HomeMy WebLinkAboutM1984-0793 - 03/14/1984L -J 4 MOTIONS - 3/14/84 The Broadmoor Park No. 3 Storm Sewer Improvement project, which provided for storm sewer installation in Robin, Whittier and whiting Drives, be accepted and (a) the contractor, J. J. Fox Construction Company, be granted a 5 day time extension against a 28 day time overrun and 23 days be charged as liquidated damages at $55.00 per day, (b) $877.83 be retained pending disposition of a wage classification matter, and (c) payment of $5,527.75 be made to the contractor. The total work done on this 8th Year Community Development Block Grant project was $61,538.45. SEP' 9198-4 M84- 0793�.��'�'' ; -