HomeMy WebLinkAboutM1982-0456 - 11/10/19820 MOTIONS 11/10/82 The Downtown Curb, Sidewalk and Driveway REnovatons project be accepted and final payment of $27,237.89 be made to Civil Constructors, Inc. for a total project cost of $244,518.89. A 24 day extension of time is recommended due to the extra work necessitated by Change Orders No. 1 and No. 2 which called for the construction of additional sidewalk, curb and guttaer replacement, an additional pebble walk and a retaining wall. THe project was funded with 1977 Street Bond funds. MICROFILNILU 082-0456' !vp� ,�.