve @ $1,000.00/Each
3•
12" Check Valve
1 Valve @ $1,600.00/Each
k. 24" Bolt Set
2 Sets @ $93.40/Set
= $ 5,676.00
= $ 4,186.00
= $ 1,700.00
= $ 1,933_00
= $ 1,000.00
$ 1,600.00
$ 186_80
1. 20" Bolt Set
1 Set @ $41.52/Set $ 41.52
m. 18" Bolt Set
4 Sets @ $36.96/Set
n. 16" Bolt Set
1 Set @ $27.72/Set
o. 12" Bolt Set
6 Sets @ $19.80/Set
p. 24"• Gasket
2 Gaskets @ $7.00/Each
q. 20" Gasket
1 Gasket @ $6.70/Each
r. 18" Gasket
4 Gaskets @ $5.70/Each
s. 16" Gasket
1 Gasket @ $5.25/Each
t. 12" Gasket
6 Gaskets @ $4.50/Each
= $ 147.84
_ $ 27.72
= $ 118.80
$ 14.00
$ 6.70
$ 22.80
= $ 5.25
$ 27_00
u. 18" Spool Piece
2 Spools @ $600.00/Each = $ 1,200.00
MATERIAL SUB -TOTAL = $39,733_43 '
'range Order No. 9
age 3
II. Labor
a. Foreman
301 Hours @ $11.50/Hr. = $ 3,461.50
b. Pipefitter
289 Hours @ $11.93/Hr. $ 3,447.77
c. Operator
26 Hours @ $8.00/Hr. $ - 208.00
d. Laborer
134 Hours @ $5.18/Hr. = $ 694.12
LABOR SUB -TOTAL = $ 7,811.39
III. Equipment
a. Pneumatic Wrench w/Compressor
73 Hours 0 $13.75/Hr. = $ 1,003.75
b. Crane
26 Hours @ $30.15/Hr. = $ 783.90
F. Flat Bed Truck
16 Hours @ $6.59/Hr. = $ 105.44
EQUIPMENT SUB -TOTAL $ 1,893.09
IV. Subcontract Work for Va1ve Disassembly and
Cleaning, and Pipe Rental for Extra
By -Pass Pumping
a. Valve Disassembly & Cleaning
1 Lump Sum @ $351.60
b. Pipe Rental
2 Weeks @ $400.00/Wk.
SUBCONTRACT SUB -TOTAL
SUB -TOTAL
Payroll Taxes & Insurance
@ 22% of $7,811.39
SUB -TOTAL
Profit @ 15%
$ 351.60
$ 800.00 -
$ 1,151.60
_ $ 50,589.51
$ 1,718.51
$ 52,308.02
= $ 7,846.20
CHANGE ORDER NO. 9 TOTAL = $ 60,154.22
THE ORIGINAL'SUM WAS
$ 6,685,759.00
THE MAXIMUM NET CHANGE BY PREVIOUS CHANGE ORDERS - $ 183,601.89
'Mange Order No. 9
age 4
THE MAXIMUM CONTRACT SUM PRIOR TO THIS CHANGE ORDER WAS ,
THE CONTRACT AMOUNT WILL BE INCREASED BY THIS CHANGE ORDER
THE NEW CONTRACT AMOUNT INCLUDING THIS CHANGE ORDER
THE ORIGINAL COMPLETION TIME WAS
THE NET CHANGE BY PREVIOUS CHANGE ORDERS
THE COMPLETION TIME PRIOR TO THIS CHANGE ORDER WAS
THE COMPLETION TIME WILL BE INCREASED BY THIS CHANGE ORDER
THE CONTRACT COMPLETION TIME INCLUDING THIS CHANGE ORDER
$ 6,869,360.89
$ 60,154.22
$ 6,929,515.11
500 Working Days
500 Working Days
500 Working Days
ENGIIS'EER: \ CONTRACTOR:
URBAN\,ENGINEE INC F & E ERECTION COMPANY
BY: ' Walt\ BY: e__,
-_
Vance Davis -
Project Superintendent
La ry J. Urban,
Partner •
Date:
8-29-S3
OWNER:
CITY OF CORPUS CHRISTY
BY:
James K. Lontos, P.E.
