Loading...
HomeMy WebLinkAboutM1984-1154 - 10/09/19840 0 MOTIONS - 10/9/84 10. The following actions be taken on the Animal Shelter Improvement project: 1) The contractor be granted a 47 -day time extension against a 94 -day time overrun due to additional work added by change order, and the fact the City had placed the building in use, and he be charged liquidated damages for the remaining 47 days at a rate of $100 per day for a total of $4700. 2) The project be accepted and final payment of $28,806.43 be authorized to the contractor, American Roofing and Construction Company. The total cost of this 1977 bond project was $288,739.30, which provided for the construction of a new quarantine building and kennel building and other items of work such as fencing and paving at the Animal Control facilities on Navigation Boulevard. M84 -1154