MOTIONS - 7/21/82
The Corpus Christi Marina Boat Slip Addition project on the L -Head be
accepted and payment of $77,618.67 be made to the Goldston
Corporation. It is recommended that $2,000 be retained for payment at
a later date upon delivery and installation of light fixtures
previously ordered. It is further recommended that the contractor be
granted a 108 -day time extension because of non - delivery of electrical
and lighting materials. The boat slips were put into use by the City
in December, 1981. The total cost of this 1977 bond project was
$382,681.70.