12. The Main Drive Street and Drainage Improvement project be accepted and
final payment of $118,727.46 be authorized to Claude Chapman Construction
Co., Inc. It is further recommended that Change Order No. 3 in the amount
of $6,200 be approved which included the construction of a retaining wall
and handrail in front of a business at Main and Erne Drive to provide a
safe sidewalk section. The total cost of this 1977 Voluntary Paving
project, which was supplemented with Community Development Block Grant
funds, is $944,848.10.
M84 -1171