HomeMy WebLinkAboutM1984-0986 - 07/03/1984MOTIONS - 7/3/84 7. The following actions be taken on the Pedestrian Crossing at Peoples Street and Shoreline Boulevard: a. The project be accepted and final payment of $11,378.22 be authorized to A. Ortiz Construction & Paving, Inc. b. The contractor be granted a 40 day time extension against a 49 day contract overrun due to delays in the delivery of materials, and liquidated damages of $55.00 per day for the remaining 9 days be charged for a total of $495.00. The total cost of this 7th Year Community Development Block Grant project was $69,460.03. M84 -0986 , , y