HomeMy WebLinkAbout18183 ORD - 04/18/1984AN ORDINANCE
APPROVING CHANGE ORDER NOS. 18, 19, AND 23 TO THE CONTRACT
WITH F & E ERECTION COMPANY FOR THE SECOND PHASE OF
EXPANSION OF THE OSO WASTEWATER TREATMENT PLANT WHICH
PROVIDES FOR ADDITIONAL WORK AT THE OSO PLANT INVOLVING
ADDITIONAL ELECTRICAL LIGHTING AND WIRING AND ALSO REPLACING
WALKWAY BRIDGES; APPROPRIATING $86,042.70; AND DECLARING AN
EMERGENCY.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF CORPUS CHRISTI,
TEXAS:
SECTION 1. That there is hereby approved Change Order Nos. 18, 19,
and 23 to the contract with F & E Erection Company for the second phase of
expansion of the Oso Wastewater Treatment Plant which provides for additional
work at the Oso Plant involving additional electrical lighting and wiring and
also replacing walkway bridges, all as more fully set forth in the change
orders, substantial copies of which are attached hereto and made a part hereof,
marked Exhibits "A", "B", and "C".
SECTION 2. That there is hereby appropriated $86,042.70 from the
No. 250 Sanitary Sewer Bond Fund.
Section 3. That upon written request of the Mayor or five Council
members, copy attached, to find and declare an emergency due to the need to take
immediate action to preserve and protect public property by expediting the
construction of public improvements, such finding of an emergency is made and
declared requiring suspension of the Charter rule as to consideration and voting
upon ordinances or resolutions at three regular meetings so that this ordinance
is passed and shall take effect upon first reading as an emergency measure this
the 18th day of April, 1984.
ATTEST:
c°a�
APPROVED: /79( DAY OF APRIL, 1984
J. BRUCE AVCOCK, CITY ATTORNEY
ty Attorne
MAYOR
THE CI '' OF CORPUS CHRISTI, TEXAS
SEP 2 81984
ACIR1R 4n-
18183
P.O. BOX 6355, 2725 SWANTNER
CORPUS CHRISTI, TEXAS 78411 PHONE 854-3101
Pollution Control Project No. W.P.C.-TEX-1214
E.P.A. Step 3 Grant No. C-48-1214
Improvements to the Oso Wastewater Treatment Plant
Corpus Christi, Texas
Contract No. 5, Treatment Plant Expansion
Second Phase of Plant Construction
CHANGE ORDER NO. 18
Job No. 9254.30
This Change Order addresses additional electrical work required to complete
the project, and involves thq following five (5) items:
1. Raising Electrical Manhole (54+00 N & 105+00 E)
2. Rewire Blower Houses #1 & #5, and Sludge Pump Building
3. Entrance Sign Lighting
4. Light Fixture at Bar Screen/Grit Removal Unit
5. Overhead Power Feed and Lights to Chlorine Contact Chambers #1 & #2
PART A: NECESSITY OF THE CHANGE ORDER:
Item No. 1 - Raising Electrical Manhole
At plant site coordinates 54+00 North and 105+00 East is an existing
electrical manhole utilized in the electrical work required for this
project. It becomes necessary to raise the top of this existing electrical
,manhole to slightly above final grade for easy access and to keep the
manhole from collecting water, dirt, etc.
Item No. 2 - Rewire Blower Houses #1 and #5, and Sludge Pump Building
The original Contract as designed called for reusing existing wiring,
wall receptacles, and light fixtures in each of these three buildings.
However, due to the extended time period between the design phase and
the construction period, some existing light fixtures, wall receptacles,
and wiring are either missing or deteriorated to such a degree that they
cannot be reused. New light fixtures, wall receptacles, and wiring will
be required in these three buildings so that electrical work in Contract 45
can be completed.
.3 Change Order No. 18
Page 2
Item No. 3 - Entrance Sign Lighting
Contract #5, as designed and bid, called for only an electrical stub -
out at the new plant entrance sign for a future light to be installed.
At this time, it is recommended that a light be supplied and installed
at the entrance sign under work in Contract #5.
Item No. 4 - Light Fixture at the Bar Screen/Grit Removal Unit
Because of the orientation of this unit to the existing and proposed
plant site lighting, and an overhang constructed as part of the bar
screen, a dark area at night now exists. It is recommended that a light
fixture be supplied and installed for plant personnel to operate, clean,
or perform maintenance work on the equipment during nightime hours.
