Loading...
HomeMy WebLinkAboutM1984-0977 - 06/26/1984a 0 MOTIONS - 6/26/84 16. The Leopard /Baldwin Area Street Improvement Project be accepted and final payment of $59,961.23 be authorized to King Construction Company. That the contractor be granted an 11 -day time extension against a 20 -day contract time overrun due to delays caused by utility relocation work, and liquidated damages of $100 per day for the remaining 9 days be charged, for a total of $900. The total cost of this 1977 Voluntary Paving street reconstruction project was $430,943.84. M1GRb o6 M84 -0977 SEP 19 1984