HomeMy WebLinkAbout19670 ORD - 03/06/1987AN ORDINANCE
AUTHORIZING THE EXECUTION OF CHANGE ORDER NO. 5 FOR THE
FLOUR BLUFF PLANT EXPANSION PROJECT; APPROPRIATING
$9,571.40; AND DECLARING AN EMERGENCY.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF CORPUS CHRISTI,
TEXAS:
SECTION 1. That Change Order No. 5 in the amount of $9,571.40 to
the contract with Basic Constructors, Inc. for the Flour Bluff Plant
Expansion project, is hereby approved.
SECTION 2. That there is hereby appropriated $9,571.40 from the
Sanitary Sewer Bond Fund, Project No. 250-82-2.1.
SECTION 3. That upon written request of the Mayor or five Council
members, copy attached, to find and declare an emergency due to the need of
appropriating the abovementioned funds ate the earliest practicable date,
such finding of an emergency is made and declared requiring suspension of
the Charter rule as to consideration and voting upon ordinances or
resolutions at three regular meetings so that this ordinance is passed and
shall take effect u on"i�first reading as an emergency measure this the
1/70% day of �Afal , 19 $7 .
ATTEST:
City Secretary MAYOR
THE CITY OF CORPUS CHRISTI, TEXAS
APPROVED: DAY OF [/4tQJLr.� , 1917
HAL GEORGE, CITY ATTORNEY
03P.110.01
1J67o MICROFILMED
'URBAN
ENGINEERING
CORPUS CHRISTI. TEXAS
P.O. BOX 6355, 2725 SWANTNER
CORPUS CHRISTI, TEXAS 78411 (512) 854-3101
E.P.A. Project Grant No. C--48-1215--03
Flour Bluff Wastewater Facility Improvements
Corpus Christi, Texas
CHANGE ORDER "45
Job No. 9984.30
This Change Order involves Two (2) separate items, and should be
considered as follows:
Item No. 1 Construct a six feet high decorative block wall with a wood
cedar gate around Lift Station "42.
Item No. 2 - Lift Station '42 Extended Warranty
PART A: NECESSITY OF THE CHANGE ORDER
Item No. 1 -- The City Wastewater Services Division has requested
that a decorative concrete block wall be constructed
around Lift Station 4t2 and its electrical transformer.
Also proposed is a double gate constructed of cedar
wood. The lift station is located on Flour Bluff Drive
near Purdue Road.
Item No. 2 - Warranty Agreement
WHEREAS, BASIC CONTRACTORS, INC. ("Contractor") and the City
of Corpus Christi, Texas ("City") are parties to that certain
agreement for the Flour Bluff Wastewater Facility Improvements,
Corpus Christi, Texas, further identified as Pollution Control
Project No. W.P.C.--TEX--48-- 1215, E.P.A. Step 2 Grant No.
C•-48-1215-•02 (the "Agreement"); and
WHEREAS, part of the Agreement includes construction of a unit
known as "Lift Station No. 2"; and
Change Order No. 5
Page 2
WHEREAS, City has notified Contractor that Lift Station No. 2,
as constructed by Contractor, is not acceptable to City; and
WHEREAS, Contractor desired to secure acceptance of Lift
Station No. 2 by City.
It is, therefore, AGREED, by City and Contractor that the
Agreement is hereby amended by addition of the following
warranty:
"Contractor shall fully maintain and keep in good repair, at its
own expense, the wet well liner of Lift Station No. 2, for a
period of five (5) years from City's acceptance of Lift Station
No. 2. Without limitation on the generality of the foregoing,
Contractor's obligation hereunder shall include: (a) repairs
satisfactory to City of any leak which develops at the
construction joint of the wet well, (b) repairs satisfactory to
City if the wet well liner should become detached or partially
detached from the wet well wall, (c) by-pass pumping including
but not limited to provision and installation of all necessary
pumps and other equipment needed to maintain sewer service
while the wet well is out of operation, (d) flow diversion, (e)
and all work associated with removing the lift station from
service and placing it back in service after warranty
maintenance and repairs have been performed."
PART B: COST BREAKDOWN•
Item No. 1 -Construct decorative block wall at Lift Station "2.
