MOTION - 3/31/82
The Van Galen Drainage System Phase III project be accepted and final
payment of $22,440.80 be made to H & H Concrete Construction Company
for a total of $156,974.60. The project provided for the construction
of approximately 780 linear feet of 8' x 4' reinforced concrete box
and approximately 1,400 linear feet of reinforced concrete pipe
ranging from 15" diameter to 48" diameter in an area north of Glenoak
Drive. A portion of the project was constructed through a future
subdivision, South Sea Islands Unit 2, with the developer, JaCom
Builders, Inc., contributing $28,000 to supplement 1977 bonds to fund
the project, which was awarded November 4, 1981. This is the last
phase of the Van Galen Drainage System and completes the project in
accordance with the scope of the 1977 bond program.
M82 -0028