Item No. 5 - Overhead Power. Feed and Lights to Chlorine Contact
Chambers #1 and #2
Due to the extended time period between the design phase and the construction'
period, the power feed to the sludge scraper mechanisms for each of these
Chlorine Contact Chambers has deteriorated to a state that it cannot be •
reused. A new power feed will be required for operation of the scraper'
mechanism. In addition, it is recommended that light fixtures be
supplied and installed on the existing bridges of both chambers.
PART B: COST BREAKDOWN:
Item No. 1 - Raising Electrical Manhole
I. Material
II. Labor
III. Equipment
IV. Freight and Handling
V. Insurance & Taxes
@ 17.7% of $441.06
SUB -TOTAL:
Overhead @ 22%
SUB -TOTAL:
Profit @ 25%
ITEM NO. 1 TOTAL:
= $ 1,350.00
= $ 441.00
_ $ 272.00
= $ 68.00
• $ 78.00
• $ 2,209.00
• $ 486.00
• $ 2,695.00
_ $ 404.25
$ 3,099.25
Change Order No. I8
Page 3 ,
Item No. 2 - Rewire Blower Houses #1 and #5
and Sludge Pump Building
Blower House #1:
I. Material = $ 608.15
II. Labor • $ 762.45
III. Freight = $ 30.41
IV. Payroll Insurances & Taxes • $ 152.49
@ 200 of $762.45
V. Equipment, Tools & Fuel $ 501.46
SUB -TOTAL: _ $ 2,054.96
Overhead @ 100: _ $ 205.50
SUB -TOTAL: = $ 2,260.46
Profit @ 5%: _ $ 113.02
BLOWER. HOUSE #1 TOTAL: _ $ 2,373.48
Blower House #5:
I. Material = $ 796.24
II. Labor $ 768.43
III. Freight 39.81
IV. Payroll Insurance & Taxes ▪ $ 153.69
@ 20%.of $768.43
V. Equipment, Tools & Fuel = •$ 543.44
SUB -TOTAL: _ $ 2,301.61
Overhead @ 10%:
SUB -TOTAL:
Profit @ 5%:
BLOWER HOUSE 05 TOTAL:
Sludge Pump Building:
I. Material.
• $ 237.10
= $ 2,538.71
• $ 130.41
$ 2,669.12
= $ 376.22
• Change Order No. 18
Page 4
II. Labor
III. Freight
= $ 357.50
$ 18.76
IV. Payroll Insurance & Taxes
@ 20% of $357.50 = $ 72.50
V. Equipment, Tools & Fuel = $ 235.13
SUBTOTAL: _ $ 1,058.11
Overhead @ 10%: _ $ 105.81
SUB -TOTAL: _ $ 1,163.92
Profit @ 5%: = $ 58.20
SLUDGE PUMP BUILDING TOTAL: _ $ 1,222.12
SUMMARY
BLOWER HOUSE 91 = $ 2,373.48
BLOWER HOUSE 115 = $ 2,669.12
SLUDGE PUMP BUILDING $ 1.222.12
ITEM NO. 2 TOTAL: _ $ 6,264.72
Item No. 3 - Entrance Sign Lighting
I. Material = $ 439.86
II. Labor 277.55
III. Payroll Insurance & Taxes
@ 22% of $277.55 = $ 61.06
1V. Freight
V. Equipment, Tools & Fuel
= S 21.99
$ 181.48
SUB -TOTAL: _ $ 981.94
Overhead @ 10%: _ $ 98.19
SUB -TOTAL: 8 1,080.13
Profit @ 5%: = $ 54.01
ITEM NO. 3 TOTAL: = $ 1,134.14
Change Order No. 18
Page 5
Item No. 4 - Light Fixture at Bar Screen/
Grit Removal Unit
I. Material
II. Labor
III. Freight
= $ 479.35
= $ 127.01
• $ 23.97
IV. Payroll Insurance & Taxes
@ 22% of $127.01 = $ 27.94
V. Equipment, Tools & Fuel - $ 83.05
SUB -TOTAL:
Overhead @ 10%:
SUB -TOTAL:
Profit @ 5%:
ITEM NO. 4 TOTAL:
Item No. 5 - Overhead Power Feed and Lights
to Chlorine Contact Chambers 41 & 42
I. Material
II. Labor
III. Payroll Insurance & Taxes
@ 17.3e of $1,503.25
IV. Freight
V. Equipment, Tools & Fuel
• $ 741.32
• $ 74.13
• $ 815.45
• $ 40.77
• $ 856.22
= $ 1,309.55
• $ 1,503.25
• $ 260.06
$ 55.91
• $ 746.23
SUB -TOTAL: .$ 3,875.00
Credit for Deleted Work Items = $ 348.56
SUB -TOTAL: _ $ 3,526.44
Overhead @ 10%: _ $ 352.64
SUB -TOTAL: $ 3,879.08
Profit @ 5%: = $ 193.95
ITEM NO. 5 TOTAL: _ $ 4,073.03
Change Order No. 18
Page 6
COST BREAKDOWN SUMMARY
