Loading...
HomeMy WebLinkAboutM1984-1006 - 07/17/19840 0 MOTIONS - 7/17/84 6. The Taxiway Fillets, Taxiway Extension and Runway 13 -31 Improvement project at Corpus Christi International Airport be accepted providing for the following actions: a. The contractor be granted a 30 day time extension for the runway opening phase of the project against a 45 day time overrun. b. Liquidated damages of $1,000 per day for 15 days for a total of $15,000 be deducted on the runway opening phase of the project. C. Remaining funds of $302,617.93 be authorized to Heldenfels Brothers, Inc. The Federal Aviation Administration's share on this 1982 bond project was 90% of the cost with the local share being 10 %. Total cost of construction is $2,105,297.98. M84 -1006,