Assistant City Manager
Date:
Date: 8-23 - .03
P.O. BOX 6355. 2725 SWANTNER
CORPUS CHRISTI. TEXAS 78411 PHONE 854-3101
Pollution Control Project No. W.P.C.-TEX-1214
E.P.R. Step 3 Grant No. C-48-1214
Improvements to the Oso Wastewater Treatment Plant
Corpus Christi, Texas
Contract No. 5, Treatment Plant Expansion
Second Phase of Plant Construction
CHANGE ORDER NO. 10
PART A: NECESSITY OF THE CHANGE ORDER:
Job No. 9254.30
This Change Order involves additional modifications to the bar screen/grit
removal structure as requested by the City of Corpus Christi. The original
contract -included minor modifications to the existing bar screen/parshall
flume structure, however, to aid in aesthetics and possibly increase safety,
the Owner has requested that additional modifications be performed.
PART B: DESCRIPTION OF THE WORK:
Approximately 20' of an existing 9" concrete wall will be demolished and
disposed of off-site. In addition, a total of 20' of concrete retaining
wall will be constructed at three different locations. At the south end of.
this structure, 12' of retaining wall will be built connecting the east
side of the existing parshall flume to the southwest corner of the modified
grit removal basin. Located at the north end of this structure, 4' of
retaining wall will be built connecting the northeast corner of the old
bar screen to the northwest corner of the modified grit removal basin.
Finally, 4' of retaining wall will be constructed immediately south of the
stair landing on the west side of the modified grit removal basin. After
completion of the 3 new retaining walls, fill material will be placed
between the old bar screen/parshall flume structure and the modified grit
removal basin. The fill material will be brought up to the top of the
existing and new retaining walls.
PART C: COST BREAKDOWN:
I. Materials
a. 3/4" Plywood Forms
3 Sheets @ $14.72/Each
b. 2 x 4 Form Bracing
41 Board Feet @ $0.35/B.F.
c. Reinforcing Steel
149 Pounds@ $0.20/LB.
$ 44.16
= $ 14.35
= $ 29.80
2nge Order No. 10
rage 2 .
d. Epoxy
1 Gallon 0 $15.00/Gal.
e. 3000 p.s.i. Concrete
2 Cubic Yards @ $50.75/C.Y.
f. Form Ties
80 Square Feet @ $0.11/S.F.
II. Labor
= $ 15.00
$ 101.50
= $ 8.80
MATERIAL SUB -TOTAL $ 213.61
a. Foreman
27 Hours @ $11.50/Hr.
b. Operators
9 Hours @ $8.00/Hr.
c. Carpenter
22 Hours @ $6.00/Hr.
d. Ironworker
3 Hours @ $4.96/Hr.
e. 'Finisher
7 Hours 0 6.50/Hr.
f. Laborers
81 Hours 0 $4.60/Hr.
III. Equipment
= $ 310.50
S 72.00
= $ 132.00
= - $ 14.88
= $ 45.50
_ $ 372.60
LABOR SUB -TOTAL = $ 947.48
a. Air Compressor
8 Hours @ $6.68/Hr.
b. Crane
1 Hour 0 $30.15/Hr.
c. Flat Bed Truck
1 Hour @ $6.59/Hr.
= $ 53.44
_ $ 30.15
= $ 6.59
d. Front End Loader
8 Hours @ $21.93/Hr. _ $ - 175.44
e. Plate Compactor
8 Hours @ $2.25/Hr.
= $ 18.00
f. Dump Truck (Rental)
4 Hours -0 $25.00/Hr. - = $ 100.00
EQUIPMENT SUB -TOTAL = $ 383.62
cuange Order No.'10
Page 3
IV. Sub -contract Work
Painting of Concrete Walls:
1 Lump Sum @ $160.00 = $ 160.00
SUB -CONTRACT SUB -TOTAL
SUB -TOTAL
$ 160.00
= $ 1,704.71
Payroll Taxes & Insurance
8 22% of $947.48 $ 208.45
SUB -TOTAL
Profit @ 15%
CHANGE ORDER #10 TOTAL
$ 1,913.16
= $ 286.97
$ 2,200.23
THE ORIGINAL CONTRACT SUM WAS $ 6,685,759.00
THE MAXIMUM NET CHANGE BY PREVIOUS CHANGE ORDERS $ 243,756.11
THE MAXIMUM CONTRACT SUM PRIOR TO THIS CHANGE ORDER WAS $ 6,929,515.11
THE CONTRACT AMOUNT WILL BE INCREASED BY THIS CHANGE ORDER $ 2,200.13
THE NEW CONTRACT AMOUNT INCLUDING THIS CHANGE ORDER $ 6,931,715.24
THE ORIGINAL COMPLETION TIME WAS
THE NET CHANGE BY PREVIOUS CHANGE ORDERS
THE COMPLETION TIME PRIOR TO THIS CHANGE ORDER WAS
THE COMPLETION TIME WILL BE INCREASED BY THIS CHANGE ORDER
THE CONTRACT COMPLETION TIME INCLUDING THIS CHANGE ORDER
500 Working Days
500 Working Days
500 Working Days
ENG NEER:
URBAN ENG
BY:
CONTRACTOR:
BERING F & E ERECTION COMP
arry J. .an
Partner
Date: August 3', 1983
OWNER:
CITY OF CORPUS CHRISTI
BY:
James K. Lontos, P.E.
