MOTIONS - 4/11/84
14. Accepting the Water System Improvement Project at the Holly Road Reservoir
and (a) authorizing a 69 -day time extension to supplement the allotted 30
working days for the project due to water line material delivery problems
and extra work added by change order and (b) authorizing final payment of
$19,722.90 to Delta Utilities. This $165,189 project, which is funded from
the Water Bond Fund, is one of the high priority projects approved upon
adoption of the Water Master Plan. The intent of the project is to divide
the City Distribution System into two (2) tier pressure system in order to
improve water pressure in the south part of the City as well as the Central
City area.