ITEM NO. 1 TOTAL:
ITEM NO. 2 TOTAL:
ITEM NO. 3 TOTAL:
ITEM NO. 4 TOTAL:
ITEM NO. 5 TOTAL:
SUB -TOTAL
$ 3,099.25
$ 6,264.72
• $ 1,134.14
_ $ 856.22
_ $ 4,073.03
• $15,427.36
General Contractor's Overhead
& Profit 4 15% _ $ 2,314.10
CHANGE ORDER 418 TOTAL:
THE ORIGINAL CONTRACT SUM WAS
THE MAXIMUM NET CHANGE BY PREVIOUS CHANGE ORDERS
THE MAXIMUM CONTRACT SUM PRIOR TO THIS CHANGE ORDER WAS
THE CONTRACT AMOUNT WILL BE INCREASED BY THIS CHANGE ORDER
THE NEW CONTRACT AMOUNT INCLUDING THIS CHANGE ORDER
THE ORIGINAL COMPLETION TIME WAS
THE NET CHANGE BY PREVIOUS CHANGE ORDERS
THE COMPLETION TIME PRIOR TO THIS CHANGE ORDER WAS
THE COMPLETION TIME WILL BE INCREASED BY THIS CHANGE ORDER
THE CONTRACT COMPLETION TIME INCLUDING THIS CHANGE ORDER
• $17,741.46
$6,685,759.00
$ 674,980.52•
$7,360,739.52
$ 17,741.46
$7,378,480.98
500 Working Days
160 Working Days
660 Working Days
- 0-
660 Working Days
Change Order No. 18
Page 7
ENGINEER: CONTRACTOR:
URBAN ENGINEERING F & E ERECTION COMPANY
BY: \ + BY: 4vz //. /�jZ/-4ii%'�.—
Larry J. U , P.E. Bobby Greaves
Partner Project Superintendent
Date: February 10, 1984 Date: February 10, 1984
OWNER:
CITT OF CORPUS CHRISTI
BY:
James K. Lentos, P.E.
Assistant City Manager
Date:
P.O. BOX 6355, 2725 SWANTNER
CORPUS CHRISTI, TEXAS 78411 PHONE 854-3101
Pollution Control Project No. W.P.C.-TEX-1214
E.P.A. Step 3 Grant No. C -48-12I4
Improvements to the Oso Wastewater Treatment Plant
Corpus Christi, Texas
Contract No. 5, Treatment Plant Expansion
Second Phase of Plant Construction
CHANGE ORDER NO. 19
Job No. 9254.30
This Change Order addresses additional electrical work required to complete
the project, and involves the following three (3) items:
1. New Underground Electrical Service to Blower Houses #1, 3, & 5.
2. New Lighting Fixtures and Receptacles for the Pre -Thickener
Bridges.
3. Underground Electrical Conduit and Wiring.
PART A: NECESSITY OF THE CHANGE'ORDER:
Item No. 1 - Underground Electrical Service to Blower Houses #1, 3, & 5.
Between the design phase and the construction phase of this Contract,
A Central Power & Light transformer rack on the north 12.4 XV feeder
serving Blower Houses #1, 3, & 5 has deteriorated into a condition that
replacement was required. Central Power & Light has installed a new
transformer rack on this north 12.4 KV feeder, approximately 50 feet
north of the previous location..
At the new transformer rack location, it becomes necessary to provide
additional buried conduit and wiring to provide the required secondary
connections at the new transformer rack.
Item No. 2 - New Lighting Fixtures and Receptacles for the Pre -Thickener Bridges.
At the time of Contract #5 design, the lighting fixtures and receptacles
were serviceable and did not require replacement. Since the design phase,
and now into construction, the fixtures and receptacles have deteriorated
to a degree that they cannot be reused. As requested by the City of
Corpus Christi, new high pressure sodium lighting fixtures with receptacles
will be furnished and installed.
. Change Order No. 19
Page 2
Item No. 3 - Underground Electrical Conduit and Wiring.
Seven (7) electrical duct banks installed on Oso Contract #4 wi1l require
extensions to new equipment furnished and installed on Oso•Contract #5.
