HomeMy WebLinkAbout030392 ORD - 01/13/2015 Ordinance amending the FY 2015 Capital Improvement Budget adopted by Ordinance
No. 030303 by transferring $3,936,000 from Public Health & Safety 2014 Certificates of
Obligation in Fund 3367 Project #E11061 Cefe Valenzuela Landfill Disposal Cells Interim
Cover- Cells 3D, 4A and 4B to the Landfill Pavement/ Roadway Life Cycle Replacement
Project; authorizing the City Manager, or designee, to execute a construction contract
with Haas-Anderson Construction, LTD of Corpus Christi, Texas in the amount of
$3,757,566.25 for the Cefe Valenzuela Landfill Pavement Life Cycle Replacement project
for the base bid; and authorizing the City Manager, or designee, to execute a
construction materials testing contract with Tolunay Wong of Corpus Christi, Texas in
the amount of $147,075 for the Cefe Valenzuela Landfill Pavement Life Cycle
Replacement project.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF CORPUS CHRISTI, TEXAS:
SECTION 1. The FY 2015 Capital Improvement Budget adopted by Ordinance No. 030303 is
amended to transfer$3,936,000 from the Cefe Valenzuela Landfill Disposal Cells Interim Cover
- Cells 3D, 4A and 4B project in Fund 3367 to the Cefe Valenzuela Landfill Pavement Life
Cycle Replacement project.
SECTION 2. The City Manager or designee is authorized to execute a construction contract for
the Cefe Valenzuela Landfill Pavement Life Cycle Replacement project for the Base Bid in the
amount of $3,757,566.25 with Haas-Anderson Construction, LTD of Corpus Christi, Texas for
construction of necessary roadway repairs.
SECTION 3. The City Manager or designee is authorized to execute a construction materials
testing contract for the Cefe Valenzuela Landfill Pavement Life Cycle Replacement project in
the amount of $147,075 with Tolunay Wong of Corpus Christi, Texas for required material
testing.
ATTEST: [ TH CITY F CORPUS CHRISTI
-Reit-V4.4
Rebecca Huerta Nelda Martinez
City Secretary Mayor
l� .i l ;? •
INDEXEI
The foregoing,,ordinance as read for the first time and passed to its second reading on
this the 1U I "day of L )/&,v)--gill , 20 1L11 by the following vote:
Nelda MartinezOChad Magill 4—
Kelley Allen A . i ' Colleen McIntyre
4
Rudy Garza Lillian Riojas / 1
Priscilla Leal eili Mark Scott IA A
David Loeb
The foregoin,gg,,�ordinance wa read for the second time and passed finally on
this the `'`5r� day of i\,\)Lk , 20 15, by the following vote:
Nelda Martinez . ,,: Brian Rosas _aAbloi
Rudy Garza Imo.;! Lucy Rubio n 0
-----4L
Chad Magill . .J Mark Scott
Colleen McIntyre I . I Carolyn Vaughn
Lillian Riojas
I
•
PASSED AND APPROVED this the 16h-day of , 20
ATTEST:
1-24,.. 4,47., L _ 11..
Rebecca Huerta elda Marti �-
City Secretary Mayor
030392 i
CITY OF CORPUS CHRISTI
CERTIFICATION OF FUNDS
(City Charter Article IV, Sections 7&8)
I, the Director of Financial Services of the City of Corpus Christi, Texas (or his/her duly authorized
representative), hereby certify to the City Council and other appropriate officers that the money required
for the current fiscal year's portion of the contract, agreement, obligation or expenditure described
below is in the Treasury to the credit of the Fund specified below, from which it is to be drawn, and has
not been appropriated for any other purpose. Future payments are subject to annual appropriation
by the City Council.
City Council Action Date: January 13, 2015
Ordinance amending the FY 2015 Capital Improvement Budget adopted by Ordinance No.
030303 by transferring $140,000 from Public Health & Safety 2004 Certificates of Obligation in
Fund 3359 project reserves and $3,936,000 from Public Health & Safety 2014 Certificates of
Obligation Fund 3367 Project #E11061 Cefe Valenzuela Landfill Disposal Cells Interim Cover -
Cells 3D, 4A and 4B to the Landfill Pavement / Roadway Life Cycle Replacement Project);
increasing expenditures in the amount of$140,000; authorizing the City Manager, or designee, to
execute a construction contract with Haas-Anderson Construction, LTD of Corpus Christi, Texas in the
amount of $3,757,566.25 for the Cefe Valenzuela Landfill Pavement Life Cycle Replacement project
for the base bid; and authorizing the City Manager, or designee, to execute a construction materials
testing contract with Tolunay Wong of Corpus Christi, Texas in the amount of $147,075 for the Cefe
Valenzuela Landfill Pavement Life Cycle Replacement project.
Amount Required: $3.936,000.00
Fund Name Accounting Unit Account Activity No. Amount
No.
Public H & S 2014 CO's 3367-033 550910 E11061013367EXP -3,936,000.00
Public H & S 2014 CO's 3367-033 550910 140329013367EXP 3,936,000.00
Total $0
❑ Certification Not Required `P
Director of Financial Services
Date: DEC 1 6 2014
I
lst-0o13 /O
CITY OF CORPUS CHRISTI
CERTIFICATION OF FUNDS
(City Charter Article IV, Sections 7&8)
I, the Director of Financial Services of the City of Corpus Christi, Texas (or his/her duly authorized
representative), hereby certify to the City Council and other appropriate officers that the money required
for the current fiscal year's portion of the contract, agreement, obligation or expenditure described
below is in the Treasury to the credit of the Fund specified below, from which it is to be drawn, and has
not been appropriated for any other purpose. Future payments are subject to annual appropriation
by the City Council.
City Council Action Date: January 13. 2015
Ordinance amending the FY 2015 Capital Improvement Budget adopted by Ordinance No. 030303 by
transferring $140,000 from Public Health & Safety 2004 Certificates of Obligation Fund 3359 project
reserves and $3,936,000 from Public Health & Safety 2014 Certificates of Obligation in Fund 3367
Project#E11061 Cefe Valenzuela Landfill Disposal Cells Interim Cover - Cells 3D, 4A and 4B to the
Landfill Pavement/ Roadway Life Cycle Replacement Project); increasing expenditures in the amount
of$140,000; authorizing the City Manager, or designee, to execute a construction contract with
Haas-Anderson Construction, LTD of Corpus Christi, Texas in the amount of $3,757,566.25 for
the Cefe Valenzuela Landfill Pavement Life Cycle Replacement project for the base bid; and
authorizing the City Manager, or designee, to execute a construction materials testing contract
with Tolunay Wong of Corpus Christi, Texas in the amount of$147,075 for the Cefe Valenzuela
Landfill Pavement Life Cycle Replacement project.
Amount Required: $3.904.641.25
Fund Name Accounting Unit Account Activity No. Amount
No.
Public H & S 2014 CO's 3367-033 550910 140329013367EXP 3,757,566.25
Public H & S 2014 CO's 3367-033 550920 140329013367EXP 147,075.00
Total $3,904,641.25
❑ Certification Not Required
-P_
Director of,Fjp ngia 201
i es
Date: pp�� 11
i4V-00 /34/0