Assistant City Manager
BY:
Vance Davis
• Project Superintendent
Date: August 30, 1983
u• ga BAN
ENGINEERING
CORPUS CHRISTI. TEXAS
P.O. BOX 6355, 2725 SWANTNER
CORPUS CHRISTI, TEXAS 78411 PHONE 854-3101
Pollution Control Project No. W.P.C.-TEX-1214
E.P.A. Step 3 Grant No. C-48-1214
Improvements to the Oso Wastewater Treatment Plant
Corpus Christi, Texas
Contract No. 5, Treatment Plant Expansion
Second Phase of Plant Construction
CHANGE ORDER NO. 11
PART A: NECESSITY OF THE CHANGE ORDER:
Job No. 9254.30
This Change Order involves the addition of two valves to the existing-
east
xistingeast chlorine contact chambers sludge pump house, and the elimination of
a cross connection on the suction piping outside the sludge pump house.
These modifications will greatly increase the pumping flexibility of
this pump house by allowing either sludge pump to pump down either or
both ch'orine.contact chambers.
_ t
PART B: _DESCRIPTION OF THE WORK:
On the existing suction piping of each sludge pump, a 6" gate valve with
a make-up coupling will be installed. On the existing suction piping
just outside the pump house, a buried 10" cross connection line will be •
uncovered, cut and capped with 10" mechanical joint caps. Concrete thrust
will then be installed for the 10" caps.
PART C: COST BREAKDOWN:
I. -Materials:
a. 6" Gate Valve
2 Valves @ $197.68/Each = $ 395.36
b. 6" Coupling
3 Couplings 0 $41.42/Each = $ 124.26
c. 6" Bolt & Gasket Set
10 Sets @ $7.00/Each = $ 70.00
d. 10" M.J. Cap
2 Caps @ $50.09/Each = $ 100.18
ge Order No. 11
2
e. 3000 p.s.i. Concrete
0.5 Cubic Yards @ $50.75/C.Y. _ $ 25.38
MATERIAL SUB -TOTAL = $ 715_18
II. Labor;
a. Foreman
30 Hours @ $11.50/Hr.
b. Operator
4.5 Hours @ $8.00/Hr.
c. Pipefitter
49 Hours @ $9.20/Hr.
d. Ironworker
10 Hours @ $6.00/Hr.
e. Laborer
5.5 Hours @ $4.6O/Hr.
LABOR SUB -TOTAL
III. Equipment
= $ 345.00
_ $ 36.00
$ 450.80
= $ 60.00
$ 25_30
917.10
680 Backhoe
4.5 Hours @ $18.18/Hr. = $ 81.81
EQUIPMENT SUB -TOTAL = $ 81.81
SUB -TOTAL $ 1,714.09
Payroll Taxes & Insurance
@.22% of $917.10
= $ 2OI.76
SUB -TOTAL = _ $ 1,915.85
Profit @ 15%
CHANGE ORDER #11 TOTAL
$ 287.38
$ 2,203.23
THE ORIGINAL CONTRACT SUM WAS $ 6,685,759_00
THE MAXIMUM NET CHANGE BY PREVIOUS CHANGE ORDERS $ 245,956.24
THE MAXIMUM CONTRACT SUM PRIOR TO THIS CHANGE ORDER WAS $ 6,931,715_24
THE CONTRACT AMOUNT WILL BE INCREASED BY THIS CHANGE ORDER $ 2,203.23
THE NEW CONTRACT AMOUNT INCLUDING THIS CHANGE ORDER $ 6,933,918_47
THE ORIGINAL COMPLETION TIME WAS _ 500 Working Days
THE NET CHANGE BY PREVIOUS CHANGE ORDERS -0-
Change.Order No. I1
Page 3
THE COMPLETION TIME PRIOR TO THIS CHANGE ORDER WAS 500 Working Days
THE COMPLETION TINE WILL BE INCREASED BY THIS CHANGE ORDER
THE CONTRACT COMPLETION TIME INCLUDING THIS CHANGE ORDER 500 Working Days
EN<INEE' CONTRACTOR:
UR:•N ENG VEERING F & E ERECTION
BY: •rr JBY:
Bobby D. Greaves
Project Engineer
Date:
Larry J T ban, P.E.
