HomeMy WebLinkAboutM1984-0915 - 05/16/19840 0 MOTIONS - 5/16/84 The School Sidewalk Program, Phase I project be accepted with the provision that (a) the contractor be granted a 13 day extension to supplement 30 days previously authorized on this project, (b) the contractor be charged as liquidated damages for a 14 day overrun at a rate of $35 per day for a total of $490, and (c) remaining funds of $1,005.82 normally due the contractor be retained by the City pending settlement of a subcontractor dispute. This 1982 Bond project provided for the construction of sidewalks to serve Fannin Elementary, Martin Junior High and Miller High Schools. M84 -0915 P i cl 100 FROF1LMED