HomeMy WebLinkAboutM1984-1065 - 08/21/1984MOTIONS - 8/21/84 8. Approving the following actions on the Spohn Hospital Area Street Improvements, Phase II project: a. The contractor's claim for additional compensation for the removal of concrete base on Elizabeth Street between Santa Fe and Ocean Drive be denied. b. The contractor be granted a 33 day time extension due to utility adjustments and delayed delivery of traffic signalization equipment to supplement the 60 allotted working days, for a total allotted working time of 93 days. C. The project be accepted and remaining funds of $27,974.55 be authorized to Howell Corporation & Isles Construction Company, a Joint Venture. This 8th Year Community Development Block Grant project provided for the reconstruction of Elizabeth Street from Santa Fe to Ocean Drive and the removal and replacement of driveways on Elizabeth Street from Santa Fe to South Staples Street. The total work done on this project is $270,745.50. M84 -1065