HomeMy WebLinkAboutM1984-1101 - 09/11/1984• 0 MOTIONS - 9/11/84 The following actions be taken on the Miscellaneous Parking Lot Improvement project, which is under contract to Hannes Construction Co., Inc. 1. The contractor be assessed an $800 penalty for failure to meet the Minority Business Enterprise participation requirements of the contract. The contractor be granted a 7 day time extension to supplement 30 days allotted for the work due to delays involving laboratory testing problems beyond his control. 3. The project be accepted and final payment of $9,489.48 be authorized. This project consisted of the reworking and resurfacing of parking lots in Greenwood, Lakeview and West Guth Parks and also the Gas Division equipment yard. Total work done on this project, which is funded by Park Bond Funds and the Gas Division Operating Budget, is $102,094.75. (Attachment #5) M84 -1101 &G&1,@LibaL!) SEP 191984