HomeMy WebLinkAbout024865 RES - 05/14/2002
RESOLUTION
APPROVING PLANS AND SPECIFICATIONS FOR
IMPROVEMENTS TO THE FOLLOWING HIGHWAYS IN
CORPUS CHRISTI, NUECES COUNTY, TEXAS:
Flour Bluff Area Street Improvements, Phase 1: Claride Street
from N.A.S. Drive to Mounts Street, Mounts Street from Claride
Street to Lakeside Drive, Jane Street from Jester Street to
Claride Street, Webb Street from N.A.S. Drive to Jane Street,
Scotland Street from N.A.S. Drive to Jane Street
APPROVING THE DIRECTOR OF ENGINEERING
SERVICES PROJECT CONSTRUCTION COST ESTIMATE
INCLUDING AN ESTIMATE OF THE PORTION OF COSTS
TO BE PAID BY THE CITY AND THE PORTION TO BE
PAID BY ASSESSMENTS; SETTING A PUBLIC HEARING
ON THESE PROPOSED ASSESSMENTS TO OCCUR
DURING THE JUNE 25, 2002 CITY COUNCIL MEETING;
DIRECTING THE CITY SECRETARY TO ARRANGE TO
PUBLISH NOTICE OF THIS PUBLIC HEARING; AND
ORDERING THE DIRECTOR OF ENGINEERING SERVICES
TO PROVIDE WRITTEN NOTICE OF THE PUBLIC
HEARING TO PROPERTY OWNERS
In its Resolution No~passed on May 14,2002, the City Council determined that
it was necessary to improve and ordered the improvement of the following highways in Corpus
Christi, Nueces County, Texas:
Flour Bluff Area Street Improvements, Phase 1 :
. Claride Street from N.A.S. Drive to Mounts Street
. Mounts Street from Claride Street to Lakeside Drive
. Jane Street from Jester Street to Claride Street
. Webb Street from N.A.S. Drive to Jane Street
. Scotland Street from N.A.S, Drive to Jane Street
In Resolution No.cQLf;<(g4:, the city council stated that the Project consisted on
categories or improvements: 1) street, curb, gutter, and sidewalk improvements to be paid for
partly by the city and partly by assessments; 2) driveways to be paid for entirely by assessments;
and 3) other improvements, to be paid for by the city, because either the assessment statute did
not apply to these improvements or the city was not making assessments to pay for them,
The city's department of engineering services prepared detailed project plans and
specifications, The city then received bids to construct the project accordingly.
024865
After evaluating the apparent lowest responsible bid to construct the Project, the director
of engineering services prepared a Project Construction Cost Estimate (attached as Exhibit A).
This estimate specifies anticipated total Project construction cost and the city portion of this cost,
the preliminary total of assessments, and various assessment rates. The estimate also includes a
bid tabulation and a preliminary assessment roll listing proposed assessments against each
abutting or affected property.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF CORPUS CHRISTI, TEXAS:
SECTION 1. The project plans and specifications are approved.
SECTION 2. In accordance with Texas Transportation Code Section 313.024, the
Project construction cost estimate is approved; however, the assessments listed in the preliminary
assessment roll cannot be imposed until after a public hearing is conducted in accordance with
state law and the city council's Assessment Process Rules Resolution.
SECTION 3. A public hearing on proposed assessments for the Flour Bluff Area Street
Improvements, Phase I will be held during the City Council's June 25, 2002 meeting. This
meeting will begin at 2:00 p.m. in the City Council Chambers, I" Floor, City Hall, 1201 Leopard,
Corpus Christi, Texas.
SECTION 4. The city secretary will arrange to publish notice of this public hearing in
accordance with the Assessment process Rules Resolution.
SECTION S. The director of engineering services will provide written notice of the
public hearing to property owners in accordance with the Assessment Process Rules Resolution,
ATTEST:
CITY OF CORPUS CHRISTI
A~
City Secretary
Approved this the!l day of rnCl1
James R. Bray, Jr.
City Attorney
~~ /~t#~~fl
Samuel L. Neal, Jr.
Mayor
,2002.
By:
o n p, Burke, Jr.
sistant City Attorney
CORPUS CHRlSTI, TEXAS
I y-1Y'\ DAY OF 'iY\ ~ ,2002
The above resolution was passed by the following vote:
Samuel 1. Neal, Jf. fA:-J~
Brent Chesney ~
Javier 0, Colmenero ff/
Henry Garrett O)f=-
Bill Kelly Q~~
Rex A. Kinnison {h(~
John Longoria U1-'
Jesse Noyola (L!~
Mark Scott ~/
HILEG-DlR\john\RESOLUTJ\Flour Bluff-Appr Plans & Specsreswpd
02.1865
NOTICE OF PROPOSED ASSESSMENTS
Preliminarv Assessment Roll
Flour Bluff Estates Area Street Imorovements. Phase 1
. Claride Street from N. A. S. Drive to Mounts Street
. Mounts Street from Cia ride Street to Lakeside Street
. Jane Street from Jester Street to Claride Street
. Webb Street from N. A. S. Drive to Jane Street
. Scotland Street from N. A. S, Drive to Jane Street
This street shall be constructed by excavation to a width and depth to permit the laying
of a standard 6-inch curb and gutter section, 6-inch of soil cement, 6-inch of flexible
base (limestone), 1.5-inch hot mix asphaltic concrete pavement, Type "D". The street
shall be 28-feet and constructed within the existing right-of-way. There will be 4-foot
wide standard and 5-foot wide tied reinforced concrete sidewalks 4-inches thick with
ADA compliance and 6-inch thick reinforced concrete driveway.
