MOTIONS - 1/18/84
11. The Washington Coles Area Street Improvements, Phase III project be
accepted and final payment of $73,501.68 be made to A. Ortiz Paving &
Construction Company. An 18 -day time extension is recommended for extra
work relating to change orders and delays resulting from utility
adjustments. The total cost of this 8th Year Community Development Block
Grant project was $188,718.15, which included street reconstruction of
Lake, Cabra and Chipito Streets and San Luis and Parker Alleys.