MOTIONS - 5/16/84
The School Sidewalk Program, Phase I project be accepted with the provision
that (a) the contractor be granted a 13 day extension to supplement 30 days
previously authorized on this project, (b) the contractor be charged as
liquidated damages for a 14 day overrun at a rate of $35 per day for a
total of $490, and (c) remaining funds of $1,005.82 normally due the
contractor be retained by the City pending settlement of a subcontractor
dispute. This 1982 Bond project provided for the construction of sidewalks
to serve Fannin Elementary, Martin Junior High and Miller High Schools.