HomeMy WebLinkAboutM1984-1065 - 08/21/1984MOTIONS - 8/21/84
8. Approving the following actions on the Spohn Hospital Area Street
Improvements, Phase II project:
a. The contractor's claim for additional compensation for the removal of
concrete base on Elizabeth Street between Santa Fe and Ocean Drive be
denied.
b. The contractor be granted a 33 day time extension due to utility
adjustments and delayed delivery of traffic signalization equipment to
supplement the 60 allotted working days, for a total allotted working
time of 93 days.
C. The project be accepted and remaining funds of $27,974.55 be
authorized to Howell Corporation & Isles Construction Company, a Joint
Venture.
This 8th Year Community Development Block Grant project provided for the
reconstruction of Elizabeth Street from Santa Fe to Ocean Drive and the
removal and replacement of driveways on Elizabeth Street from Santa Fe to
South Staples Street. The total work done on this project is $270,745.50.
M84 -1065