Loading...
HomeMy WebLinkAboutM1984-1024 - 07/24/19840 0 MOTIONS - 7/24/84 13. The following action be taken in connection with the Flynn Parkway Drainage Modification project: a. The project be accepted and final payment of $3,341.21 be authorized in the contractor, Boer -gear Constructors. b. The contractor be charged $3,115 as liquidated damages for 89 days at the rate of $35 per day. C. The contractor be charged $1,150.29 for repair of faulty irrigation piping which was installed and which had to be corrected by the Park Department. S &P 191984 M84 -1024 U90FILMED