MOTIONS - 10/9/84
10. The following actions be taken on the Animal Shelter Improvement project:
1) The contractor be granted a 47 -day time extension against a 94 -day
time overrun due to additional work added by change order, and the
fact the City had placed the building in use, and he be charged
liquidated damages for the remaining 47 days at a rate of $100 per
day for a total of $4700.
2) The project be accepted and final payment of $28,806.43 be authorized
to the contractor, American Roofing and Construction Company.
The total cost of this 1977 bond project was $288,739.30, which provided
for the construction of a new quarantine building and kennel building and
other items of work such as fencing and paving at the Animal Control
facilities on Navigation Boulevard.
M84 -1154