7. The following actions be taken on the Pedestrian Crossing at Peoples Street
and Shoreline Boulevard:
a. The project be accepted and final payment of $11,378.22 be authorized
to A. Ortiz Construction & Paving, Inc.
b. The contractor be granted a 40 day time extension against a 49 day
contract overrun due to delays in the delivery of materials, and
liquidated damages of $55.00 per day for the remaining 9 days be
charged for a total of $495.00.
The total cost of this 7th Year Community Development Block Grant project
was $69,460.03.