MOTIONS 11/10/82
The Downtown Curb, Sidewalk and Driveway REnovatons project be
accepted and final payment of $27,237.89 be made to Civil
Constructors, Inc. for a total project cost of $244,518.89. A 24
day extension of time is recommended due to the extra work
necessitated by Change Orders No. 1 and No. 2 which called for
the construction of additional sidewalk, curb and guttaer
replacement, an additional pebble walk and a retaining wall. THe
project was funded with 1977 Street Bond funds.