HomeMy WebLinkAboutM1982-0145 - 05/19/1982MOTIONS - 5/19/82
5. A change order for $6,959 be approved for additional work performed
for International Airport Terminal Building Renovation work. The
change order provides for a) spray -on acoustical texture in the new
restroom ceiling and vestibule, b) ceiling work at the rental car
booths, c) installation of carpet in lieu of tile at the new baggage
claim entry, d) installation of door scanners in lieu of automatic
door mats, and e) additional trim work in the enlarged ticket lobby
area. The work included items requested by the Airport Manager and
the architect to provide more acceptable finish on several areas of
the Terminal Expansion project. Funds for the change order are
available in the contingency appropriation, and no separate
appropriation is necessary. (See staff memo #6).