These seven (7) duct banks are not included in the contract drawings,
but are required for completion of the work. All work under this item
is associated with electrical interfacing between Contracts #4 and #5.
PART B: COST BREAKDOWN
Item No. 1 - Underground Electrical Service to Blower Houses #1, 3, & 5.
I. Material = $ 11,626.81
II. Labor = $ 4,450.95
III. Equipment = $ 4,432.54
IV Freight & Handling = $ 581.34
V. Payroll Insurance &
Taxes @ 27.1% of $4,450.95 = $ 1,206.76
SUB -TOTAL: = $ 22,298.40
Overhead @ 10.7% = $ 2,388.13
SUB -TOTAL: = $ 24,686.53
Profit @ 5.3% _ $ 1,323.47
ITEM NO. 1 TOTAL: _ $ 26,000.00
Item No. 2 - New Lighting Fixtures and Receptacles for the Pre -Thickener
Bridges.
I. Material = $ 653.00
II. Labor = $ 327.00
III. Equipment = $ 341.00
IV. Freight & Handling = $ 33.00
V. Payroll Insurance & Taxes
@ 19.9% of $327.00 = $ 65.00
SUB -TOTAL:
Overhead @ 100
SUB -TOTAL:
Profit @ 5%
ITEM NO. 2 TOTAL:
= $ 1,419.00
= $ 142.00
= $ 1,561.00
= $ 78.00
= $ 1,639.00
Change Order No. 19
Page 3
Item No. 3 - Underground Electrical Conduit and Wiring.
I. Material $ 4,684.35
II. Labor = $ 5,819.97
III. Equipment = $ 2,479.95
IV. Freight & Handling $ 455.75
COST BREAKDOWN SUMMARY
Item No. 1 Total:
Item No. 2 Total:
Item No. 3 Total:
SUB -TOTAL: $ 13,440.02
Overhead & Profit @ 9.4% = $ 1,264.72
ITEM NO. 3 TOTAL: $ 14,704.74
_ $ 26,000.00
$ 1,639.00
_ $ 14,704.74
SUB -TOTAL: = $ 42,343.74
General Contractor's Overhead & Profit @ 150 = $ 6,351.56
CHANGE ORDER #19 TOTAL = $ 48,695.30
THE ORIGINAL CONTRACT SUM WAS $6,685,759.00
THE MAXIMUM NET CHANGE BY PREVIOUS CHANGE ORDERS $ 692,721.98
THE MAXIMUM CONTRACT SUM PRIOR TO THIS CHANGE ORDER WAS $7,378,480.98
THE CONTRACT AMOUNT WILL BE INCREASED BY THIS CHANGE ORDER $ 48,695.30
THE NEW CONTRACT AMOUNT INCLUDING THIS CHANGE ORDER 7,427,176.28
THE ORIGINAL COMPLETION TIME WAS 500 Working Days
THE NET CHANGE BY PREVIOUS CHANGE ORDERS 160 Working Days
THE COMPLETION TIME PRIOR TO THIS CHANGE ORDER WAS 660 Working Days
THE COMPLETION TIME WILL BE INCREASED BY THIS CHANGE ORDER -0-
THE CONTRACT COMPLETION TIME INCLUDING THIS CHANGE ORDER 660 Working Days
Change Order No. 19
Page 4
Larry J. U
Partner
OWNER:
CITY OF CORPUS CHRISTI
BY:
James K. Lontos, P.E.
Assistant City Manager
Date:
CONTRACTOR:
F & E ERECTION COMPANY
BY:
Bobby D/Greaves
Project Superintendent
Date: Z, Zl _ ��
111 MAN
ENGINEERING
CORPUS CHRISTI, TEXAS
P. O. BOX 6355, 2725 SWANTNER
CORPUS CHRISTI, TEXAS 78411 PHONE 854-3101
Pollution Control Project No. W.P.C.-TEX-1214
E.P.R. Step 3 Grant No. C-48-1214
Improvements to the Oso Wastewater Treatment Plant
Corpus Christi, Texas
Contract No. 5, Treatment Plant Expansion
Second Phase of Plant Construction
CHANGE ORDER NO. 23
PART A: NECESSITY OF THE CHANGE ORDER:
PART B:
Job No. 9254.30
This Change Order involves the fabrication and installation of new
walkway bridges for Chlorine Contact Chambers #1 and #2, as
requested by the City of Corpus Christi.
The original Contract called for reusing the existing walkway bridges
on both units. Since the design of Oso Contract #5, these existing
walkway bridges have deteriorated to such a degree that replacement
is required.
