Loading...
HomeMy WebLinkAboutM1983-0347 - 06/29/1983M MOTIONS - 6/29/83 6. The Convention Center Area Drainage Improvements project be accepted and final payment of $30,706.64 for a total of $102,859.11 be made to Goldston Corporation. A 23 day time extension is recommended due to the need to delay construction for Convention Center and Port activities. A 48" diameter storm sewer relief line was extended in the Convention Center Area by tapping into the 78" diameter conduit in Water Street. The project was funded from the interest earnings in the Convention Center Bond Fund. SEP 191984 MICROEILMEQ, 083 -0 3 4?