HomeMy WebLinkAboutM1984-0794 - 03/14/19840 0( MOTIONS - 3/14/84 10. The Woodlawn /Alameda Estates Street Improvement project be accepted and final payment of $58,170.15 be authorized to Maverick Construction Company. It is further recommended that the contractor be granted a 32 day time extension due to utility delays and adjustments and extra work added by change order. The total work done on this 1982 Voluntary Paving Bond project was $452,502.05. M84 -0794 MICRUHLiv Ll)