MOTION - 6/16/82
4. The Swantner and 15th Drainage Improvements Project be accepted and
final payment of $25,692.65 for a total of $135,974.69 be made to
Maverick Construction Company. A 20 -day time extension is recommended
due to delays caused by relocating City utilities and material
deliveries. This 1977 Bond Program project provided for the
installation of 36" diameter storm sewer in both 15th Street and
Swantner Street from Louisiana Boulevard to Ohio and Indiana Streets.
JoO 191W
08 2-017 8 MlcRUFILME9