HomeMy WebLinkAboutM1983-0529 - 10/19/1983•
MOTIONS - 10/19/83
1. The Commercial Ramp Expansion and Drainage Improvements project at the
Airport be accepted and final payment of $77,664.86 be authorized to
Heldenfels Brothers, Inc. It is also recommended that a 2 day time
extension be granted for extra work to supplement the 100 working days
allotted and that 10 days be charged as liquidated damages at $100 per day
for contract overruns. The total cost of this 1977 bond project, which is
supplemented by FAA grant funds, is $766,133.30.
M83 -0529