MOTIONS - 4/7/82
A change order to the O. N. Stevens Water Treatment Plant project be
approved for $42,247. The change order provides for additional
foundation stabilization of the area within the reservoir site where
the clearwell water storage tank is to be constructed. The location
of the clearwell was changed by recommendation of the Texas Department
of Health in order to provide for future addition of a carbon
filtration unit; therefore, the new site required additional
stabilization with cement, lime, and additional piers and larger slab
to protect against water seepage. No appropriation is necessary.
(See staff memo)
M82-0056 ISEPiQI2014