I. Materials
a. Layout
b. Formwork
175 Square Feet @ $0.60/SF
c. Reinforcing Steel
300 Pounds @ $0.25/Lb.
$ 15.00
$ 105.00
- $ 75.00
Change Order No. 5
Page 3
d. Concrete
10 Cubic Yards @ $50.00/CY
e. Drill Bits & Epoxy
10 Holes @ $5.00/Hole
f. Cedar Wood Gate
1 Lump Sum @ $417.00/L5
II. Equipment
$ 500.00
$ 50.00
• $ 417.00
MATERIAL SUB -TOTAL = $ 1,162.00
a. Dump Truck Rental - $ 100.00
EQUIPMENT SUB --TOTAL - $ 100.00
III. Labor
a. Supervision
1 1 Flours @ $18.00/1-1r.
b. Layout
6 Hours @ $8.00/Hr.
c. Excavation for Wall rooting
10 Cubic Yards @ $40.00/CY
d. Base Compaction & Grading
270 Square Feet @ $0.25/SF
e. Carpentry Formwork
175 Square Feet @ $2.50/SF
f. Reinforcing Steel Placement
300 Pounds @ $0.25/Lb.
• $ 198.00
• $ 48.00
= $ .400.00
• $ 67.50
$ 437.50
$ 75.00
Change Order No. 5
Page 4
g. Concrete Placement
10 Cubic Yards @ $10.00/CY
h. Backfill & Final Grading
6 Cubic Yards @ $30.00/CY
i. Hauling excess material
10 Cubic Yards @ $3.00/CY
= $ 100.00
• $ 180.00
• $ 30.00
j. Drill Holes & Epoxy Rebar
10 holes @ $5.00/hole - $ 50.00
LABOR SUB -•TOTAL = $ 1,586.00
IV. Subcontracts
a. Masonry Subcontractor
1 lump sum @ $4,904.00/L5 = $ 4,90400
SUBCONTRACTS SUB -TOTAL = $ 4,90400
SUB -TOTAL = $ 7,752.00
Payroll Taxes & Insurance
@ 36% of $1,586.00 = $ 570.96
SUB -TOTAL
Profit @ 15%
ITEM NO. 1 TOTAL
• $ 8,322.96
- $ 1,248.44
- $ 9,571.40
Item No. 2 - Lift Station /''2 Extended Warranty
Cost Not Applicable
CHANGE ORDER /45 TOTAL - $ 9,571.40
Change Order No. 5
Page 5
THE ORIGINAL CONTRACT SUM WAS $4,166,900.00
THE MAXIMUM NET CHANGE BY PREVIOUS CHANGE ORDERS $ 183,277.91
THE MAXIMUM CONTRACT SUM PRIOR TO THIS CHANGE ORDER
WAS $.4,350,177.91
THE CONTRACT AMOUNT WILL BE INCREASED BY THIS CHANGE
ORDER
$ 9,571.40
THE NEW CONTRACT AMOUNT INCLUDING THIS CHANGE ORDER $4,359,749.31
THE ORIGINAL COMPLETION TIME WAS 360 Working Days
THE NET CHANGE BY PREVIOUS CHANGE ORDERS 154 Working Days
THE COMPLETION TIME PRIOR TO THIS CHANGE ORDER WAS 514 Working Days
THE COMPLETION TIME WILL BE UNCHANGED BY THIS CHANGE -
ORDER 0 Working Days
THE CONTRACT COMPLETION TIME INCLUDING THIS CHANGE
ORDER 514 Working Days
ENGINEER:
URBAN ENGINEERING
BY
CONTRACTOR:
BASIC CONSTRUCTORS
BY•
Les I arvey, P.E.
Project Engineer
Ji r Frith
oject Manager
Date: March 9, 1987 Date: March 9, 1987
OWNER:
CITY OF CORPUS CHRISTI
BY•
James K. Lontos, P.E.
Assistant City Manager
Date•
CITY OF CORPUS CHRISTI., TEXAS
CERTIFICATION OF FUNDS
(City Charter Article IV Section 21)
p
March 5, 1987 -
I certify to the City Council that $ 9,571.40 - , the amount required for
the contract, agreement, obligation or expenditures contemplated in the above
and foregoing ordinance is in the Treasury of the City of Corpus Christi to the
credit of:
Fund No. and Name
Project No.
250 Sanitary Sewer Bond Fund
250-82-2.1
Project Name
Flour Bluff Wastewater Plant
•
frrxn which it is proposed to be drawn, and such money is not appropriated for any
other purpose.
FIN 2-55
Revised 7/31/69
,•72e2.4.} �' , 19a/
9 01
i‘/g7
1
Corpus Christi, Texas _
1744 day of MaYWIl , 1987
TO THE MEMBERS OF THE CITY COUNCIL
Corpus Christi, Texas
For the reasons set forth in the emergency clause of the foregoing ordinance
or resolution, an emergency exists requiring suspension of the Charter rule
as to consideration and voting upon ordinances or resolutions at three
regular meetings; I/we, therefore, request that you suspend said Charter rule
and pass this ordinance or resolution finally on the date it is introduced,
or at the present meeting of the City Council.
Respectfully, - Respectfully,
Council Members
MAYOR
THE CITY OF CORPUS CHRISTI, TEXAS
The above ordinance was passed by the following vote:
Luther Jones
Dr. Jack Best
David Berlanga, Sr.
Leo Guerrero
Joe McComb
Frank Mendez
Bill Pruet
Mary Pat Slavik
Linda Strong