MOTIONS - 9/11/84
The following actions be taken on the Miscellaneous Parking Lot Improvement
project, which is under contract to Hannes Construction Co., Inc.
1. The contractor be assessed an $800 penalty for failure to meet the
Minority Business Enterprise participation requirements of the
contract.
The contractor be granted a 7 day time extension to supplement 30 days
allotted for the work due to delays involving laboratory testing
problems beyond his control.
3. The project be accepted and final payment of $9,489.48 be authorized.
This project consisted of the reworking and resurfacing of parking lots in
Greenwood, Lakeview and West Guth Parks and also the Gas Division equipment
yard. Total work done on this project, which is funded by Park Bond Funds
and the Gas Division Operating Budget, is $102,094.75. (Attachment #5)