COST BREAKDOWN:
I. Materials
New Walkway Bridges
2 Bridges @ $7,329.00/Each = $ 14,658.00
b. Structural Angles
80 Feet @ $1.15/Ft. (Credit)
II. Labor
_ ($ 92.00)
MATERIAL SUB -TOTAL: _ $ 14,566.00
a. Foreman
20 Hours @ $13.75/Hr.
b. Operator
20 Hours @ $8.00/Hr.
= $ 275.00
$ 160.00
80 cy
Change Order No, 23
Page 2
c. Ironworkers
52 Hours @ $6.50/Hr.
d. Laborers
40 Hours @ $4.60/Hr.
e. Ironworkers
30 Hours @ $6.50/Hr. (Credit)
LABOR SUB -TOTAL:
III. Equipment
a. 25 Ton Crane
20 Hours @ $30.15/Hr.
IV. Subcontract
_ $ 338.00
= $ 184.00
= ($ 195.00)
$ 762.00
$ 603.00
EQUIPMENT SUB -TOTAL: = $ 603.00
a. Freight
2 Loads @ $475.00/Load
$ 950.00
SUBCONTRACT SUB -TOTAL:= $ 950.00
SUB -TOTAL: _ $ 16,881.00
Payroll Taxes & Insurance: = $ 167.64
@ 22% of $762.00
SUB -TOTAL: _ $ 17,048.64
Overhead & Profit @ 15% = $ 2,557.30
CHANGE ORDER #23 TOTAL: = $ 19,605.94
THE ORIGINAL CONTRACT SUM WAS $ 6,685,759.00
THE MAXIMUM NET CHANGE BY PREVIOUS CHANGE ORDERS $ 749,594.92
THE MAXIMUM CONTRACT SUM PRIOR TO THIS CHANGE ORDER WAS $ 7,435,353.92
THE CONTRACT AMOUNT WILL BE INCREASED BY THIS CHANGE ORDER $ 19,605.94
THE NEW CONTRACT AMOUNT INCLUDING THIS CHANGE ORDER $ 7,454,959.86
THE ORIGINAL COMPLETION TIME WAS 500 Working Days
Change Order No. 23
Page 3
THE NET CHANGE BY PREVIOUS CHANGE ORDERS
THE COMPLETION TIME PRIOR TO THIS CHANGE ORDER WAS
THE COMPLETION TIME WILL BE INCREASED BY THIS CHANGE ORDER
160 Working Days
660 Working Days
-0-
T COMPLETION TIME INCLUDING THIS CHANGE ORDER 660 Working Days
ENG EER: CONTRACTOR:
BY:
La ry J. Urb
Partnerilli
F & E ERECTION COMPANY
BY: /% u i//
P.R. Bobby D
Greaves s
Proje Superintendent
Date: 11---Z, ^ 6 Date: 4 -
OWNER:
CITY OF CORPUS CHRISTI
BY:
James K. Lontos, P.E.
Assistant City Manager
Date:
CITY OF CORPUS CHRISTI, TERAS
CERTIFICATION OF FUNDS
(City Charter Article IV Section 21)
April 11. 1984
I certify to the City Council that $ 86,042 7n , the amount required for
the contract, agreement, obligation or expenditures contemplated in the above
and foregoing ordinance is in the Treasury of the City of Corpus Christi to the
credit of:
Fund No. and Name
Project No.
Project Nance
250 Sanitary S'war Bond Fund
250-77-27
Oso Wastewater Treatment Plant Contract No 5
from which it is proposed to be drawn, and such money is not appropriated for any
other purpose.
FIN 2-55
Revised 7/31/69
�� , 19
Corppushristi, Texa
AD day of , 1984
TO THE MEMBERS OF THE CITY COUNCIL
Corpus Christi, Texas
For the reasons set forth in the emergency clause of the foregoing ordinance
or resolution, an emergency exists requiring suspension of the Charter rule
as to consideration and voting upon ordinances or resolutions at three
regular meetings; I/we, therefore, request that you suspend said Charter rule
and pass this ordinance or resolution finally on the date it is introduced,
or at the present meeting of the City Council.
Respectfully, Respectfully,
MAYO
Council Members
THE C Y OF CORPUS CHRISTI, TEXAS
The above ordinance was passed y the following vote:
Luther Jones L
Betty N. Turner
David Berlanga, Sr.
Welder Brown
Leo Guerrero
Dr. Charles W. Kennedy
Joe McComb
Frank Mendez
Mary Pat Slavik
181613