HomeMy WebLinkAboutM1984-1044 - 08/07/19840
MOTIONS - 8/7/84
9. The following actions be taken in connection with the Interim Improvements
to the Allison Wastewater Treatment Plant:
a. The contract with the Goldston Corporation for construction of an
aerated lagoon be accepted and final payment of $26,243.50 be
authorized. Construction costs totalled $236,935.
b. The contract with the Goldston Corporation for construction of a
clarifier be accepted and final payment of $45,841.62 be authorized.
Liquidated damages in the amount of $4,000 were assessed due to the
contractor exceeding the 120 contract working days by 40 days.
Construction costs totalled $439,416.17 less liquidated damages.
Construction of the lagoon and clarifier provided for interim measures to
improve the quality of effluent until permanent expansion and improvements
are completed.
M84 - 1044