HomeMy WebLinkAboutM1984-1006 - 07/17/19840 0
MOTIONS - 7/17/84
6. The Taxiway Fillets, Taxiway Extension and Runway 13 -31 Improvement project
at Corpus Christi International Airport be accepted providing for the
following actions:
a. The contractor be granted a 30 day time extension for the runway
opening phase of the project against a 45 day time overrun.
b. Liquidated damages of $1,000 per day for 15 days for a total of
$15,000 be deducted on the runway opening phase of the project.
C. Remaining funds of $302,617.93 be authorized to Heldenfels Brothers,
Inc.
The Federal Aviation Administration's share on this 1982 bond project was
90% of the cost with the local share being 10 %. Total cost of construction
is $2,105,297.98.
M84 -1006,