Loading...
HomeMy WebLinkAboutM1984-1149 - 10/09/19849 MOTIONS - 10/9/84 The following actions be taken on the Blucher Park Area Relocation of Utilities and Drainage Improvement project: 1. The contractor be granted a 15 -day time extension against a 23 -day time overrun due to extra work added by change order and utility delays, and he be charged liquidated damages for the remaining 8 days at a rate of $100 per day for a total of $800. 2. The project be accepted, and final payment of $25,710.55 be authorized to J. D. Construction and Refinery Maintenance, Inc. The total cost of this 9th Year Community Development Block Grant Project is $206,408.50. M84 -1149