Partner
August 31, 1983
OWNER:
CITY OF CORPUS CHRISTI
BY:
Date:
James K. Lontos, P.E.
Assistant City Manager
Date: August 3I, 1983
P.O. BOX 6355, 2725 SWANTNER
CORPUS CHRISTI, TEXAS 78411 PHONE 854-3101
Pollution Control Project No. W.P.C.-TEX-1214
E.P.A. Step 3 Grant No. C-46-1214
Improvements to the Oso Wastewater Treatment Plant
Corpus Christi, Texas
Contract No. 5, Treatment Plant Expansion
Second Phase of Plant Construction
CHANGE ORDER NO. 15
PART A: NECESSITY OF THE CHANGE ORDER:
Job No. 9254.30
This Change Order involves demolition of existing concrete structures
and removal of miscellaneous existing above ground piping, as requested
by the City of Corpus Christi. The original contract required simply that
these concrete structures and piping be abandoned.
PART B: DESCRIPTION OF THE WORK:
__The work involving this Change Order will include demolition to 2'
below existing grade of the following concrete structures:
1. Parshall Flume; Coordinates
54+41N and 106+405
*2. Parshall Flume; Coordinates
55+27N and 106+35E
*3. Parshall Flume; Coordinates
56+07N and 106+35E
*4. Parshall Flume; Coordinates
57+07N and 106+31E
5. Diversion Box; Coordinates
54+93N and 105+52E
6. Diversion Box; Coordinates
56+54N and 105+52E
7. Diversion Box; Coordinates
57+74N and 106+43E
8. Gatewell; Coordinates
54+93N and 106+28E
9. Gatewell; Coordinates
56+54N and 106+28E
Exb. '
Page 2
10. Gatewell; Coordinates .
57+398 and 105+46E
11. Flow Meter Box; Coordinates
54+92N and 105+44E
12. Flow Meter Box; Coordinates
55+038 and 105+52E
13. Flow Meter Box; Coordinates
56+40N and 105+52E
14. Flow Meter Box; Coordinates
56+548 and 105+39E
15. Flow Meter Box; Coordinates
54+848 and 106+288
*One of the parshall flumes will be completely demolished to 2' below
existing grade. Concerning the remaining three parshall flumes noted by
the asterisk above, only 80% of these flumes will be demolished below
grade because of an existing live 48" D.I.F. The flowline of the 48"
D.I.P. will not allow for below grade demolition. Therefore, a reinforced
concrete wall will be constructed, forming a new junction box at the east
end of the flumes. Finally, a reinforced concrete slab will be poured
over each of the three new junction boxes.
Additional work involving this Change Order will include removal of
miscellaneous existing above ground piping on the east side of Pre -
Thickeners #1 and #2.
PART C: COST. BREAKDOWN:
