HomeMy WebLinkAboutM1984-1149 - 10/09/19849
MOTIONS - 10/9/84
The following actions be taken on the Blucher Park Area Relocation of
Utilities and Drainage Improvement project:
1. The contractor be granted a 15 -day time extension against a 23 -day
time overrun due to extra work added by change order and utility
delays, and he be charged liquidated damages for the remaining 8 days
at a rate of $100 per day for a total of $800.
2. The project be accepted, and final payment of $25,710.55 be authorized
to J. D. Construction and Refinery Maintenance, Inc.
The total cost of this 9th Year Community Development Block Grant Project
is $206,408.50.
M84 -1149