Plans and specifications be approved for the construction of clarifier
modifications to the existing chlorine contact chamber, process piping and
electrical work and bids be received on April 6, 1983. Equipment for the
clarifier has been purchased by separate contract and scheduled to be
delivered in May, 1983. The construction of the clarifier and the
installation of the equipment, together with the improvements of the
aeration lagoon, would provide interim treatment of wastewater at the
Allison Plant during the construction of the permanent improvements which
are expected to begin during the latter part of the year. (Attachment #5)