HomeMy WebLinkAboutM1983-0400 - 07/27/1983• MOTIONS - 7/27/83 The Brookhaven /Five Points Sanitary Sewer, Phase H project be accepted; final payment of $13,808.45, for a total of $91 ,698.50, be authorized to Cactus Utility Company; and the contractor be granted a three day time extension due to additional work authorized by change order. Gravity sanitary sewer lines were installed in Hearn Road, Perry Lane, Rushing Boulevard, and Emory Drive under this 1977 bond project. SEE i q 1984 MIOMW 083 -0400