The assessment rates have been calculated in accordance with the City's current
assessment policy and the low bid prices submitted by Bay, Ltd, The assessment rates
are as follows:
Item Adjusted Bid Price Plus Assessment
Engineering Cost Rates
Base Bid Add. All. NO.1
6" C. G. & PVMT.-28'-0" B-B $29.79 $25.19 $19.50 L, F.
Sidewalk - 4' Cone. SIW $2,59 $2.51 $1.00 S. F.
Driveways $5.40 N/A $5.40 S. F.
Residential, Church, School Property
6" C. G. & PVMT. $9,75 L. F.
Sidewalk (4') $1.00 S. F.
Driveways $5.40 S, F.
Actual Cost % Street (C, G., $59.88 L. F.
Pavement & SIW 28' B-B)
Total Bid Price $1,773,939.10 I $52,219,90 $1,826,159.00
Preliminary Assessments $251,224.35
City Share $1,574,934.65
'Angel R. Escobar, P. E.,
Director of Engineering Services
HIHOMEWELMAR\GEN\STREET\6122 FLOUR BLUFF PH 1\NECESSITY\NOTICE OF PROPOSED ASSI
Exhibit "A"
CITY ENGINEER'S STATEMENT
FLOUR BLUFF AREA STREET IMPROVEMENTS, PHASE 1
. Scotland Street from N. A. S. Drive to Jane Street
. Webb Street from N. A. S. Drive to Jane Street
. Claride Street from N. A. S. Drive to Mounts Street
. Jane Street from Jester Street to Claride Street
. Mounts Street from Claride Street to Lakeside Drive
My name is Angel R. Escobar. I am the City Engineer for the City of Corpus Christi and have served in
this capacity for the last 26 months and as Assistant City Engineer for the last one hundred twenty
months (120) months,
I am a Professional Engineer, licensed by the State of Texas since 1977, I have over 24 years of
experience in design of construction and estimating the costs thereof.
I am familiar with this project which encompasses:
. Scotland Street from N. A, S. Drive to Jane Street
. Webb Street from N. A, S. Drive to Jane Street
. Claride Street from N, A. S, Drive to Mounts Street
. Jane Street from Jester Street to Cia ride Street
. Mounts Street from Claride Street to Lakeside Drive
The project consists of reconstructing approximately 5,000 linear feet of 28-foot back-to-back street
including limestone base; prime; hot mix asphaltic concrete (HMAC) pavement; curb and gutter;
sidewalks and driveways; upgrading the existing storm drainage; replacing the water line; and replacing
the existing sanitary sewer. Limits of the work will be as follows:
. Scotland Street from N, A. S, Drive to Jane Street
. Webb Street from N. A. S. Drive to Jane Street
. Claride Street from N. A. S. Drive to Mounts Street
. Jane Street from Jester Street to Cia ride Street
. Mounts Street from Claride Street to Lakeside Drive
Funds to finance the project are available in the FY 2000-2001 and FY 2001-2002 Community
Development Block Grant (CDBG) Program and from Water, Wastewater, and Storm Water Capital
Improvement Program.
Prior to this hearing, I had an estimate of project costs prepared, and it compared favorably with the bids
received. In my opinion, the costs are true and accurate, This project is estimated to start in July 2002
with completion in August 2003.
(
A el . Escobar, P,E,
irector of Engineering Services
H:\HOMEWELMAR\GEN\STREET\6122 FLOUR BLUFF PH 1\CON5TRUCTION\ENGINEER STATEMENT
".u_..,_"'..'__m',_,,"~_, '.__
GEORGE
N.
PARASKEVAS
REALTORS
May 21, 2002
EVERHART PATIO PLAZA
5440 EVERHART
CORPUS CHRISTI. TEXAS 7841 t
PRELIMINARY ASSESSMENT ROLL, FLOUR BLUFF, PHASE I
Claride Street, NAS Drin to Mounts Drive
Webb Drive, NAS Drive to Laguaa Madre Sewage Disposal Plant
~Od.Dd Drive, NAS Drive to Jane Street
Jane Strut, Julu Street to CI.ride Stred
Mounts Orin, C.. ride Street to Lakeside Drive
My name is George N Paraskevas and I am a State Certified Residential appraiser and
have been evaluating property and practicing real estate in the Corpus Christi area since 1971. I have
experience in appraising both commercial and residential properties, and I am familiar with the real
estate market in Corpus Christi.
I am familiar with the Flour Bluff, Phase I Street Improvements. I agree with Mr. Jeff Barroso's
description of the conditions to be changed and I am familiar with the improvements to be made by the
City of Corpus Christi.
I have reviewed the project assessment roll; and personally examined each ofthe 126 parcels ofland
therein. In my opinion each such parcel will be specifically benefited by each improvement to be assessed
against it; without regard to the community benefit.
In addition, it is my opinion that each such parcel will be specially enhanced by such improvement at
least to the extent of the assessment stated.
Thank you,
'.1.'_,
'1
I, . ,,/!"_.~
George N Paraskevas
Appraiser
OFFICE (512) 992.2541