MOTIONS - 6/26/84
16. The Leopard /Baldwin Area Street Improvement Project be accepted and final
payment of $59,961.23 be authorized to King Construction Company. That the
contractor be granted an 11 -day time extension against a 20 -day contract
time overrun due to delays caused by utility relocation work, and
liquidated damages of $100 per day for the remaining 9 days be charged, for
a total of $900. The total cost of this 1977 Voluntary Paving street
reconstruction project was $430,943.84.