HomeMy WebLinkAboutM1983-0553 - 10/26/1983•
MOTIONS - 10/26/83
18. Accepting the Glenmore Street Improvement project from Ocean Drive to
Kentner Street and authorizing final payment of $11,118.46 to M & M
Construction Company. It is further recommended that the contractor be
granted a 39 day time extension due to delays encountered as a result of
utility adjustments. The total cost of this 1982 Voluntary Paving Street
project was $93,413.25.
r3 M83 -0553