Materials
a. Grout
8 Cubic Feet @ $3.00/C.F. _ $ 24.00
b. Plywood
1 Sheet @ $14.72/Sheet = $ 14.72
c. 2 x 6 Boards
20 Board Feet @ $0.37/B.F. _ $ 7.40
d. Reinforcing Steel
209 Pounds 0 $0.20/LB. = $ 41.80
e. 3000 p.s.i. Concrete
13 Cubic Yards 0 $50.75/C.Y. = $ 659.75
f. Sand
70 Tons @ $5.00/Ton = $ 350.00
MATERIAL SUB -TOTAL = $ 1,097.67
II. Labor
a. Foreman
94 Hours @ $11.50/Hr. _ $ 2,081.00
Change Order No. 15
Page 3
b. Operators
158 Hours @ $8.00/Hr. = $ 1,264.00
c. Finishers
10 Hours @ $6.50/Hr.
d. Ironworker
11 Hours @ $6.00/Hr.
e. Carpenter
4 Hours @ $6.00/Hr.
= $ 65.00
$ 66.00
$ 24.00
f. Laborers
226 Hours @ $4.60/Hr. = $ 1,039.60
LABOR SUB -TOTAL = $ 3,539.60
III. Equipment
a. 680 Backhoe w/Hoe Ram
134 Hours @ $24.43/Hr. = $ 3,273.62
b. Front End Loader
24 Hours @ $21.93/Hr.
c. Air Compressor w/Tools
- 16 Hours @ $6.68/Hr.
t,
IV. Subcontract
= $ 526.32
_ $ 106.88
EQUIPMENT SUB -TOTAL = $ 3,906.82
Rental Dump Truck
16 Hours @ $25.00/Hr. = $ 400.00
SUBCONTRACT SUB -TOTAL
SUB -TOTAL $ 8,944.09
Payroll Taxes 6 Insurance
@ 22% of $3,539.60 = $ 778.71
= $ 400.00
SUB -TOTAL
Profit @ 15%
CHANGE ORDER 015 TOTAL
= $ 9,722.80
$ 1,458.42
$ 11,I81.22
THE ORIGINAL CONTRACT SUM WAS $ 6,685,759.00
THE MAXIMUM NET CHANGE BY PREVIOUS CHANGE ORDERS $ 264,850.30
THE MAXIMUM CONTRACT SUM PRIOR TO THIS CHANGE ORDER WAS $ 6,950,609.30
THE CONTRACT AMOUNT WILL BE INCREASED BY THIS CHANGE ORDER $ 11,181.22
Change Order No. 15
?age 4
THE NEW CONTRACT AMOUNT INCLUDING THIS CHANGE ORDER
THE ORIGINAL COMPLETION TIME WAS
• THE NET CHANGE BY PREVIOUS CHANGE ORDERS
THE COMPLETION TIME PRIOR TO THIS CHANGE ORDER WAS
THE COMPLETION TIME WILL BE INCREASED BY THIS CHANGE ORDER
THE CON RACT COMPLETION TIME INCLUDING THIS CHANGE ORDER
ENG
URBA
ENGINE
RING
BY:
L
J. Urb n
Partner
CONTRACTOR:
6,961,790.52
500 Working Days
500 Working Days
500 Working Days
F & E ERECTION COMPANY
BY:
BobbyGD. Greaves
. Project Superintendent
Date: September 6, 1983 Date: September 6, 1983
OWNER:---77-7
CITY OF CORPUS CHRISTI
BY:
James K. Lantos, P.E.
Assistant City Manager
Date:
CITY OF CORPUS CRPISTI, TEXAS
CERTIFICATION OF FUNDS
(City Charter Article IV Section 21)
October 4, 1983
I certify to the City Council that $ 133,087.06 , the amount required for
the contract, agreement, obligation or expenditures contemplated in the above
and foregoing ordinance is in the Treasury of the City of Corpus Christi to the
credit of:
Rand No. and Name No. 250 Sanitary Sewer Bond Fund
Project No. 250-77-27
Project Name Oso Wastewater Treatment Plant Contract 5
from which it is proposed to be drawn, and such money is not appropriated for any
other purpose.
FIN 2-55
Revised 7/31/69
/ , 19
D rectorinan��
t.
Corpu�'s',,--Christi, Texas
/2. day of�Cr21. Gal-/ , 1983
TO THE MEMBERS OF THE CITY COUNCIL
Corpus Christi, Texas
For the reasons set forth in the emergency clause of the foregoing ordinance
or resolution, an emergency exists requiring suspension of the Charter rule
as to consideration and voting upon ordinances or resolutions at three
regular meetings; I/we, therefore, request that you suspend said Charter rule
and pass this ordinance or resolution finally on the date it is introduced,
or at the present meeting of the City Council.
Respectfully, Respectfully,
s
Council Members
MAYQRPrn.iem
t THE CITY OF CORPUS CHRISTI, TEXAS
The above ordinance was passed
Luther Jones
Betty N. Turner
David Berlanga, Sr.
Leo Guerrero
Herbert L. Hawkins, Jr.
Dr. Charles W. Kennedy
Joe McComb
Frank Mendez
Mary Pat Slavik
the following vote: