MOTIONS - 4/14/82
The St. Francis Street Half Street Construction project be accepted
and final payment of $13,977.01 for a total of $39,174.85 be made to
Asphalt Concrete Paving Company. This project provided for the paving
of one -half of St. Francis Street which abuts a City park in the
Highland Oaks Subdivision in Flour Bluff. The contractor exceeded the
30 -day allotted working time by 23 days. An extension of time in this
amount is recommended because it was impractical to construct one half
of the street with the other half not under construction and also
because the public was not inconvenienced during construction.