HomeMy WebLinkAboutM1984-1055 - 08/14/1984MOTIONS - 8/14/84 10. Authorizing the following actions on the Cole Street Improvement project: a. The project be accepted and final payment of $10,725.07 be authorized to Ibanez Construction Company, Inc. b. The contractor be granted a 10 day time extension against a 27 day time overrun due to additional work added by change order and delays caused by the relocation of utilities, and the contractor be charged liquidated damages for the remaining 17 days at a rate of $100 per day for a total of $1,700. The total cost of this 1982 Voluntary Paving Bond project, which provided for the reconstruction of Cole Street to residential street standards from Ocean Drive to Santa Fe Street, was $99,690.70. M84 -1055